Professional Documents
Culture Documents
1-S2.0-S0886779821004995-Main 1
1-S2.0-S0886779821004995-Main 1
A B S T R A C T
The Hong Kong Zhuhai Macao Bridge (HZMB) link is currently one of the largest fixed links ever realised. The link comprises various bridges, causeways, artificial
islands and tunnels and has a total length of more than 55 km with an investment of about RMB 120billion (approx. €15 billion). The Link accommodates a dual
carriageway with three traffic lanes in each direction.
The construction of the Link started at the end of 2010 and was opened to traffic in October 2018. The HZMB Link is internationally regarded as one of the most
challenging sea crossing projects in China and a demonstration of China’s comprehensive breakthrough in technology, scientific research and other related fields.
The offshore part of the HZMB Link, crossing the Pearl River Estuary involves one of the world’s longest and deepest immersed tunnels. The tunnel was designed
and constructed to meet state-of-the-art requirements and challenging structural, geotechnical and marine/offshore conditions. The HZMB tunnel won the ITA
Tunnelling Award Major Project of the Year 2018.
This paper presents the project from the Client perspective. The paper will give a general introduction of the project, will provide information regarding the
challenging environment in which the tunnel had to be realized and the high demanding design criteria that were applicable. Furthermore, the evaluation of the
various technical options will be discussed, ultimately leading to the selection of the immersed tunnel option. The paper will also look into the background of
selecting the Design & Build contract approach for this project and the experiences that were built up using this type of contract, new to China on this scale. Finally,
the paper introduces how operation and maintenance of the tunnel is planned and executed so as to guarantee the 120-year design lifetime. In Ref. (The Islands and
Tunnel Project of HZM Link et al., 2022) more details of the project are discussed from the D&B contractors’ perspective.
1. Introduction (yellow dashed line in Fig. 3). The transition from the bridges to the
tunnel is realised with artificial islands with a length of 625 m each.
1.1. Brief project description (Quanke et al., 2011; de Wit, 2011; Ying
Li and (Hans) de Wit,2017; de Wit and Kuiper, 2018)
1.2. The role in Great Bay area
The Main Bridge Project (Fig. 1) covers the main offshore section of
the HZMB link of some 30 km, crossing the Pearl River Estuary from the The realization of the Hong Kong Zhuhai Macao Bridge was a major
Hong Kong border at the eastern side to the Zhuhai/Macao Border decision made by the central government to support and stimulate the
Control Facility Island at the western side. economic and social development and integration of Hong Kong, Macao
The Link accommodates a dual carriageway with three traffic lanes and the Pearl River Delta region. It is an essential link in the main road
in each direction. To allow the passage of sea going vessels, major cable network connecting the big urban areas around Guangzhou, Shenzhen,
stayed bridges crossing different navigation channels are included in the Hong Kong, Macao and Zhuhai (Fig. 4).
link (Fig. 2). The project was a major achievement of close cooperation between
The crossing of the main shipping channels giving access to the port Guangdong, Hong Kong and Macao under the “one country, two sys
areas of Guangzhou and Hong Kong and located at the eastern side of the tems” principle. The bridge link connects the east and west shores of the
Pearl River Estuary, close to Hong Kong International Airport, is realised Great Bay area of Guangdong, Hong Kong and Macao and is the Golden
using an approx. 6.7 km tunnel of which some 5.664 km is immersed Link of the Bay Area in the new era. It will promote and stimulate an
effective connection of transport infrastructure, close exchanges and
* Corresponding author.
E-mail address: h.dewit@tec-tunnel.com (H. de Wit).
https://doi.org/10.1016/j.tust.2021.104308
Received 30 November 2021; Accepted 1 December 2021
Available online 21 December 2021
0886-7798/© 2021 Elsevier Ltd. All rights reserved.
S. Quanke et al. Tunnelling and Underground Space Technology incorporating Trenchless Technology Research 121 (2022) 104308
cooperation between the mainland and Hong Kong and Macao, further
strengthen the position of Hong Kong as a trade centre, stimulate the
development of Macao’s tourism, and promote the development of the
Great Bay area as a whole.
As a leading project in the Great Bay area, the Hong Kong Zhuhai
Macao Bridge project has been under preparation and construction for
more than ten years. Hong Kong, Macao and Zhuhai City of Guangdong
Province, the main stakeholders of the project, are part of China.
However, due to historical reasons, different social and legal systems
and technical standards had to be considered and implemented. In the
process of the planning and the construction of the project, issues caused
by the differences between the three areas have been solved through
constructive communication, negotiation and innovation in a major
Fig. 5. Aerial view of HZMB indicating curved alignment (from Zhuhai side).
2
S. Quanke et al. Tunnelling and Underground Space Technology incorporating Trenchless Technology Research 121 (2022) 104308
future passage of 300.000 tons oil tankers (roof at 29 m below lowest • Hydrology: at the project site the estuary has a width of approx. 30
tide). The longitudinal alignment design was further provided with a km. Studies have shown that under normal conditions, there is:
“W”-shape in the middle section with a minimum of 0.3% slope to o A gentle change of tides (irregular semi diurnal) with a limited
ensure suitable natural drainage in this area (also see Fig. 8 - long tidal range; the mean sea level is 0.54 m and the average tidal
section). range is 1.24 m (see Table 1).
