Professional Documents
Culture Documents
A. 8%
B. 7%
C. 5%
D. 9%
Solution:
A. 78
B. 65
C. 73
D. 63
MSE= (25+25+25+121+169)/5=73
3. The demand and forecast for five periods are shown in the table below. What will be
the tracking signal at the end of 2016?
A. +4.5
B. -3.5
C. -1.5
D. +2.5
Solution:
TS=(RSFE/MAD)
RSFE= (-10-5+15-10+15+30) = 35
MAD= 85/6 = 14.5
TS = 35/14.2 = 2.46
4. A steel company faced the following demand for its products during the past few
months; the company is using last year’s corresponding monthly sales as this year’s
forecast. What is the Mean absolute deviation (MAD) for the forecasted demand-
A. 1075
B. 1325
C. 1025
D. 1275
A. 675
B. 525
C. 765
D. 875
Solution:
On solving
a=375
b = 75
Now repair expenses for a 4-year-old truck
Y = 375+(75*4) =675
7. For a canteen, the actual demand for disposable cups was 500 units in January and 600
units in February. The forecast for the month of January was 400 units. The forecast for
the month of March considering the smoothing coefficient as 0.75 is___________.
(Round off to nearest integer value)
A. 569
B. 479
C. 453
D. 543
Solution:
Forecast for February
F2 = 0.75*500+(1-0.75)*400 = 475
Forecast for March
F3 = 0.75*600+(1-0.75)*475 = 568.75
8. The demand and forecast for February are 12000 and 10275, respectively. Using single
exponential smoothing method (smoothing coefficient= 0.25), forecast for the month
of March is:
A. 431
B. 9587
C. 10706
D. 11550
Solution:
Smoothing coefficient= 0.25
Forecast for March
FMar = 0.25*12000+(1-0.25)*10275 = 10706 (approx.)
9. In a forecasting model, at the end of period 13, the forecasted value for period 14 is 75.
Actual value in the periods 14 to 16 are constant at 100. If the assumed simple
exponential smoothing parameter is 0.5, then the MSE at the end of period 16 is:
A. 820.31
B. 273.44
C. 43.75
D. 14.58
Solution:
F15 = 0.5*100+(1-0.5) *75 = 87.5
F16 = 0.5*100+(1-0.5) *87.5 = 93.75
A. 269
B. 267
C. 277
D. 264
Solution:
F2015 = 0.5*280+(1-0.5) *260 = 270
F2016 = 0.5*268+(1-0.5) *270 = 269
F2017 = 0.5*259+(1-0.5) *269 = 264
F2018 = 0.5*270+(1-0.5) *264 = 267
F2019 = 0.5*287+(1-0.5) *267 = 277
NPTEL POM Assignment: Week 4 Solutions
1. The term ‘Setup Cost’ in EOQ analysis is analogous to-
A. Ordering Cost
B. Carrying Cost
C. Shortage Cost
D. Transportation Cost
2. In the EOQ model, the total inventory cost is minimized when:
A. Ordering cost is equal to holding cost per unit per time period
B. Ordering cost is greater than holding cost per unit per time period
C. Holding cost per unit per time period is zero
D. Ordering cost is zero
3. A particular item has a demand of 2500 units/year. The cost of one procurement is Rs
2500 and the holding cost per unit is Rs 200/year. The replacement is instantaneous,
and no shortages are allowed. What is the optimum number of orders /years?
A. 15
B. 20
C. 10
D. 30
Solution:
D = 2500 units/year
Co = 2500
Ch = 200/year
EOQ = SQRT ((2 *2500 *2500)/ 200) = 250
EOQ = 250 units/order
Optimum number of order = Demand/EOQ = 2500/250 = 10 orders/year
4. Which of the following statements is correct regarding inventory holding cost?
A. It decreases as the inventory holding period increases.
B. It increases as the inventory holding period increases.
C. It has no impact on the EOQ calculation.
D. It is constant regardless of the inventory holding period.
5. What are some limitations of the EOQ model?
A. It assumes constant demand and cost
B. It does not consider the effects of inflation.
C. It does not account for price changes.
D. All options are correct.
6. When the ordering cost is increased to 4 times, the EOQ will be-
A. Doubled
B. Halved
C. Tripled
D. Unchanged
Solution: EOQ is directly proportional to SQRT (ordering cost)
7. An item can be purchased for Rs.200. The ordering cost is Rs 400 and the inventory
carrying cost is 5% of the item cost per annum. If the annual demand is 8000 units,
the economic ordering quantity is____________-
A. 700
B. 800
C. 900
D. 1000
Solution:
D = 8000, Cu = Rs 200 per unit, Cc = 5% of Cu = 0.05 * 200 = Rs 10 per unit per
year, Co = Rs 400 per order, Q =?
