You are on page 1of 35

STRUCTURAL DRAWINGS

Volume 3: Tender Drawings

Client: Project Title: Drawing Title: Realini Architects


R B Bader
Sierra Leone Field Office of Rehabilitation / Completion and Structural - Cover Sheet A Associates Limited 72 Wellington Street, Freetown
Engineers
Planners

the African Dvelopment Outfitting Work for Office Date: August, 2016

Bank (ADB) Building Drawn by: MLY SL/ADB/ST-CS


Checked by: INY
Regent Road, Hill Station, Freetown
Project status: Design: Tender: Y Contract / Construction: Scale: Sheet Size: A3
25/11/2016 16:59:52
NOTES:-

1. The figures are concrete compressive


strength readings N/mm2.
N 2. Column readings are written on the
A B C D E F G H beams.
3. Beam readings are written on the
beams.
4. Slab readings are written on the open
56 70 60 68 69 spaces.
1 5. Circled readings are those that fall
56 below the specified concrete
54
compressive strength of 25N/mm2,
56 these imply problem area.
51 51
49
63 6. The contractor is responsible for
51 54
verification of the structural design
57 56 52
2 59 before proceeding with construction of
structural elements.
52 56 46 33 LEGEND:-
58
3 44
Existing reinforced concrete wall
44 Existing beams
Existing staircase to be demolished
Existing column
Existing column to be demolished
Existing column pad
Existing Slab thickness 150mm
4

Project Title: Drawing Title: No. Description Date Architects


1.0 Description dd-mm-yyyy
Realini Engineers
R B Bader
Rehabilitation / Completion and Outfitting Work for Existing A Planners
Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Basement Plan Date: August, 2016
Schmidt Hammer SL/ADB/ST-01
For Sierra Leone Field Office of the African Drawn by: BWB

Development Bank (ADB) Result Checked by: SDD Sheet Size: A3


Drawing status: Design: Tender: Contract / Construction: Scale: 1 :100 Printed on: August, 2016
NOTES:-

N A B C D E F G H I
1. The figures are concrete compressive
strength readings N/mm2.
2. Column readings are written on the
beams.
57 60 68 3. Beam readings are written on the
1 beams.
47 47 47 47
50 50 45 40 4. Slab readings are written on the open
spaces.
70 67 5. Circled readings are those that fall
44 70
70 below the specified concrete
69 compressive strength of 25N/mm2,
2 50 these imply problem area.
54 42 6. The contractor is responsible for
10 68
70 verification of the structural design
61 55 46 before proceeding with construction of
3 40 57
58
57 57 structural elements.
70
63 LEGEND:-
15
35 Existing beams
38 53 53 24 54 Existing beams to be demolished
61
Existing slab to be demolished
25
Existing staircase to be demolished
69 47 54 54 54 66 55
4 22 55 13 Existing column
24
63 Existing column to be demolished
36
8 Existing Slab thickness 150mm
2

Project Title: Drawing Title: No. Description Date Architects


1.0 Description dd-mm-yyyy
Realini Engineers
R B Bader
Rehabilitation / Completion and Outfitting Work for Existing A Planners
Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Ground Floor Plan Date: August, 2016
Schmidt Hammer SL/ADB/ST-02
For Sierra Leone Field Office of the African Drawn by: BWB

Development Bank (ADB) Result Checked by: SDD Sheet Size: A3


Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 100 Printed on: August, 2016
N NOTES:-
A B C D E F G H I 1. The figures are concrete compressive
strength readings N/mm2.
2. Column readings are written on the
beams.
1 3. Beam readings are written on the
beams.
20 17 4. Slab readings are written on the open
spaces.
18 5. Circled readings are those that fall
below the specified concrete
2 compressive strength of 25N/mm2,
these imply problem area.
21 6. The contractor is responsible for
verification of the structural design
3 before proceeding with construction of
28 27 38 structural elements.
60 LEGEND:-
21 26 58 Existing beams
24 Existing beams to be demolished
12 70
10
24 30 Existing slab to be demolished
18
4 51 55
Existing staircase to be demolished
55 70
59 Existing column
Existing column to be demolished
Existing Slab thickness 150mm