1.4. Environmental conditions and design requirements o Under normal conditions the flow rates and waves are relatively low
and consequently low erosion of the banks and the navigation
The HZMB tunnel was subject to stringent design requirements and channels; these would be convenient conditions for transport and
challenging environmental conditions. Some of the essential ones are immersion. However, during the rain season the discharge of the
listed below. Pearl River can be considerable carrying fine sediments. Over the
Environmental conditions: dredged trench the flow velocity would drop causing the deposition
of sedimentation in the trench bottom. To limit siltation in the open
• Meteorology: the project is located in a subtropical marine monsoon trench its excavation and the tunnel element placement, that time of
climate area: an open trench must be kept short as possible.
o The annual average temperature is approx. 22.5 ◦ C; the average o The tidal flows are mainly in N-S and NNW-SSE direction (approx.
temperature of July (hottest month) is around 28.5 ◦ C. perpendicular to the alignment). The current speeds in ebb tide
o The humidity in the area is relatively high with an average (average 0.25–0.5 m/s) are slightly higher than in rising tide
monthly relative humidity of over 70%. (0.25–0.4 m/s). At spring tide, the speeds are slightly higher, at neap
o The average annual rainfall is between 1880 and 2300 mm and the tide slightly lower. Maximum currents of 1–2 m/s have been
average annual rainfall days are about 140.7 days. observed as well.
o Typhoons will occur in the area on a yearly basis, with an average
number of about 2 and a maximum of around 6. The typhoons However, in the area conditions may change rapidly, due to:
mainly occur from June to October.
o Large discharge during the rain-season from the upstream Pearl
It can be concluded that the climate is not too favourable when it River area;
comes to durability (especially when combined with the aggressive o Wind and wave conditions in the storm season (June-October).
marine environment) and for the working conditions during the
execution of the works. In the Tables 2 and 3 current speeds and significant wave heights are
presented for various return periods:
It should be noted that for the transportation and the immersion of
the tunnel elements waves with longer periods, that result in wave
lengths (and lower wave heights) in the order of the length of the tunnel
Table 1 elements may be more critical (swell waves).
Water Levels.
Table 3
Significant wave heights.
3
S. Quanke et al. Tunnelling and Underground Space Technology incorporating Trenchless Technology Research 121 (2022) 104308
4
S. Quanke et al. Tunnelling and Underground Space Technology incorporating Trenchless Technology Research 121 (2022) 104308
realized in the world at that time, also the design was regarded as o The various marine operations such as dredging, soil treatment and
challenging. foundation installation, immersion and backfilling can very well be
Comparison of the two options aligned with the shipping (including temporary deviations of the
The tunnel options were compared on the following aspects: shipping channels). The length of the tunnel is approx. 6 km and will
enable and allow this; however, still more impact will be experienced
• Construction costs from immersed tunnel construction
• Environmental impact during operation phase
The construction costs for the bored tunnel were estimated to be at
least 10% higher than the immersed tunnel; this was mainly due to the In the evaluation is has been concluded that the environmental
longer and deeper bored tunnel, the cross passages, the deeper cut & impact of the bored tunnel is larger:
cover tunnels and the longer artificial islands. It should be noted that
this only involves cross passages every 500 m which is on the high-end o Due to the longer islands the hydraulic blockage effects would be
regarding tunnel safety and where 250 m would maybe be more larger;
appropriate. o Since the bored tunnel is at a much deeper level (road level some
13.5 m deeper), the vehicles would need to overcome larger height
• Time schedule differences. This will influence / increase the car emissions and
therefore the impact on the environment.
For both options a construction planning was developed. The con • Project / construction risks
struction of the immersed tunnel option was estimated to take 56
months. The construction of the bored tunnel would take 66 months, The overall risk level of the bored tunnel option for the HZMB project
some 10 months longer than for the immersed tunnel. Main reasons for is considered larger than the risk level of the immersed tunnel. Impor
this difference: tant items in the risk evaluation are:
o the fact that for the immersed tunnel option more construction ac o Geological conditions with soft soil and hard rock are considered
tivities can take place in parallel. E.g. construction of the bored more challenging for the bored tunnel construction with an excep
tunnel can only start when the (at least one of the) artificial islands tional diameter of 16.88 m (one of the worlds’ largest) and more
including the deep cut & cover tunnels are completed; for the prone to delays. The immersed tunnel option is evaluated to be more
immersed tunnel option the construction of the islands and cut & flexible for and adaptive to variation and surprises in the subground.
cover tunnels can be done in parallel with the dredging and the Additionally, the immersed tunnel is on a higher level, not touching
fabrication of the tunnel elements; the hard rock.
o longer tunnel, longer islands, deeper cut & cover tunnels o The time schedule for the bored tunnel is less flexible to mitigate
o construction of the cross passages delays on main activities. Construction of the island(s), the launching
shaft, the bored tunnel and the finishing works are (more or less)
In addition, the risk for delays were regarded higher for the bored serial activities and delays in the individual activities will have an
tunnel option; immediate effect on the time schedule. The main activities in the
immersed tunnel construction can be to a greater extent carried in
• (Environmental) Impact during construction phase parallel and therefore less sensitive to delays in the critical path of
the project.