So, EOQ = sqrt(2DCo/Cc) = sqrt ((2 *8000*400)/ 10) = 800 units.
8. A specific product has demand during lead time of 250 units, with a standard
deviation of 32 units. What safety stock (approximately) provides a 99% service
level? (At 99% service level, z= 2.80)
A. 75
B. 85
C. 90
D. 105
Solution:
Safety Stock = z*σdLT =2.8 *32 = 89.6 ~ 90
9. Demand for a water purifier is 15 units per day. The standard deviation of demand is
4 units per day, and the order lead time is 6 days. The service level is 95%. What
should the reorder point be? (At 95% service level, z= 1.64)
A. About 105
B. About 80
C. About 84
D. About 97
Solution:
Given: d=15, σ= 4, L= 6, z = 1.64
ROP = dL + SS = 15*6 + 4 * 1.64 = 96.56
10. A company uses 4,000 units of a component per year, with an ordering cost of Rs.
100 per order and a carrying cost of Rs. 5 per unit per year. What will be the EOQ and
total annual inventory cost?
A. 200 units, Rs. 10,000
B. 400 units, Rs. 11,000
C. 300 units, Rs. 11,000
D. 200 units, Rs. 13000
Solution:
D = 4000, Cc = Rs 5, Co = Rs 100
EOQ = sqrt(2DCo/Cc) = sqrt ((2 *4000*100)/ 5) = 400 units.
Total Cost= (D/EOQ)* Co + (EOQ/2)* Co = (4000/400)*100 + (400/2)*5 = 11000
NPTEL POMS Week 5 Solutions
1. The manager at a retail store, has to decide on the number of items to purchase for the
upcoming season. Each item costs Rs. 25 and is sold for Rs. 75. Any unsold item at
the end of the season is disposed of for Rs. 12. The inventory holding cost for the
season is Rs. 5. What is the cost of understocking per item (in Rs.) for this manager?
A. 100
B. 50
C. 42
D. 18
2. The manager at a retail store, has to decide on the number of items to purchase for the
upcoming season. Each item costs Rs. 25 and is sold for Rs. 75. Any unsold item at
the end of the season is disposed of for Rs. 12. The inventory holding cost for the
season is Rs. 5. What is the cost of overstocking per item (in Rs.) for this manager?
A. 37
B. 50
C. 42
D. 18
Solution:
s = 12 – 5 = 7 Rs.; Cu = p – c = 75 - 25 = 50 Rs.; Co = c – s = 25 - 7 = 18 Rs.
3. The manager at a retail store, has to decide on the number of items to purchase for the
upcoming season. Each item costs Rs. 25 and is sold for Rs. 75. Any unsold item at
the end of the season is disposed of for Rs. 12. The inventory holding cost for the
season is Rs. 5. Determine the optimal stocking level for this manager:
A. 0.58
B. 0.63
C. 0.73
D. 0.88
Solution: CSL = Cu/ Cu+Co = 50/(50+18) = 0.73
4. What is a two-bin system?
A. A system in which orders are placed when only one complete bin of stock is
remaining.
B. A system in which suppliers deliver two bins at a time.
C. A system in which everything is split between two storage bins.
D. A system in which two full bins of an item are always held in stock.
5. VED analysis of inventory management stands for____________.
A. Vital-essential-desirable
B. Valuable-easy-disposable
C. Very-easily-delivered.
D. Valuable-effective-dispensable
6. The ABC analysis classifies items based on their-
A. Lead Time
B. Demand Variability
C. Unit Cost
D. Storage Requirements
7. The following table is an example of-
Week 1 Week 2 Week 3 Week 4
Clothes dryer 300 80 120 100
Upright freezer 200 500
Clothes washer 200 200
A. Aggregate plan
B. Master Production Schedule
C. Load report
D. Inventory record
8. Product A is made of three units of B. B is made of one units of C and four units of D.
D is made of two unit of E and three units of F. If 45 A are required, how many units
of ‘E’ component are needed (without lead time consideration)?
