Professional Documents
Culture Documents
SEMESTER: II
TITLE OF THE PAPER: QUANTITATIVE TECHNIQUES
SUBJECT CODE: 21CMBA21
SECTION A – UNIT I
SECTION A – UNIT II
SECTION A – UNIT IV
SECTION A – UNIT V
SECTION B – UNIT I
8X1 + 8X2 ≤ 80
X1, X2 ≥ 0
Subject to X1 + X2 ≥ 8
6X1 + X2 ≥ 12
X1, X2 ≥ 0
78. Assess and Solve the following LPP problem using graphical method
X1 + X2 ≤ 20
X1, X2 ≥ 0
3X1 + 2X2 ≤ 6
2X1 + 3X2 ≤ 6
X1, X2 ≥ 0
X1 + X2 ≤ 40
2X1 + X2 ≤ 60
X1, X2 ≥ 0
5X1 + X2 ≤ 100
X1 + X2 ≤ 50
X1, X2 ≥ 0
SECTION B – UNIT II
86. Calculate basic feasible solution of a transportation problem using North West Corner
rule.
Destination
D1 D2 D3 Supply
Source
S1 2 7 4 5
S2 3 3 1 8
S3 5 4 7 7
S4 1 6 2 14
Demand 7 9 18 34
87. Find the initial basic feasible solution of a transportation problem using Least cost
method
Destination
D1 D2 D3 D4 Supply
Source
S1 1 2 3 4 6
S2 4 3 2 0 8
S3 0 2 2 1 10
Demand 4 6 8 6 24
Destination
D1 D2 D3 Supply
Source
S1 8 7 3 60
S2 3 8 9 70
S3 11 3 5 80
Demand 50 80 80 210
89. By using VAM (Vogel’s Approximation Method), Estimate the initial basic feasible
solution.
Destination
D1 D2 D3 D4 Supply
Source
S1 11 13 17 14 250
S2 16 18 14 10 300
S3 21 24 13 10 400
Demand 200 225 275 250 950
90. Determine the initial basic feasible solution of a transportation problem using VAM
Destination
D1 D2 D3 D4 Supply
Source
S1 3 3 4 1 100
S2 4 2 4 2 125
S3 1 5 3 2 75
Demand 120 80 75 25 300
91. By using VAM (Vogel’s Approximation Method), Assess and calculate the initial basic
feasible solution.
Destination
D1 D2 D3 D4 Supply
Source
S1 15 1 42 33 23
S2 80 42 26 81 44
S3 90 40 66 60 33
Demand 23 31 16 30 100
92. Estimate the transportation problem initial basic solution by North West Corner Rule
method
Destination
D1 D2 D3 Supply
Source
S1 2 2 3 10
S2 4 1 2 15
S3 1 3 1 40
Demand 20 15 30 65
93. Calculate the transportation problem initial basic solution the following transportation
problem using NWCR method
Destination
D1 D2 D3 D4 Supply
Source
S1 1 5 3 3 34
S2 3 3 1 2 15
S3 0 2 2 3 12
S4 2 7 2 4 19
Demand 21 25 17 17 80
94. Obtain the initial basic feasible solution of a transportation problem using Vogel’s
Approximation method.
Destination
D1 D2 D3 Supply
Source
S1 10 9 8 8
S2 10 7 10 7
S3 11 9 7 9
S4 12 14 10 4
Demand 10 10 8 28
95. Find the minimum cost solution for the following transportation problem using VAM.
Destination
D1 D2 D3 Supply
Source
S1 16 19 12 14
S2 22 13 19 16
S3 14 28 8 12
Demand 10 15 17 42
96. The following table gives the activities in a construction project and other relevant
information
98. The following table gives the activities of a project and their duration in days
100. The utility data for a network is given below. Use CPM to draw network, critical path,
duration and float.
102. The activities of a project have the following PERT time estimates
Activity O M P
1-2 3 6 15
1-6 2 5 14
2-3 6 12 30
2-4 2 5 8
3-5 5 11 17
4-5 3 6 15
5-8 1 4 7
6-7 3 9 27
7-8 4 19 28
Draw the network diagram, estimate the critical path, project completion time ,
variance and standard deviation
103. The following table gives the activities of a small project. Draw a network using
PERT, calculate critical path, project completion time and variance & standard deviation.
Activity O M P
1-2 1 4 7
1-3 5 10 17
2-4 3 3 3
2-6 1 4 7
3-4 8 15 26
3-5 2 4 8
4-5 5 5 5
5-6 2 5 8
104. The following table gives data on estimates optimistic, most likely and pessimistic
duration in weeks for a project using PERT.