The construction of immersed tunnels generally has a larger/ o The immersed tunnel option is considered more sensitive to meteo
different environmental impact than the construction of bored tunnels: rological, hydrological and other natural conditions especially for
the marine operations.
o Dredging of the immersion trench, although dredging techniques are o The construction organization for the immersed tunnel is regarded
available nowadays that significantly reduce the impact. more complicated with more (external) stakeholders due to the many
o The island construction for the immersed tunnel option is more marine operations and therefore requires a solid preparation to avoid
favourable, due to the smaller sizes. delays.
Fig. 8. Islands & tunnel plan and vertical layout (west = right side) / (E represents the tunnel elements).
5
S. Quanke et al. Tunnelling and Underground Space Technology incorporating Trenchless Technology Research 121 (2022) 104308
2.2.1. Introduction
The HZMB tunnel has a length of 6.704 km with an immersed section
of approximately 5.664 km. A plan view and the longitudinal section of
the tunnel are shown in Fig. 8. The tunnel cross section comprises two
traffic tubes (tube for each traffic direction) and a central gallery for
evacuation/escape and services (cables, mains, pipes) including a
separate duct for smoke extraction. At both ends, the tunnel connects to
Fig. 10. Transportation and positioning tunnel element. artificial islands to realize the transition from the tunnel to the bridge
sections. The maximum water depth for immersion (trench bottom) is
o Due to the many more joints and the deeper level the bored tunnel is approx. 45 m.
regarded more sensitive to water leakages than the immersed tunnel. The immersed section consists of 33 elements of which most are 180
m long. All are 37.95 m wide and 11.4 m high. A standard element of
The bored tunnel was evaluated to have a higher risk profile, with a 180 m is composed of eight 22.5 m-long segments (Fig. 9).
greater number of risks that may have a significant effect on quality, Shear keys are used over the joints to prevent transverse and vertical
costs and schedule; for which reason a significant larger risk reservation discontinuous movements over the segment joints. For the trans
budget had to be added to costs, that were already estimated to be at portation and immersion (see Fig. 10), temporary pre-stressing was used
least 10% higher. to connect the 8 segments into a whole element structure with adequate
6
S. Quanke et al. Tunnelling and Underground Space Technology incorporating Trenchless Technology Research 121 (2022) 104308
1) Large-spans for the road tubes: the maximum span for a 3 lane traffic
layout in one tube in the cross-section reaches 14.55 m.
2) Water depth: a depth at the tunnel base slab is over 40 m. The large
water depths are challenging for the water proofing of the tunnel.
3) Ground cover loads on the tunnel: Prior to the deepening of the
navigation channel sedimentation is allowed to take place on the
tunnel roof. The maximum sedimentation thickness on top of tunnel
can reach 21 m after tunnel is completed (see Fig. 8), which will be
the largest sedimentation load ever on an immersed tunnel.
4) Geological condition: the soil conditions are poor and locally quite Fig. 13. a. Option with central gallery for point extraction ventilation concept.
variable, and are considered very challenging for the tunnel design. b. Option with side galleries for full transverse ventilation.
5) Limitation structural dimensions: The individual tunnel element has
to be able to float during the transport and immersion stages, which
means that there is limitation to the element structural dimensions
determined by the balance between the upward water forces and the
downward element weight and the weight of temporary transport
and immersion equipment.
6) Seismic impact: the project is located at a medium seismic region (Ⅶ
earthquake intensity design). The seismic conditions must be prop
erly incorporated in the design of the joints and tunnel seals / water
stops.
In the concept design stage various options were studied since the
above conditions were regarded not standard and the need for further
examination was recognized. Various cross section geometry concepts
and various structural solutions were studied:
• The high ground loads on the tunnel would require a significant Fig. 14. Structural concepts for cross section. a. Reinforced concrete option 1
amount of post-tensioning. Since the post-tensioning (at least pre- (increased height of tunnel cross section) b. Reinforced concrete option 2
dominantly) had to be installed in the element production stage, (increased width in central gallery) c. Transverse post-tensioning.
substantial temporary structures would be required to counter-act
7
S. Quanke et al. Tunnelling and Underground Space Technology incorporating Trenchless Technology Research 121 (2022) 104308
(1) Geotechnical conditions (including variation) 2.2.3.3. Foundation improvement preliminary design. As indicated above,
(2) Surcharge loads (magnitude and variation) foundation improvement measures are required over the shallower parts
(3) Accidental loads such as seismic events and sunken ships of the tunnel alignment, connecting to the artificial islands. In this way
(4) Internal forces (bending moment, shear forces etc.) the settlements and differential settlements can be limited and therefore
(5) Construction costs also the internal forces in the tunnel. In addition, ground treatment is
applied to promote smooth transition from one tunnel part (e.g. piled cut
Based upon the various studies, it was concluded that the segmental and cover tunnel at the islands) to the other (e.g. immersed tunnel).
