LEVELLING RESOURCES

Primavera P6 Professional has the capability to level resource allocations when they become
overloaded across a number of activities. This can be a particularly valuable feature when you
have a resource constrained project that includes a scarce resource whose skills cannot easily be
hired in to overcome shortfalls.

 Firstly, define the max units per time for the resource

 Open the activity window