Activity O M P
1-2 1 1 7
1-3 1 4 7
1-4 2 2 8
2-5 1 1 1
3-5 2 5 14
4-5 2 5 8
5-6 3 6 15
Draw the project network and find the critical path, expected project duration and
variance & standard deviation.
105. The following indicates the details of the activities of a project. The duration are in
days. (PERT)
Activity O M P
1-2 4 5 6
1-3 8 9 11
1-4 6 8 12
2-4 2 4 6
2-5 3 4 6
3-4 2 3 4
4-5 3 5 8
(a) Draw project network (b) Find critical path (c) Find project completion time and
variance & standard deviation.
SECTION B – UNIT IV
106. A machine costs Rs. 10,000. Its operating cost (Running cost) and resale values are
given below.
Year 1 2 3 4 5 6 7 8
Operating 1000 1200 1400 1700 2000 2500 3000 3500
maintenance
cost
107. A machine owner finds from his past records that the costs per year of maintaining a
machine whose costs is Rs. 6000 are given below
Year 1 2 3 4 5 6 7 8
Operating 1000 1200 1400 1800 2300 2800 3400 4000
maintenance
cost
Resale 3000 1500 750 375 200 200 200 200
value
Determine at what are a replacement is due?
108. The following table gives the running costs per year and the resale price of a certain
equipment whose costs is Rs. 5000
`Year 1 2 3 4 5 6 7 8
Operating 1500 1600 1800 2100 2500 2900 3400 4400
maintenance
cost
Resale value 3500 2500 1700 1200 800 500 500 500
109. The following table gives the running cost per year and resale price of certain
machine whose costs is Rs. 50000.
`Year 1 2 3 4 5 6 7 8
Operating 15000 16000 18000 21000 25000 29000 43000 40000
maintenance
cost
Resale value 35000 25000 17000 12000 8000 5000 5000 5000
Player B
12 1 30 -10
20 3 10 5
Player A -5 -2 25 0
15 -4 10 6
111. Discuss the solution of the following game with the payoff.
Player B
10 4 11 7
8 7 9 20
Player A
9 5 -2 12
Player B
0.4 0.5 0.9 0.3
0.8 0.4 0.3 0.7
Player A 0.7 0.6 0.8 0.9
0.7 0.2 0.4 0.6
113. Explain the maximin principle for game with the following payoff
Player B
20 12 15
Player A 11 10 12
15 11 10
114. Discuss the solution of the following game
Player B
8 2 9 5
6 5 7 18
Player A
7 3 -4 10
Player B
-2 0 0 5 3
3 2 1 2 2
Player A -4 -3 0 -2 6
5 3 -4 2 -6
SECTION B – UNIT V
116. The automobile company manufactures around 150 scooters. The daily production
varies from 146 to 154 depending upon the availability of raw materials and other
working conditions.
The finished mopeds are transported in a specially arranged lorry accommodating 200
mopeds. Using the following 15 random numbers 82, 89, 78, 24, 53, 61, 18, 45, 04,
23, 50, 77, 27, 54, 10. Simulate the process to find out
a. What will be the average number of mopeds waiting in the factory?
b. What will be the average number of empty spaces in the lorry?
118. The automobile company manufactures around 100 cars. The production is more
accurately described by the probability distribution given below.
The finished cars are transported in a specially arranged lorry accommodating 101
cars. (a) What will be the average number of cars waiting in the factory?
(b) What will be the average number of empty spaces in the lorry?
Using the following random numbers 68, 75, 29, 94, 08, 74, 36, 47, 31, 78, 38,
59, 91, 06, 31. Simulate the process.
119. Find the optimal solution for the assignment problem using Hungarian method with
the following cost matrix
AREA
W X Y Z
A 11 17 8 16
B 9 7 12 6
SALESMAN
C 13 16 15 12
D 14 10 12 11
120. Solve the following assignment problem using Hungarian method. The matrix entries
represent the processing time in hours.
OPERATOR
A B C D
1 5 3 2 8
2 7 9 2 6
JOB
3 6 4 5 7
4 5 7 7 8
121. Use Hungarian method to solve the assignment problem of four salesmen A, B, C and
D available to handle four counters W, X, Y and Z. Each salesman can handle any
counter. The matrix times are the service time in hours. Find the minimum total service
time.
SALESMEN
A B C D
W 41 72 39 52
X 22 29 49 65
COUNTERS
Y 27 39 60 51
Z 45 50 48 52
122. Solve the following assignment problem using Hungarian method. The matrix entries
represent the processing times in hours.
OPERATOR
1 2 3 4 5
JOB 1 9 11 14 11 7
2 6 15 13 13 10
3 12 13 6 8 8
4 11 9 10 12 9
5 7 12 14 10 14
123. Assign the four tasks to four operators. Solve the following assignment problem using
Hungarian method.