8
S. Quanke et al. Tunnelling and Underground Space Technology incorporating Trenchless Technology Research 121 (2022) 104308
of the trench, and to create very good conditions for the installation of a
high-quality gravel bed (Fig. 18).
Ground treatment: In the below Table 5 the ground treatments along
the tunnel are presented:
The tunnel settlements have been closely monitored during the
construction phase as well as during the operation phase. From the
current monitoring results, it shows that the optimized man-made
foundation and the ground treatment works under the tunnel are
behaving consistent and generally within the expected bandwidth (also
see Fig. 32).
Fig. 16. Principles of end bearing piles (left) and SRP (right) – dimensions in mm.
2.2.4. Artificial islands
In the concept and preliminary design stage a comprehensive study
was carried out after the various options that would create better 2.2.4.1. Geometric design. In the early technical studies, a 100X1000m
foundation conditions for the (immersed tunnel). The following options rectangular shaped artificial island was initially designed. After carrying
were studied: hydraulic and aesthetic studies and undertaking physical model tests,
the islands were optimized from a hydraulic blockage and landscaping
(1) Improvement of the ground properties in terms of strength and perspective. (Fig. 19).
stiffness and to increase the uniform behaviour of the ground (to It resulted is an optimized design being a 625 m long oyster shell-
serve smooth transition). shaped artificial island (Fig. 20), which not only satisfies the transi
• Replacement of soft soils by means of sandy gravels or gravel tion function between bridge and immersed tunnel but is more suitable
• Settlement Reduction Piles (steel piles) in soft cohesive layers (no for the hydrodynamic environment of the Pearl River Estuary. To house
end bearing!) all the necessary services on the island the width of the island was
• Cement deep mixing piles in soft cohesive layers (close to islands) increased to some 160 m, coming from a standpoint that a larger width is
• Sand compaction piles not enlarging the hydraulic blockage.
(2) Foundation piles on bearing ground layers in case the ground is
too weak or too unpredictable (close to the artificial islands 2.2.4.2. Preliminary design. As for the tunnel, the geotechnical condi
where large reclamations are carried out) (Fig. 16). tions for the construction of the artificial islands are not very favorable
either. Since large land reclamations and extensive back fill operations
For the tunnel, several foundation treatment schemes were devel are involved the geotechnical design is quite delicate in order to meet
oped, in which above options were used in different sections. In Table 4 the settlement/deformation requirements that were defined. In the
and Fig. 17 the various types of ground treatment are presented that concept and preliminary design stage numerous options were studied
were selected for the preliminary design that would serve as a reference and evaluated. From the various designs, it became obvious, that the
for the construction tender. involvement of the construction companies would be essential. There
The soil investigation used for the preliminary design was still rela was a strong relation between the design and the actual execution and if
tively limited. In parallel with the preliminary design development, a contractor would be specialist in a certain special foundation or marine
extensive additional survey was undertaken to allow a proper assess works technique, it should be possible to incorporate that in the design.
ment of the risks and uncertainties and to adjust or optimize the designs This would stimulate cost and time efficiency and reduce risks. For the
accordingly. The investigation was concentrated in areas where most D&C tender, a concept illustrative design (Fig. 21) was developed to
uncertainties exist (e.g. transition area between the immersed tunnel serve as a reference and that involved the following main stages:
and the artificial islands). Amongst others, the geotechnical investiga
tion will include Cone Penetration Tests, Standard Penetration Tests and • Excavate soft top layers of mud
Vane Shear Tests, Borehole testing to get (undisturbed) samples for • Sand compaction piles to improve underlying cohesive layers
laboratory tests and soil classifications etc. (depending on back fill levels)
• In fill with coarse sand to be compacted
2.2.3.4. Foundation detailed design. For the detailed design the D&C • Formation of the sea defense walls consisting of rock or stone layers
Contractor China Communications Construction Co., Ltd.(CCCC) and his and revetments of doloses
design team adjusted and optimized the foundation design, amongst • Install circular sheet piles walls or diaphragm walls as retaining
others by using the additional ground survey. The design is summarized structure for the cut and cover tunnels (on some locations also to
below but is discussed in more detail in ref (港珠澳大桥主体工程结构健 serve as part of the sea defense in the final phase)
康监测系统需求分析报告, 2013). • Construct cut and cover tunnel founded on bored piles
Man-made foundation: a 2 m uniform riprap (mass stone) layer was • Finishing works
proposed to prepare a high-quality installation of the final gravel bed
(compensation of higher dredging tolerance, storage of sedimentation). Based upon this reference design and a set of functional and technical
Thereafter, a 1.3 m gravel bed was installed in bunds and with a high specifications, the bidding construction consortia could develop and
accuracy. The 2 m riprap preparation layer appeared to be a very suit propose their designs.
able measure in these soft soil conditions, with a serious risk of siltation
Table 4
Ground treatment in preliminary design.
9
S. Quanke et al. Tunnelling and Underground Space Technology incorporating Trenchless Technology Research 121 (2022) 104308
Fig. 17. Ground treatment along the tunnel alignment (preliminary design).