No. Description Date Architects


Project Title: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Bader Planners
Rehabilitation / Completion and Outfitting Work for A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Existing First Floor Date: August, 2016

For Sierra Leone Field Office of the African Plan Schmidt Drawn by: BWB
SL/ADB/ST-03

Development Bank (ADB) Hammer Result Checked by: SDD Sheet Size: A3
Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 100 Printed on: August, 2016
N A B
NOTES:-
C D E F G H I 1. The figures are concrete compressive
strength readings N/mm2.
2. Column readings are written on the
beams.
1 21
18
3. Beam readings are written on the
beams.
4. Slab readings are written on the open
spaces.
5. Circled readings are those that fall
below the specified concrete
2 compressive strength of 25N/mm2,
21 these imply problem area.
17 6. The contractor is responsible for
verification of the structural design
3 20 before proceeding with construction of
structural elements.
LEGEND:-
Existing beams
Existing beams to be demolished
Existing slab to be demolished

4 19 Existing Slab thickness 150mm

No. Description Date Architects


Project Title: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Bader Planners
Rehabilitation / Completion and Outfitting Work for A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Existing Roof Date: August, 2016

For Sierra Leone Field Office of the African Beams Drawn by: BWB
SL/ADB/ST-04
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 100 Printed on: August, 2016
NOTES

27711

N A B C D E F G H I

C1 C1 C1 C1 C1 C1
1 C1

C2
2 C1 C1
Legend
Existing Beam Maintained
C2 New Beam
3 C2 C2
Existing Retaining Wall Maintained
New Retaining Wall

reinforced
concrete
Existing Column Footings

wall
New Column Footings and trenches
C1
Existing Columns Maintained

Existing columns Modified

C1 New Columns

Existing Slab Maintained

4 C1 C1
New Slab

Project Title: Drawing Title: No. Description Date Architects


1.0 Description dd-mm-yyyy
Realini Engineers
R B Bader Planners
Rehabilitation / Completion and Outfitting Work for A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Proposed Basement Date: August, 2016
SL/ADB/ST-05
For Sierra Leone Field Office of the African Structural Layout Drawn by: PH
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 100 Printed on: August, 2014
NOTES

A B C D E F G H I
N
Type A C1 C1 C1 C1 C1 C1 Type A C1
C1
1 duct

Type A

Type B
C1 C2 Type A
Type A C1 Type A
2 C2

Type A
Legend
Type A

Type B

Type B

Type B

Type B
C2 Existing Beam Maintained
3 C2 C2Type B C2 Type A C2 C2 Type A
C2 New Beam
Existing Retaining Wall Maintained
New Retaining Wall
Type A C2 Type A Type A
Existing Column Footings
C2 C2 C2 C2 C2 New Column Footings and trenches
Type B

Type B

Type B
Existing Columns Maintained

Existing columns Modified


Type A

New Columns

Type A Type A Existing Slab Maintained


4
C1 C1 C1 C1 C1 C1 C1 New Slab

Project Title: Drawing Title: No. Description Date Architects


1.0 Description dd-mm-yyyy
Realini Engineers
R B Bader Planners
Rehabilitation / Completion and Outfitting Work for A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Proposed Ground Date: August, 2016
SL/ADB/ST-06
For Sierra Leone Field Office of the African Floor Structural Drawn by: PH

Development Bank (ADB) Layout Checked by: SDD Sheet Size: A3


Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 100 Printed on: August, 2014
NOTES

A B C D E F G H I
N
Type A C1 C1 Type A C1 C1 Type A C1 C1
1 C1
duct

Type A

Type B

Type B
C1 Type A C1 Type A Type A Type A Type A C2
2
C2
Legend
Type A

Type B

Type B

Type B

C2 Existing Beam Maintained


Type A C2 Type A C2 C2 Type A
3 C2
New Beam
C2 C2 C2 Existing Retaining Wall Maintained
New Retaining Wall
Type A Type A Type A
Type A C2 Existing Column Footings
C2 C2 C2 C2 C2 New Column Footings and trenches
Type A