OPERATORS
1 2 3 4
A 20 28 19 13
B 15 30 31 28
TASKS
C 40 21 20 17
D 21 28 26 12
124. Solve the following assignment problem shown in Table using Hungarian method. The
matrix entries are processing time of each man in hours
MEN
1 2 3 4 5
1 20 15 18 20 25
2 18 20 12 14 15
JOB 3 21 23 25 27 25
4 17 18 21 23 20
5 18 18 16 19 20
125. Assign the four person to four jobs. Solve the following assignment problem using
Hungarian method.
JOB
1 2 3 4
A 20 25 22 28
B 15 18 23 17
PERSON
C 19 17 21 24
D 25 23 24 24
SECTION C
126. Find the initial basic feasible solution of a transportation problem using (a) North
West Corner Rule (b) Least Cost method (c) VAM
Destination
D1 D2 D3 D4 Supply
Source
S1 6 4 1 5 14
S2 8 9 2 7 16
S3 4 3 6 2 5
Demand 6 10 15 4 35
127. Determine the initial basic feasible solution of a transportation problem using (a)
North West Corner Rule (b) Least Cost method (c) VAM
Destination
D1 D2 D3 Supply
Source
S1 2 7 4 5
S2 3 3 1 8
S3 5 4 7 7
S4 1 6 2 14
Demand 7 9 18 34
128. Solve the following transportation problem using (a) North West Corner Rule (b)
Least Cost method (c) VAM
Destination
D1 D2 D3 D4 Supply
Source
S1 48 60 56 58 140
S2 45 55 53 60 260
S3 50 65 60 62 360
S4 52 64 55 61 220
Demand 200 320 250 210 980
129. Estimate initial basic solution by solving the following transportation problem using
(a) North West Corner Rule (b) Least Cost method (c) VAM
Destination
D1 D2 D3 D4 Supply
Source
S1 190 300 500 100 70
S2 700 300 400 600 90
S3 400 100 600 200 180
Demand 50 80 70 140 340
130. A project has the following characteristic and time estimate – Optimistic time (O),
Most likely time (M) and Pessimistic time (P). Construct a PERT network to find the
critical path, project completion time and the variance & standard deviation.
Activity O M P
1-2 1 5 1.5
2-3 1 3 2
2-4 1 5 3
3-5 3 5 4
4-5 2 4 3
4-6 3 7 5
5-7 4 6 5
6-7 6 8 7
7-8 2 6 4
7-9 4 8 6
8 – 10 1 3 2
9 - 10 3 7 5
131. Compute the project network, critical path and variance & standard deviation using
PERT
132. The following indicates the details of a project and the duration are in days. (a) Draw
the project network (b) Find the critical path (c) Calculate project completion time and
variance & standard deviation using PERT
Activity O M P
1-2 2 5 8
1–4 4 19 28
1-5 5 11 17
2-3 3 9 27
2-6 3 6 15
3-6 2 5 14
4-6 3 6 15
5-7 1 4 7
5-8 2 5 14
6-8 6 12 30
7-8 2 5 8
Use PERT to determine critical path, project completion time and variance & standard
deviation.
134. Consider the following project whose activities along with PERT time estimates, the
optimistic time (O), most likely time (M) and pessimistic time (P) are given as follows
135. A truck owner finds from his past records that the maintenance costs per year of a
truck whose purchase price is Rs. 8000 are as given below.
Year 1 2 3 4 5 6 7 8
Operating 1000 1300 1700 2200 2900 3800 4800 6000
maintenance
cost
Resale 4000 2000 1200 600 500 400 400 400
value
Determine the time at which it is profitable to replace the truck.
136. A machine costs Rs. 6000. The running cost and the resale value (salvage value) at
the end of the year is given below.
Year 1 2 3 4 5 6 7
Operating 1200 1400 1600 1800 2000 2400 3000
maintenance
cost
Resale value 4000 2666 2000 1500 1000 600 600
137. For the following payoff, find the value of the game
Player B
3 -1 4 6 7
-1 8 2 4 12
Player A 16 8 6 14 12
1 11 -4 2 1
138. Using the minimax criterion find the optimal strategies for the players in the
following game.
Player B
8 10 13 16 9
7 12 6 15 10
Player A 9 18 9 13 25
4 9 8 20 6
139. ABC Co. Like to launch a project involving various activities as follows. Construct a
project network using PERT, critical path, project completion time and variance.
Activity O M P
1-2 1 8 10
1-3 18 20 22
1-4 26 33 40
2-5 16 18 20
2-6 15 20 25
3-6 6 9 12
4-7 7 10 12
5-7 7 8 9
6-7 3 4 5
-----------------------