10
S. Quanke et al. Tunnelling and Underground Space Technology incorporating Trenchless Technology Research 121 (2022) 104308
Table 5
Ground treatment detailed design.
11
S. Quanke et al. Tunnelling and Underground Space Technology incorporating Trenchless Technology Research 121 (2022) 104308
Fig. 24. Various stages of artificial island construction (from top left to bottom
right: transport cylinders, installation of cylinder, installation of infill sheeting,
Fig. 23. Illustration of the islands’ revetment and shore protection. soil improvement around the perimeter of the island.
12
S. Quanke et al. Tunnelling and Underground Space Technology incorporating Trenchless Technology Research 121 (2022) 104308
13
S. Quanke et al. Tunnelling and Underground Space Technology incorporating Trenchless Technology Research 121 (2022) 104308
The development of D&B contract form in the Chinese context is an HZMB is a complicated large-scale offshore project combining
integrated innovative process that combines the local Chinese context bridges, islands and an underwater tunnel. It is an essential component
with international practices so as to promote specific D&B contract of the main road network in the Pearl River Delta in Guangdong Pro
strategy in the mainland of China. For the HZMB artificial islands and vence and of the national planned highway network. No national or
tunnel project the Client Organisation HZMBA provided the preliminary international codes or standards cover all of items that are significant to
design as the reference design in the bidding documents and selected the the operation and maintenance of this Main Link. Not only important for
D&B consortium (with special requirements for the consortium’s for a successful completion of the works but also to guarantee a durable and
mation and management). Through this principle, possible impact of the sustainable link with a high availability level and operation quality in
specific existing domestic infrastructure procedures and qualification the 120 years’ service life. Therefore, the Client Organization prepared a
system procedures on the efficiency of the D&B contracting procedures systematic consideration on project specific standards and requirements
could be resolved. It became an innovative new contract mode, made on operation and maintenance through the whole life process. Each
suitable for China’s national situations and for the specific features of system relies on each other, complements and checks each other.
the islands & tunnel. The decision-making process for the D&B contract Especially, for the sea-crossing immersed tunnel considering the limited
mode was a process of managing risks and transferring risks from the experience in China, each system has been given high attention.
government representative organisation to the (state-owned) contrac
tors, following the principle of transferring specific risks to the organi 4.2. Operation and maintenance standards (港珠澳大桥专用营运及
sation best capable of managing them. 维护标准, 2009; 港珠澳大桥营运及维护准则, 2009; 港珠澳大桥主体工
The preparation of the D&B bidding documents of the islands & 程运营维护技术手册, 2018; 港珠澳大桥主体工程运营维护技术手册,
tunnel took 8 months. The documents fully represented the Client’s 2018)
ideas on the D&B contract development for the specific Chinese market
and integrated the international D&B common practice. It appeared a In the feasibility study stage of the project in 2008, the Client
solid foundation for the smooth implementation of the subsequent Organisation already formulated the “Specific Operation and Mainte
design and construction. nance Standard for Hong Kong Zhuhai Macao Bridge” to ensure that the
After public bidding, on December 21, 2010, the Client and China function and service requirements could be developed and defined for
Communications Construction Co., Ltd.(CCCC) signed the D&B contract the future operation phase. The compilation team of this standard has
for the HZMB artificial islands and tunnel project. After seven years of extensively investigated and collected the practical experience from
14
S. Quanke et al. Tunnelling and Underground Space Technology incorporating Trenchless Technology Research 121 (2022) 104308
national and international major large bridges, tunnels and artificial (including repair, strengthening, replacement and other measures)
islands. The standard took reference of relevant regulations of the na might be needed when the requirements cannot be met in mid-time. It is
tional and highway transportation industries, and relevant standards of an important technical guidance for the practical operation and main
Hong Kong, Macao and foreign countries. It had also consulted experts tenance of the project after completion.
from all over the world. This standard provided very useful guidance
and help for the design, implementation, operation and maintenance of 4.3. Structural health monitoring design (港珠澳大桥主体工程结构
Hong Kong Zhuhai Macao Bridge. Since the start of concept design, 健康监测系统需求分析报告, 2013; 港珠澳大桥主体工程交通工程结构
designers have integrated the standard into the designs to improve 健康监测工程施工图联合设计, 2012)
conditions for better future operation and maintenance.
In the preliminary design stage, the designer updated and prepared Since the preliminary design stage, the concept of health monitoring
the “Criteria for Operation and Maintenance of Hong Kong Zhuhai system of Hong Kong Zhuhai Macao Bridge combining with the elec
Macao Bridge” based on the abovementioned standard. After being tronic manual inspection system has been established (Fig. 31) and was
reviewed by the Client’s consultant, it was included in the D&B bidding implemented into the realization stage of the system. The main objec
documents for “islands & tunnel”, which was the subsequent basis for tives are:
the design and construction.