Type A
Type A

Existing Columns Maintained

Type A

Type A
Type A
Existing columns Modified
Type A

New Columns

Type A Type A Type A Type A Type A Type A Existing Slab Maintained


4 New Slab
C1 C1 C1 C1 C1 C1 C1

Project Title: Drawing Title: No. Description Date Architects


1.0 Description dd-mm-yyyy
Realini Engineers
R B Bader Planners
Rehabilitation / Completion and Outfitting Work for A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Proposed First Date: August, 2016
SL/ADB/ST-07
For Sierra Leone Field Office of the African Floor Structural Drawn by: PH

Development Bank (ADB) Layout Checked by: SDD Sheet Size: A3


Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 100 Printed on: August, 2014
NOTES

N A B C D E F G H I

Type A C1 Type A Type A C1 Type A C1 Type A C1 Type A C1


C1
1 duct

Type A

Type B

Type B

Type B

Type A
Type B Type B
C2
C1 Type A C1
2

Type A
Type B

Type B

Type B
Type A

Legend
Existing Beam Maintained
Type B Type B Type B C2 Type A New Beam
C2 C2 C2 duct

3 C2 C2 C2 Existing Retaining Wall Maintained


New Retaining Wall

Type B Type B Type B Type B Existing Column Footings

New Column Footings and trenches


C2 C2 C2 Type A

Type B
C2 C2

Type B
C2

Type B
Existing Columns Maintained
Type B

Type B

Existing columns Modified

Type A
C2 New Columns
Type A

Type B
Existing Slab Maintained

4 New Slab

Type A C1 Type A C1Type A C1 Type A C1 Type A C1Type A C1

Project Title: Drawing Title: No. Description Date Architects


1.0 Description dd-mm-yyyy
Realini Engineers
R B Bader Planners
Rehabilitation / Completion and Outfitting Work for A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Proposed Date: August, 2016
SL/ADB/ST-08
For Sierra Leone Field Office of the African Structural Roof Drawn by: PH

Development Bank (ADB) Beams Checked by: SDD Sheet Size: A3


Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 100 Printed on: August, 2014
NOTES

6Y16 06
Y10 05 4Y16 06
Y10 05
SECTION Y-Y
SECTION Y-Y

Y1602-150P B1
Y1602-150P B2

Y1204-200P T2 Y1204-200P T2

Y1601-150P B1 Y1203-200P T1
Y1601-150P B2 Y1203-200P T1

BASE C1 BASE C2

6Y16 05 4Y16 06
NGL. NGL.

Y10 05 Y10 05

75mm Blinding concrete 75mm Blinding concrete

COLUMN TYPE C1 COLUMN TYPE C2


Project Title: Drawing Title: No. Description Date Architects
1.0 Description dd-mm-yyyy
Realini Engineers
R B Bader Planners
Rehabilitation / Completion and Outfitting Work for A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Proposed Column Date: August, 2016
SL/ADB/ST-09
For Sierra Leone Field Office of the African Details Drawn by: PH
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 40 Printed on: August, 2014
NOTES

150

Project Title: Drawing Title: No. Description Date Architects


1.0 Description dd-mm-yyyy
Realini Engineers
R B Bader Planners
Rehabilitation / Completion and Outfitting Work for A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Proposed Beam/Slab Date: August, 2016
SL/ADB/ST-10
For Sierra Leone Field Office of the African Details Drawn by: PH
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 10 Printed on: August, 2014
NOTES

N A B C D E F G H I

TYPE A
TYPE A
TYPE A TYPE A

TYPE B
TYPE B
3

TYPE C
TYPE F
TYPE B
TYPE D
Legend
TYPE E
TYPE E

4 TYPE D TYPE B Roof Truss

TYPE B
Lift
TYPE B

TYPE A TYPE A

TYPE A
TYPE A

TYPE E

No. Description Date Architects


Client: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Rehabilitation / Completion and Outfitting Work for A
Bader Planners
Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Roof Truss Layout Date: October, 2016
for sierra leone field office of the African Development Drawn by: PH SL/ADB/ST-11
Bank (ADB) Checked by: SDD Sheet Size: A3
Drawing status: Design: Tender: Contract / Construction: Scale: 1 :100 Printed on: Oct, 2016
NOTES