A. 540
B. 830
C. 1620
D. 1080
Solution:
A (1)
For 1 unit of A, requirement of E
E (2) F (3)
9. Each M requires 4 of component N; each N requires 3 of part O. The lead time for the
assembly of M is 3 weeks. The lead time for the manufacture of N is 4 weeks. The
lead time for the procurement of O is 3 weeks. The cumulative lead time for M is
_______ weeks).
A. 10
B. 12
C. 36
D. 16
Solution: Cumulative lead time = 3+4+3 = 10 weeks
10. _______________contains a listing of all of the assemblies, subassemblies, parts, part
costs, and raw materials that are needed to produce one unit of a finished product.
A. Forecast Sheet
B. Inventory Record
C. Bill of Materials
D. Purchase Order
NPTEL POM Week 6 Solutions
1. Consider the following data for an MRP lot sizing problem-
Item cost per unit Rs. 100
Carrying cost 5% of Unit cost/ per week
Set up cost Rs. 500 per set up
Week 1 2 3 4 5 6 7 8 9 10
Net 50 68 42 - 33 30 32 - 30 35
Requiremen
t
What is lot size if we follow the EOQ method?
A. 80
B. 85
C. 70
D. 90
Solution:
Ordering cost = Rs. 500
Carrying cost = 0.05 *100 = Rs 5
Demand = 320
Avg. Demand = 320/10 = 32
EOQ = SQRT (2*32*500)/5) = SQRT (6400) = 80
So, LOT SIZE = 80
2. In Material requirement planning, if the inventory holding cost is very high and the
setup cost is zero, which one of the following lot-sizing approaches should be used?
A. Economic Order Quantity
B. Lot-for-Lot
C. Base Stock Level
D. Fixed period Quantity
3. Consider the following data for an MRP lot sizing problem-
Item cost per unit Rs. 100
Carrying cost 5% of unit cost/ per week
Set up cost Rs. 500 per set up
Week 1 2 3 4 5 6 7 8 9 10
Net 50 68 42 - 33 30 32 - 30 35
Requiremen
t
After how many weeks an order should be placed as per the POQ method? (Assume
52 weeks in a year)
A. 5
B. 7
C. 6
D. 2
Solution:
Ordering cost = Rs. 500
Carrying cost = 0.05 *100 = Rs 5
Demand = 320
Avg. Demand = 320/10 = 32
EOQ = SQRT (2*32*500)/5) = SQRT (6400) = 80
Demand for 10 weeks = 320
Demand for 1 week = 32
Demand for 52 weeks = 32 * 52 = 1664
Annual Demand = 1664
Number of orders = 1664/80 = 21 orders
Period = 52/ 21 = 2.47 = 2 weeks (approx.)
4. In order to use the "level capacity strategy," variations in demand are met by-
A. Varying output during the regular time without changing employment levels
B. Varying output during regular time by changing employment levels
C. Using a combination of inventories, overtime, part-time, and back orders
D. Price adjustments
a) 72000
b) 73400
c) 74000
d) 70000
Solution:
Output
Regular 1200 1200 1200 1200 1200 1200 7200
Inventory
Beginning 0 300 300 100 0 0
Ending 300 300 100 0 0 0
Average 150 300 200 50 0 0
Backorder 100
Cost
Regular 12000 12000 12000 12000 12000 12000
Inventory Cost 300 600 400 100 0 0
Back order 600
Total 12300 12600 12400 12100 12600 12000 74000
Q4: Consider the following forecast for 6 consecutive days.
a) Day 2
b) Day 3
c) Day 4
d) Day 5
Solution:
Output
Regular 1200 1200 1200 1200 1200 1200 7200
Inventory
Beginning 0 300 300 100 0 0
Ending 300 300 100 0 0 0
Average 150 300 200 50 0 0
Backorder 100
Cost
Regular 12000 12000 12000 12000 12000 12000
Inventory Cost 300 600 400 100 0 0
Back order 600
Total 12300 12600 12400 12100 12600 12000 74000
There is a backorder of 100 units on Day 5
a) 4500
b) 7200
c) 3000
d) 11700
Solution:
6 Backorder cost
20 No. of workers
a) Day 4
b) Day 3
c) Day 4 and Day 5
d) Day 6
Solution:
6 Backorder cost
20 No. of workers
Q7: Considering the level and chase plans given in the previous questions which of the following is
not true?
Q8: Which of the following is not the correct consideration for optimizing the total cost of a
production plan:
a) Serviceability
b) Special features
c) Aesthetics
d) Price
Note: Questions 5, 6 and 7 had some missing information (highlighted in red), the marks for the
questions will be compensated in the final evaluation.