Before the handover of the whole project after construction and • To provide a platform for the scientific and orderly O&M manage
under the management of the Client, Client’s consultant (lead party) and ment of Hong Kong Zhuhai Macao Bridge during the operation
together with designer and contractor, the “Technical Manual for period, and to establish a digital and information-based “archive” for
Operation and Maintenance (O&M) of Main Works of Hong Kong Zhuhai the whole life of the structure based on the comprehensive moni
Macao Bridge” was compiled, which was a further deepening of the toring and management maintenance system.
above two standards. It is divided into four Volumes, namely, the Gen • To effectively control the structural state and its’ development and
eral Part(1), the Islands & Tunnel(2), the Bridges(3) and the Traffic evolution trend during the operation period, timely diagnose and
Engineering incl. installations and systems(4). Different from normal warning of deviating conditions, performance of hierarchical and
O&M manuals in China, in the Volume of Islands & Tunnel special re comprehensive assessment on the health status of the structure are
quirements had been defined in the daily inspection and cleaning, reg implemented to ensure the safe operation of the structure.
ular inspection, periodic inspection, emergency inspection and special • To provide decision support for reasonable, active and preventive
inspection. As an innovation, the manual added the requirements for maintenance measures in order to effectively manage and reduce the
initial inspection (time around handover), inspection accessibility, O&M costs of the whole lifecycle and maximize the service life of the
technical condition evaluation, and especially the structural health structure.
analysis and evaluation including durability inspection and monitoring,
durability evaluation and redesign. The manual emphasizes the impor
tance of preventive maintenance and regular check of the structural
health state to guarantee the remaining service lifetime. Redesign
15
S. Quanke et al. Tunnelling and Underground Space Technology incorporating Trenchless Technology Research 121 (2022) 104308
The ideas of the Structure Health Monitoring System are as follows: service performance of structures, the algorithm of condition assessment
and maintenance decision-making, the active management and control
• Assess risks and analyse component vulnerability of each structural of traffic operation and emergency intervention, and the integrated
item to determine the essential components of the structure. intelligent operation and maintenance platform. The holographic
• Based upon these structural essential components, develop and sensing technology, the 3D perception technology, and the related
establish a monitoring program. The monitoring plan includes equipment for sea-crossing facilities of HZMB are under development,
monitoring items, frequency, characteristic value, etc. and a parallel digital Intelligent O&M Technical System is established,
• The data of the automatic monitoring system and the manual in so as to realize holographic perception, accurate evaluation, rapid
spection constitute the database for monitoring early warning and maintenance and active management and control of the operation status
structural safety assessment. of the facilities. This is to improve the service performance and service
• Using to monitoring data and based on structural component eval life, to reduce the operation and maintenance cost, and to ensure the
uation, establish an early warning scheme including threshold / operational safety.
trigger levels. In the first 3–5 years during operational phase, intelligent operation
• Assess structural safety, mainly on technical condition assessment. and maintenance technology research and practical application will be
completed, including:
The automatic monitoring items of immersed tunnel in this project
amongst others include: • Holographic stereo sensing technology and equipment.
• Service status assessment and intelligent maintenance technology
• Environmental temperature and humidity and equipment.
• Traffic load • Key technologies for intelligent operation and emergency response.
• Ground motion response • Key technologies of bridge- island- tunnel multimodal data collection
• Joint opening and displacement and development of knowledge systems.
• Structural stress • Key technologies and special applications with the option to be easy
• Structural temperature included in the intelligent platform.
• Concrete corrosion
• Joint leakage Two key scientific items are planned to be solved on short notice:
16
S. Quanke et al. Tunnelling and Underground Space Technology incorporating Trenchless Technology Research 121 (2022) 104308
2) The preparation of an evolution mechanism and risk early warning on the waterfront of Zhuhai City, with a maximum wind force of level 15
model of the service performance of the bridge-island-tunnel system (48 m/s) near the typhoon centre. After the typhoon, through the on-site
with multi field coupling of uncertainties. emergency inspection and judgment (at that time, the construction of
the structural health monitoring system was not fully completed, so the
It targets to break through five key technical problems: automatic monitoring data was not recorded), it was concluded that the
bridge structure had performed very well with no damage to primary
1) Unmanned equipment with multi-sensor fusion and intelligent patrol structural components.
& inspection technology. On September 16, 2018, another super typhoon “Mangosteen” of
2) Real-time online evaluation, hierarchical early warning and long- level 17 made a frontal landing near Zhuhai City, Guangdong Province.
term service performance index system driven by data model. This was the second time that the Hong Kong Zhuhai Macao Bridge has
3) Detailed parallel system for intelligent active control of traffic been “baptized” by a strong typhoon of over level 14 before it was
operation and emergency response and intervention. actually opened to traffic. During the typhoon, the bridge structure
4) Data collaborative interconnection technology for intelligent O&M. monitoring system operated stable, and the maximum instantaneous
5) Scheduling technology of heterogeneous fusion of multimodal wind speed was up to 55 m/s, and the average maximum wind speed
massive data and multi-type services. was up to 47.05 m/s in ten minutes (all located at the top of Qingzhou