No. Description Date Architects


Client: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Rehabilitation / Completion and Outfitting Work for A
Bader Planners
Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Roof Truss Details Date: October, 2016
for sierra leone field office of the African Development Drawn by: PH SL/ADB/ST-12
Bank (ADB) Checked by: SDD Sheet Size: A3
Drawing status: Design: Tender: Contract / Construction: Scale: Not To Scale Printed on: Oct, 2016
NOTES

No. Description Date Architects


Client: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Rehabilitation / Completion and Outfitting Work for A
Bader Planners
Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Roof Truss Details Date: October, 2016
for sierra leone field office of the African Development Drawn by: PH SL/ADB/ST-13
Bank (ADB) Checked by: SDD Sheet Size: A3
Drawing status: Design: Tender: Contract / Construction: Scale: Not To Scale Printed on: Oct, 2016
NOTES

No. Description Date Architects


Client: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Rehabilitation / Completion and Outfitting Work for A
Bader Planners
Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Roof Truss Details Date: October, 2016
for sierra leone field office of the African Development Drawn by: PH SL/ADB/ST-14
Bank (ADB) Checked by: SDD Sheet Size: A3
Drawing status: Design: Tender: Contract / Construction: Scale: Not To Scale Printed on: Oct, 2016
NOTES

FIRST FLOOR
Y1202-150P

Y1201-150P
Y1208-150P

Y1204-150P
P
150
-
2 03
Y1

GROUND FLOOR
Y1206-150P Y1205-150P

Y1202-150P
50P
1
12-
Y
Y12-150P
BASEMENT FLOOR
C2 C1

Project Title: Drawing Title: No. Description Date Architects


1.0 Description dd-mm-yyyy
Realini Engineers
R B Bader Planners
Rehabilitation / Completion and Outfitting Work for A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Proposed R/C Date: August, 2016
SL/ADB/ST-15
For Sierra Leone Field Office of the African Details For Drawn by: PH

Development Bank (ADB) Staircase No.1 Checked by: SDD Sheet Size: A3
Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 40 Printed on: August, 2014
NOTES

Y1202-150P Y1205-150P

Y1201-150P
Y12-150P

Y1206-150P
Y1205-150P Y1203-150P

Y1204-150P

600 100

2600
200

Project Title: Drawing Title: No. Description Date Architects


1.0 Description dd-mm-yyyy
Realini Engineers
R B Bader Planners
Rehabilitation / Completion and Outfitting Work for R/C Roof Slab With A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Parapet & Details Date: August, 2016
SL/ADB/ST-16
For Sierra Leone Field Office of the African For Staircase No.2 Drawn by: PH
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 30 Printed on: August, 2014
150mm Thick Roof Slab NOTES
(Height to be determined on site)

300 1900 300

02 02 02 02 02 02 02 02 02 02 02
02 02

300
04 04
04 04 04 04 04 04 04 04 04 04 04

y1201-200mm T2 100mm Blinding


concrete
Basement y1603-200mm B2

y1208-150P

y1207-150P

y1206-150P
y1201-200mm T2
y1205-150P y1603-200mm B2

300 1900 300


300

2500
y1207-150P
1900

y1206-150P

Lift Base
300

y1205-150P
y1206-150P

Project Title: Drawing Title: No. Description Date Architects


1.0 Description dd-mm-yyyy
Realini Engineers
R B Bader Planners
Rehabilitation / Completion and Outfitting Work for A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown R/C Details For Date: August, 2016
SL/ADB/ST-17
For Sierra Leone Field Office of the African Lift Shaft Drawn by: PH
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 75 Printed on: August, 2014
NOTES:-