Week 8
Q1: A higher level of prevention costs generally leads to:
Q3: Shigeo Shingo, known for the "SMED" system, focused on:
Q4: What is the difference between variable and attribute control charts?
a) Variable charts use data that can be counted, while attribute charts use data that can be
measured.
b) Variable charts use data that can be measured numerically, while attribute charts use data
that can be categorized.
c) Variable charts are used for continuous data, while attribute charts are used for discrete
data.
d) There is no significant difference between variable and attribute control charts.
Q5: Following are the 5 samples taken, each with 5 observations for the time taken in the machining
process. The process is known to have a standard deviation of 1 minute.
Observation Sample
1 20 23 19 21 23
2 18 22 21 18 24
3 21 21 23 22 19
4 20 24 18 23 18
5 18 19 18 18 24
Which of the following is not true:
4. As the average of individual samples are between the UCL and LCL the process is said to be within
control
Q6: Following are the 5 samples taken, each with 5 observations for the time taken in the machining
process.
Observation Sample
1 20 23 19 21 23
2 18 22 21 18 24
3 21 21 23 22 19
4 20 24 18 23 18
5 18 19 18 18 24
What is the value of R-bar
a) 2
b) 4.8
c) 5.2
d) 4.3
Solution
Observation Sample
1 20 23 19 21 23
2 18 22 21 18 24
3 21 21 23 22 19
4 20 24 18 23 18
5 18 19 18 18 24
Sample
Avg 19.4 21.8 19.8 20.4 21.6
Max 21 24 23 23 24
Min 18 19 18 18 18
Max-Min 3 5 5 5 6
Average 4.8
1 100 20
2 100 5
3 100 8
4 100 11
5 100 16
Q8: Which chart can plot the defective pieces (n number) in the output of any process?
Q10: Which of the following charts is suitable for plotting the no. of cracks on a floor:
Q2. Data of printed sheets are taken at regular intervals using c-chart in a company is as follows:
Number of
Sample No.
defects
1 11
2 9
3 7
4 9
5 10
6 22
7 7
8 10
9 10
10 6
Considering a control chart using 3 standard deviation control limits what will be upper control limits
for the process:
a) 21.1
b) 24.4
c) 22.0
d) None of the above
Solution:
𝑐̅ = 10.1
Q3: Acceptance sampling is suitable for all the following cases, except:
a) Where, destructive inspection is required
b) Where, population is too large
c) Where, rate of production is high
d) Where, products of different specifications are being made.
Q4. A manufacturer compares the filling volumes of two different machines using separate
histograms. Machine A's histogram has a larger standard deviation than Machine B's histogram.
What can you conclude?
Solution: Double sampling is done if the defects are found to be between the lower and upper limit
and the summation of the defects is done and compared with C3 if =it happens to be lower that C3
than the lot is accepted. Thus the value of the C3 should be more than upper limit.
Q7: A sampling plan with a low acceptance number (e.g., 0) and a high sample size is likely to have
an OC curve that:
Q8. A process manufactures bolts with a USL of 12.5 cm and an LSL of 11.5 cm. The sample data
shows a mean length of 12.2 cm and a standard deviation of 0.2 cm. What can you conclude about
the process capability based on the Cp value?
Solution:
12.5 − 11.5
𝐶𝑝 = = 0.8333 (𝑁𝑜𝑡 𝑐𝑎𝑝𝑎𝑏𝑙𝑒)
3 × 0.2
Based on the Cp value the process is not capable.
Since the mean of the observed sample not centered around the specification limits, even if we
consider Cpk value
12.5 − 12.2
𝐶𝑝𝑘 (𝑓𝑟𝑜𝑚 𝑈𝑆𝐿) = = 0.5 (𝑁𝑜𝑡 𝑐𝑎𝑝𝑎𝑏𝑙𝑒)
3 × 0.2
The index of 0.2 represents that the process needs significant improvement.
a) 2000
b) 6000
c) 1000
Solution:
Q2 Consider a case of a high rework rate in the shirt stitching department, leading to delays and
production cost increase. Map the following activities with their corresponding DMAIC phases
1. Monitor the effectiveness of solutions through rework rate measurement. (D) Define
5. Track daily rework rates for different shirt styles. (C) Control
Q3. A service industry project focuses on reducing the cycle time of a process, does it directly
contribute to the Six Sigma sigma level (DPMO)?