bridge tower – close to the western tunnel portal). All the monitoring
5. PERFORMANCE OF THE STRUCTURE values of the structure were within the design allowable range. The
Hong Kong Zhuhai Macao Bridge survived this mega typhoon without
5.1. Impact of sedimentation and settlements any structural damage.
Two years after the completion of the works (approx. one year after 5.3. Structural reaction after earthquake
the opening), the overall condition of the tunnel is considered and
assessed as good. The settlements of the immersed tunnel are stable and At 06:55 on January 5, 2020, an earthquake with a magnitude of 3.5
converging. Taking E13 in deep buried section as an example; the initial occurred in the sea area of Zhuhai City, Guangdong Province, with a
monitoring of settlements started on Sept 20, 2013 (immediate after focal depth of 12 km. The epicentre of the earthquake was located in the
immersion); the settlement data as of December 31, 2019 are as follows: south of Hong Kong Zhuhai Macao Bridge, with a straight distance of
the cumulative average settlement measured at segment E13-S1 (pri about 24 km. According to the analysis of structural health monitoring
mary end) was – 58.6 mm; the cumulative average settlement measured data, the impact intensity of the earthquake on the bridge was 2.96◦ , far
by segment E13-S8 (secondary end) was – 43.1 mm. The cumulative less than the seismic intensity of the bridge fortification, and the struc
settlement time curve of E13 is presented in Fig. 32 and shows stabili ture was not affected at all. At the time of earthquake, the vibration of
zation of settlements. the tunnel structure increased obviously, but it was far less than the
To analyse the siltation level change after the backfilling of the design allowable value, and it recovered to the pre-earthquake level
immersed tunnel, a multi beam sounding system has been used for the immediately after the earthquake.
whole tunnel siltation monitoring for 16 times since July 2017. Ac
cording to the latest survey data in November 2019, compared with the 6. CONCLUSIONS
acceptance data of the backfilling of the tunnel element, the maximum
thickness of the siltation at the top of the tunnel element is approx. 7.3 m (1) Before, China had no experience in the construction of super long
located at E21 (the acceptance time of the backfilling of the element was and deep immersed tube tunnel under the marine offshore con
in December 2015). Considering both the results of the design calcula ditions and founded in thick and soft soil conditions. After
tion and the deformation monitoring data of the immersed tunnel, it can advanced and detailed investigation and study, careful planning,
be concluded that the current tunnel settlements (and maybe more and cooperation with international teams, and systematic
important the settlement development trend) are well within the experimental research, a large number of design and construction
allowable range of the design, and therefore resulting in a safe and parameters were obtained that were essential for the realization
sound structure. of the fixed link including the tunnel. This very thorough prep
aration of the project resulted in the successful construction and
completion of the whole project including the subsea immersed
5.2. Structural response after two strong typhoons
tunnel. The HZMB link started normal operation late 2018. Using
an extensive monitoring program, it could be concluded that all
On August 23, 2017, the major typhoon “Pigeon” of level 15 landed
performance indexes are within the predetermined level.
(2) In the project preparation stage, the Owner took the lead and
conducted detailed investigation and verification of the project in
terms of design development, project scheme, taking into account
the challenging environmental conditions. The Owner analysed
technology, materials, equipment, management, project staffing
and other factors. Through risk analysis, various mitigating
measures and project plans were formulated. For verification of
criticical design items such as tunnel foundation treatment, lon
gitudinal calculation, aseismic performance, joint design con
cepts and so on, different independent analyses of several parties
(including universities and international consultants) and model
tests have been carried out to ensure to that technologies were
feasible and the process is controllable. Various sets of large-scale
special equipment and information control technology were
developed. The project goal was “long life and high quality” and
the established construction principle “Industrialization, large
Fig. 32. E13 accumulative settlement- time curve. scale, standardization and assembly ”. At the same time the D&B
17
S. Quanke et al. Tunnelling and Underground Space Technology incorporating Trenchless Technology Research 121 (2022) 104308
contract mode was established, and the associated quality man ▪ Lead member: China Communications Construction Co.,
agement methods were implemented with the help of partnership Ltd. (CCCC)
and internationalization. ▪ Construction members:
(3) The project has obtained research funds from the science and • AECOM Co., Ltd. (project management support)
technology support plan of the Central Government. More than • Shanghai Urban Construction Group Corporation, Ltd.
30 enterprises, universities and scientific research institutions ▪ Design members:
have conducted research and development on key technologies • CCCC Highway Consultants Co., Ltd (design lead
and equipment for the design, construction and operation of the member) (China)
deep buried immersed tunnel and the offshore artificial island for • COWI A/S (Denmark)
more than five years. Many innovative design approaches and • Shanghai Tunnel Engineering & Rail Transit Design and
solutions have been made, such as design philosophy, advanced Research Institute (China)
analysis methodologies and software, (structural) durability • CCCC Fourth Harbor Design Institute Co., Ltd. (China)
principles, testing and monitoring technologies, emergency and • Construction Supervisor of artificial islands and tunnel work:
calamity prevention and management etc. The successful imple • Lead member: China Railway Wuhan Bridge Engineering Consul
mentation of the project also benefitted from the great progress of tation & Management Co., Ltd. (China)
China’s capacity for equipment manufacturing and the coopera • Associate Members:
tion of different industries. ▪ Guangzhou Port & Waterway Engineering Supervision
(4) The technology and management experience, the technical Co., Ltd. (China)
standard and the industrial systems that were developed during ▪ Guangzhou Municipal Engineering Supervision Co., Ltd.
the preparation and realization of HZMB immersed tunnel and (China)
artificial islands, can be used for reference for major transport
infrastructure interconnection projects in China’s “one belt one Miscellaneous:
road” countries, for the realization of major projects in the bay Several figures in this paper are based or have been taken from
area of Guangdong and Hong Kong, and for other similar projects design reports that were developed by the Design JV on behalf of the
in China and around the world. Client in the Conceptual and Preliminary Design stage.