12138

3263 1725 4225 2825

J K L M N
C4 C4 C4 C4
C3 C3

7 Type C Type C Type C


Type C

Type C

Type C

Type C
2325
5075

6 C3 C3 Type C Type C C3

LEGEND:-
Type C

Type C

Type C

Type C
2225

Columns

Beams
Footing
5 Type C Type C Type C
P/C Strips
C3 C3

C4 C4 C4 C4 C4

No. Description Date Architects


Project Title: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Bader Planners
Rehabilitation / Completion and Outfitting Work for Generator House A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Structural Date: August, 2016
SL/ADB/ST-18
For Sierra Leone Field Office of the African Foundation Layout Drawn by: BWB
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 40 Printed on: August, 2016
NOTES:-

J K L M N
12138
3263 1725 4225 2825
C4 C4 C3 C4 C3 C4

7
2325

C3
5075

C3
6 C3

LEGEND:-
2225

Columns

Floor Slab 150mm thick with


12mm rod meshed at 150mm
spacing C-C
5
C4 C4 C3 C4 C4 C3 C4

No. Description Date Architects


Project Title: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Bader Planners
Rehabilitation / Completion and Outfitting Work for Generator House A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Floor Slab Date: August, 2016
SL/ADB/ST-19
For Sierra Leone Field Office of the African Drawn by: BWB
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 40 Printed on: August, 2016
NOTES:-
225 400

225

225
SECTION K-K
900 SECTION M-M

338 225 338 1200


400 400 400
338 225 338
900

900
300
225
400
225
BEAM TYPE C
Varies

Varies

900
1200

COLUMN TYPE C3 COLUMN TYPE C4


No. Description Date Architects
Project Title: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Bader Planners
Rehabilitation / Completion and Outfitting Work for A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Generator House Date: August, 2016
SL/ADB/ST-20
For Sierra Leone Field Office of the African Structural Details Drawn by: BWB
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 30 Printed on: August, 2016
NOTES:-

O P Q
300 2300 300 2300 300

Type D Type D

450
8

C5 C5
C5
Type D

Type D

Type D
4000

3600
LEGEND:-
Columns

Beams
C5
Footing

P/C Strips
C5 C5

450
9

Type D Type D

No. Description Date Architects


Project Title: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Bader Planners
Rehabilitation / Completion and Outfitting Work for A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Water Tank Structural Date: August, 2016
Foundation Layout SL/ADB/ST-21
For Sierra Leone Field Office of the African Drawn by: BWB
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 100 Printed on: August, 2016
NOTES:-

O P Q
8 150 5700

4000
LEGEND:-
Columns
Floor Slab 200mm thick with
16mm rod meshed at 150mm
150

spacing C-C
9

No. Description Date Architects


Project Title: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Bader Planners
Rehabilitation / Completion and Outfitting Work for Water Tank A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Ground Floor Date: August, 2016
SL/ADB/ST-22
For Sierra Leone Field Office of the African Slab Details Drawn by: BWB
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 100 Printed on: August, 2016
NOTES:-
O P Q

Y16 B1

450
8

1600

4200
4000

3100

2563

LEGEND:-
Columns
Reinforcement
450
9

1350
Y16 B2 Y16 T2 Y16 T1
Y12-150P T1
Y16-200P B1 200

Y16-200P B2 Y12-150P T2

No. Description Date Architects


Project Title: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Bader Planners
Rehabilitation / Completion and Outfitting Work for Water Tank A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Mezzanine Floor Date: August, 2016
SL/ADB/ST-23
For Sierra Leone Field Office of the African Suspended Slab Drawn by: BWB
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Details Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 100 Printed on: August, 2016
NOTES:-
O P Q
5400

Y16 B1

4000
Y16 B2
LEGEND:-
Columns
Reinforcement
9

Y16 T1 Y16 T2 Y16 T2 Y16 B1

Y12-150P T1
Y16-200P B1 200

Y16-200P B2 Y12-150P T2
No. Description Date Architects
Project Title: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Bader Planners
Rehabilitation / Completion and Outfitting Work for Water Tank Typical A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown First Floor and Date: August, 2016
SL/ADB/ST-24
For Sierra Leone Field Office of the African Suspended Slab Drawn by: BWB
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Details Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 100 Printed on: August, 2016
NOTES:-
6Y16 06
Y10 05

SECTION Y-Y

Y1602-150P B2

Y1204-200P T2

Y1601-150P B1 Y1203-200P T1

BASE C5

6Y16 05
NGL.