Q5: A widely used service quality model is SERVQUAL. What do the five dimensions of SERVQUAL
represent?
Q8. A hospital needs to arrange its departments for optimal patient flow and staff collaboration.
What layout approach would be most appropriate?
A. Product layout
B. Fixed-position layout
C. Process layout
D. Cellular layout
Q9: For a panel distributor the average daily demand is 4.5 panels per day and the shifts are 7.5
hours long. The total standard time required for all the tasks is 35025.1 seconds what is the cycle
time in minutes:
a) 450
b) 166.6
c) 100
d) None of the above
Solution:
Cycle time = Operating time per day/ Desired output rate = 450 Minutes/4.5 panels = 100 minute
Q10: A line with 3 tasks has the following processing times and assigned workstations:
Task A: 4 minutes (Station 1)
What is the idle time at Station 2 if the line operates at a cycle time of 6 minutes?
A. 0 minutes
B. 1 minute
C. 2 minutes
D. 4 minutes
A. At the beginning
B. Towards the end
C. on the Critical Path
D. not on the critical path
A. 15
B. 17
C. 18
D. None of the above
Solution:
Possible paths:
ACGH – 6+8+5+3 = 22
ADH – 6+4+3 = 13
AEFH – 6+3+7+3 = 19
A. B-F-H
B. A-E-F-H
C. A-D-H
D. A-C-G-H
Solution:
Possible paths:
ACGH – 6+8+5+3 = 22
ADH – 6+4+3 = 13
AEFH – 6+3+7+3 = 19
Considering the time duration to be in days, what is the latest possible day to start activity G
A. 10
B. 11
C. 13
D. 14
Solution:
Possible paths:
ACGH – 6+8+5+3 = 22
ADH – 6+4+3 = 13
AEFH – 6+3+7+3 = 19
Since activity G is on the critical path, the latest and earliest date to start G will be 14th
Optimistic Pessimistic
Activity Precedence estimate Most Likely estimate
A - 5 6 10
B - 4 5 8
C A 6 8 12
D A 3 4 6
E A 2 3 5
F B,E 3 7 12
G C 2 5 8
H G,D,F 2 3 5
Which of the following is the expected critical path?
A. A-C-G-H
B. A-D-H
C. A-E-F-H
D. B-F-H
Solution:
Estimated
Most Likely time
Activity Precedence Optimistic est. (o) Pessimistic est. (p)
(m)
e=(o+4*m+p)/6
A - 5 6 10 6.5
B - 4 5 8 5.333333333
C A 6 8 12 8.333333333
D A 3 4 6 4.166666667
E A 2 3 5 3.166666667
F B,E 3 7 12 7.166666667
G C 2 5 8 5
H G,D,F 2 3 5 3.166666667
Path Time
ACGH 23.00
ADH 13.83
AEFH 20.00
BFH 15.67
As the estimated time is maximum for path ACGH, that is the critical path in this problem.
Q6. What is the standard deviation of the critical path in the above problem?
A. 1.85
B. 1.09
C. 1.71
D. None of the above
Solution:
Q7. What is the probability that the project will be completed within 25 days?
A. 0.8413
B. 0.8781
C. 0.2023
D. 0.7022
Solution: For calculating the probability for the project to be completed within 25 days
25−23
𝑧= = 1.1655
1.7159
Q8. There are 3 components in series being used in a machine with respective reliability of 80%,
95%, and 90%. If another component for finishing is being added in the series with reliability of
99%. The reliability of the system will
A. Increase
B. Decrease
C. Remain unchanged.
D. Cannot be determined.
Solution: Adding a new component in the series will reduce the reliability as the initial reliability
will be multiplied with the reliability of the newly added component.
Q9. A machine being used in the system takes on average 2 hours of maintenance time for every
30 hours of working, what is the total availability of the machine?
A. 1
B. .98
C. .9375
D. 1.067
𝑀𝑇𝐵𝐹 30
Solution: 𝐴𝑣𝑎𝑖𝑙𝑎𝑏𝑖𝑙𝑖𝑡𝑦 = = = 0.9375
𝑀𝑇𝐵𝐹+𝑀𝑇𝑇𝑅 30+2
Q10. An asset that has been operational for 4,000 hours in a year. For that year, that asset broke
down eight times. And total time spent in repair was 200 hours, what were the MTTR and MTBF
respectively?
A. 25,500
B. 50,250
C. 30, 475
D. 25,525