References
Declaration of Competing Interest
Su Quanke, Chen Yue, Ying Li, J.C.W.M. de Wit, Hongkong Zhuhai Macao Bridge Link in
The authors declare that they have no known competing financial China, Stretching the limits of Immersed Tunnelling, ITA Proceedings Helsinki, May
2011.
interests or personal relationships that could have appeared to influence J.C.W.M. de Wit, China’s Hong Kong Zhuhai Macao Bridge (HZMB) Link, China’s latest
the work reported in this paper. infrastructure challenge,Tunnels & Tunneling, March 2011.
Ying Li, J.C.W.M.(Hans) de Wit, The Technical Difficulties and Innovations of
ImmersedTunnel in Hong Kong Zhuhai Macao Bridge Project, Southern Energy
Appendix A Construction, No.2, 2017.
Hans de Wit, René Kuiper, Ying Li, Quanke Su and Yue Chen, An innovative design
concept for the Immersed Tunnel of the Hong Kong Zhuhai Macao Bridge Project –
COLOPHON: Following an alternative review approach for the approval of an innovative concept,
Project Organisation ITA Proceedings Dubai, May 2018.
Client Organisation: Lin, M., Lin, W., Liu, X., Yin, H., 2021. Jibing Gao. The Island and Tunnel Projects of
Hong Kong- Zhuhai-Macao Bridge, TUST.
Yongling Zhu, Zhaohan Sheng, Jinwen Zhang, Lie Yu, etc, 〈〈港珠澳大桥工程决策理论与
• Client Hong: Kong-Zhuhai-Macao Bridge Authority 实务》“Decision making theory and practice of Hong Kong Zhuhai Macao Bridge
• Designer: Design JV led by HPDI for Concept Design (see below) Project”, China Communications Press, 2020.
• Client Consultant: Tunnel Engineering Consultants (Netherlands) Jinwen, ZHANG., Yumin, QIU., 2018. How does the improved D&B mode degrade the
complex integrity of infrastructure mega-projects? Evidence from the Hong Kong-
and GMDI (China) Zhuhai-Macao Bridge project in China. Front. Eng. Manag. 5 (1), 40–51.
• Construction quality management consultant: Mott MacDonald Co., 张劲文, 设计施工总承包的中国式实践, 桥梁杂志, 2017.12. Zhang Jinwen, Chinese
Ltd. practice of design and construction D&B contracting, Bridge Journal, December
2017.
〈〈港珠澳大桥专用营运及维护标准》, 2009.03, Special operation and maintenance
Designer and contractor: standard for Hong Kong Zhuhai Macao Bridge, March 2009.
〈〈港珠澳大桥营运及维护准则》, 2009.07, Criteria for operation and maintenance of
Hong Kong Zhuhai Macao Bridge, July 2009.
• Conceptual and Preliminary design phase 〈〈港珠澳大桥主体工程运营维护技术手册》(总体篇), 2018.03, Technical manual for
• Lead designer: CCCC Highway Consultants Co., Ltd. (China) operation and maintenance of main works of Hong Kong Zhuhai Macao Bridge
• associate design members: (General Part), March 2018.
〈〈港珠澳大桥主体工程运营维护技术手册》(岛隧篇), 2018.03, Technical manual for
▪ COWI A/S (Denmark) operation and maintenance of main works of Hong Kong Zhuhai Macao Bridge
▪ Arup (Hong Kong) (Islands & Tunnel Part), March 2018.
▪ Shanghai Tunnel Engineering & Rail Transit Design and 港珠澳大桥主体工程结构健康监测系统需求分析报告, 2013.06, Demand analysis report
on structural health monitoring system of main works of Hong Kong Zhuhai Macao
Research Institute (China)
Bridge, June 2013.
▪ CCCC First Harbor Consultants Co., Ltd. (China) 港珠澳大桥主体工程交通工程结构健康监测工程施工图联合设计, 2012.10, Joint design
• General contracting phase design and construction of artificial of construction drawings for structural health monitoring works of main works of
islands and tunnel works: Hong Kong Zhuhai Macao Bridge, October 2012.
The Islands and Tunnel Project of HZM Link, Wei Lin, Ming Lin, Xiaodong Liu, Haiqing
• General contracting consortium design and construction of artifi Yin, Jibing Gao, TUST 2022 Immersed Tunnels.
cial islands and tunnel work:
18