Y10 05

75mm Blinding concrete

COLUMN TYPE C5

No. Description Date Architects


Project Title: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Bader Planners
Rehabilitation / Completion and Outfitting Work for Water Tank A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Structural Details Date: August, 2016
SL/ADB/ST-25
For Sierra Leone Field Office of the African Drawn by: BWB
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 100 Printed on: August, 2016
NOTES:-

R S T U
8600

10 Type F Type F Type F


C6 C6 C6 C6
4450

Type F

Type F

Type F

Type F
LEGEND:-
Columns

Beams
Footing
C6 C6 C6 C6
P/C Strips
11 Type F Type F Type F

No. Description Date Architects


Project Title: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Bader Planners
Rehabilitation / Completion and Outfitting Work for Drivers/Security/ A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Waiting Area Lounge Date: August, 2016
SL/ADB/ST-26
For Sierra Leone Field Office of the African Foundation Structural Drawn by: BWB
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Layout Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 30 Printed on: August, 2016
NOTES:-

R S T U
8600

10
C6 C6 C6 C6
4450

LEGEND:-
Columns
Floor Slab 150mm thick with
12mm rod meshed at 150mm
spacing C-C

C6 C6 C6 C6
11

No. Description Date Architects


Project Title: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Bader Planners
Rehabilitation / Completion and Outfitting Work for Drivers/Security/ A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Waiting Area Lounge Date: August, 2016
SL/ADB/ST-27
For Sierra Leone Field Office of the African R/C Floor Slab Drawn by: BWB
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 30 Printed on: August, 2016
NOTES:-
300

300
SECTION K-K

900
300 300 300

300 300 300


900

300
300

300

BEAM TYPE F
Varies

900

COLUMN TYPE C6

No. Description Date Architects


Project Title: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Bader
Rehabilitation / Completion and Outfitting Work for Drivers/Security/ A Planners
Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Waiting Area Lounge Date: August, 2016
SL/ADB/ST-28
For Sierra Leone Field Office of the African Structural Details Drawn by: BWB
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Drawing status: Design: Tender: Contract / Construction: Scale: Not To Scale Printed on: August, 2016
NOTES:-
2300

C7 C7
Type G
C7 C7
Type G

Type G
1550

C7 C7 C7 C7

LEGEND:-
Columns

Beams
Footing

P/C Strips
Floor Slab 100mm thick with
16mm rod meshed at 150mm
spacing C-C

Y16-200P B1 100

Y16-200P B2
No. Description Date Architects
Project Title: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Rehabilitation / Completion and Outfitting Work for Back Security Post A
Bader Planners
Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Foundation Structural Date: August, 2016

For Sierra Leone Field Office of the African Layout,Ground Floor Drawn by: BWB
SL/ADB/ST-29
Slab & Suspended Checked by: SDD Sheet Size: A3
Development Bank (ADB)
Slab Details Drawing status: Design: Tender: Contract / Construction: Scale: Not To Scale Printed on: August, 2016
NOTES:-
200

200
SECTION K-K

800
300 200 300

300 200 300


800

200
200

200

BEAM TYPE G
Varies

800

COLUMN TYPE C7
No. Description Date Architects
Project Title: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Bader Planners
Rehabilitation / Completion and Outfitting Work for A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Back Security Post Date: August, 2016

For Sierra Leone Field Office of the African Structural Details Drawn by: BWB
SL/ADB/ST-30
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Drawing status: Design: Tender: Contract / Construction: Scale: Not To Scale Printed on: August, 2016
NOTES:-

2000

1500
Y16-200P T1
Y16-200P T2
300

Y16-200P B1
Y16-200P B2

No. Description Date Architects


Project Title: Drawing Title: Realini
1.0 Description dd-mm-yyyy R B Engineers
Bader Planners
Rehabilitation / Completion and Outfitting Work for Concrete Plinth For A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Fire Hydrant Pump Date: August, 2016
SL/ADB/ST-31
For Sierra Leone Field Office of the African Layout Drawn by: BWB
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 30 Printed on: August, 2016
NOTES:-

STAIRCASE No. 1 STAIRCASE No: 2


BENDING DETAILS BENDING DETAILS

Number Number

t)

t)
s(

s(
)

)
R
R

)
ON

ON
(m

(m
(m

(m
as

MMETE

as
MMETE
BAR BAR

t
TI

TI
Symbol (m) Symbol (m)

en

en
tal

tal
lm

lm
th

th
ts

ts
CA

CA

AM
AM

en

ng

en

ng
MARK MARK

m
bto

bto
ta

ta
ele

ele
LO

LO
m

m
Le

Le
DI
DI

Total Total

To

To
Su

Su
ele

ele
e

e
th

th
of

of
in

in
2000 1500
02 12 4.783 3283 0.133
BUTTOM 10 2 28 133.924
01 BUTTOM 12 10 3 30 7.389 221.67 3589 0.230
1800

1750 1500
02 12 14 2 28 2.000 56.00 125 125 0.266 03 BUTTOM 12 10 1 10 2.100 21.000 600 0.021

2000
03 TOP 12 10 1 10 2.450 24.50 0.024 1500
04 TOP 12 10 1 10 2.100 600 0.024
450 21.000

04 TOP 12 10 1 10 2.450 24.50 450 0.024


05 BUTTOM 12 44 1 10 2.000 20.000 125 1750 125 0.020
2000

2000
BUTTOM 10 10 2.600 26.00 600 0.01 450

P
05 12 1 10.25

TO
50 10 0.010

M
06 10 1 1.025
125

O
450

TT
BU
3250
06 12 10 1 10 2000 0.01
TOP 2.600 26.00 600 3280
07 BUTTOM 12 10 1 10 8.030 80.300 0.080
1500

2000
07 TOP 12 10 1 10 2.600 600 0.01
26.00

450
P

50 1 50 26.00
TO

2.600 125
M

08 10 450 0.01
O
TT
BU

Project Title: Drawing Title: No. Description Date Architects


1.0 Description dd-mm-yyyy
Realini Engineers
R B Bader Planners
Rehabilitation / Completion and Outfitting Work for A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Staircase No.1 & 2 Date: August, 2016
SL/ADB/ST-32
For Sierra Leone Field Office of the African Bending Details Drawn by: PH
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 30 Printed on: August, 2016
NOTES:-

LIFT ROOF SLAB


BENDING DETAILS

Number

(t)
)
R

)
ON

ss
(m
(m
MMETE

ma
BAR

t
TI
Symbol (m)

en

tal
th
s
CA

t
AM

en

ng
m
MARK

bto

tal
ele
LO

Le
DI
Total

To
Su
ele
e
th

of
in
2975

200
01 TOP 12 80 1 80 3.4 269 1.216

2975 LIFT SHAFT


02 TOP 12 1 3.4 0.266 BENDING DETAILS

200
80 80 269

Number

(t)
)
R

)
ON

(m

s
(m

as
MMETE
BAR

200

t
TI
3.4 Symbol (m)

en

tal

m
80 80

th
0.678

ts
03 BOTTOM 16 1 269

CA

AM

en

ng
MARK

bto

tal
ele
LO

Le
DI
Total

To
2975

Su
ele
e
th

of
in
200
04 BOTTOM 16 80 1 80 3.4 269 0.678
05 Front 12 136 1 136 9 507.3 9 1.216
2975

06 Back 12 136 1 136 9 507.3 9 0.266

2250

200
LIFT SHAFT BASE
07 Front 12 68 1 68 5.2 348.8 0.678
BENDING DETAILS 2250

Number

(t)
m)
R

)
ON

2250

ss
(m
MM ETE

200
al (

ma
BAR
t
TI

Symbol (m)
en

th

5.13 0.678
ts

12 136 1 136 348.8


CA

08 Back
tot
AM

en

ng

MARK
m

2250

tal
ele
LO

b
Le
DI

Total

To
Su
ele
e
th

of
in

2475
125

01 TOP 12 34 1 34 2.73 93 1.216

2475
02 BUTTOM 12 34 1 34 2.73 93 0.266
125
RS

100
BA

10 100

03 10 4 1 4 0.5 2 0 0.01
10
ER
AC

0
SP

Project Title: Drawing Title: No. Description Date Architects


1.0 Description dd-mm-yyyy
Realini Engineers
R B Bader Planners
Rehabilitation / Completion and Outfitting Work for Lift Shaft Base & A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Slab Bending Date: August, 2016
SL/ADB/ST-33
For Sierra Leone Field Office of the African Details Drawn by: PH
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 30 Printed on: August, 2016
NOTES:-

Water tank Mezzanine Floor Slab Roof Slab & Parapet Water Tank
BENDING DETAILS BENDING DETAILS

Number Number

t)

t)
(

(
)

)
R

R
)

)
N

N
(m

ss

(m

ss
(m

(m
MMETE

MMETE
O

O
ma

ma
BAR BAR

t
TI

TI
Symbol (m) Symbol (m)

en

en
tal

tal
th

th
ts

ts
CA

CA
AM

AM
ng

ng
en

en
m

m
MARK MARK

bt o

bt o
tal

tal
ele

ele
LO

LO
m

m
Le

Le
DI

DI
Total Total

To

To
Su

Su
ele

ele
e

e
th

th
of

of
in

in
2650 5300

150

150
TOP 27 1 27 2.950 71.50 0.071 01 TOP 27 1 27 5.600 151.20 0.150

150

150
12 12

150

150
150

150
BOTTOM 16 27 1 27 2.950 71.50 0.071 02 BOTTOM 16 35 1 35 4.200 147.00 0.140
2650 3900

3900
TOP 12 19 1 19 4.200 79.80 0.079

150

150
150
150
BOTTOM 16 19 1 19 4.200 79.80 0.079 Roof Slab & Parapet Water Tank
3900 BENDING DETAILS

Number

(t)
2688

)
R

)
ON

ss
(m
(m
MMETE
TOP 12 1 13

150

ma
13 37.70 150 0.037 BAR

t
2.988

TI
Symbol (m)

en

tal
th
ts
CA

AM

en

ng
m
MARK

bto

tal
ele
LO

Le
DI
Total

To
Su
ele
e
th

of
in
150
150

BOTTOM 16 19 1 18 2.988 53.78 0.053 5300

150

150
M
TO
2688 01 16 35 1 27 5.600 151.20 0.150

O
TT
BO
1775

150

150
13

P
TOP 12 1
150
150

13 2.075 26.98 0.027 M

TO
02 O 16 35 1 35 4.200 147.00 0.140
TT
BO 3900

AL AL
T

RT ZO ET
N

500
IC NT
VE RI AP
O
150

FR
150

08 12 35 1 35 4.200 147.00 0.07

HOPAR
BOTTOM 16 18

K
18 1 2.075 37.35 0.037

C
BA
2000
1775

Project Title: Drawing Title: No. Description Date Architects


1.0 Description dd-mm-yyyy
Realini Engineers
R B Bader Planners
Rehabilitation / Completion and Outfitting Work for Water Tank A Associates Limited 72 Wellington Street, Freetown
Office Building at Regent Road, Hill Station, Freetown Mezzanine Slab & Date: August, 2016
SL/ADB/ST-34
For Sierra Leone Field Office of the African Typical Slab Drawn by: PH
Checked by: SDD Sheet Size: A3
Development Bank (ADB) Bending Details Drawing status: Design: Tender: Contract / Construction: Scale: 1 : 30 Printed on: August, 2016

You might also like