You are on page 1of 1

Details Total Contract

Tons 540 1080


FOB 1075 1075
Contract Value 580500 1161000
Advance 58050 116100 VESSEL TRAVEL DATES
1st Shipment DEPARTURE ARRIVAL VESSEL / VOYAGE NO. TRANSIT
Shipment 81 162
Value 87075 174150
25TH MAR 2023 28TH APR 2023 MSC RIONAWB312R 34 DAYS
88% Payment 76626 153252
Payment Date 3rd April
Final Payment 1741.5 3483 2% Payment 1st week of May

1ST APR 2023 5TH MAY 2023 MSC RIONAWB313R 34 DAYS

8TH APR 2023 13TH MAY 2023 MSC RIONAWB314R 35 DAYS


2nd Shipment
Shipment 108 216
Value 116100 232200
15TH APR 2023 19TH MAY 2023 MSC RIONAWB315R 34 DAYS
88% Payment 102168 204336
Payment Date 17th April
Final Payment 2322 4644 2% Payment 4th Week of May

22ND APR 2023 26TH MAY 2023 MSC RIONAWB316R 34 DAYS


3rd Shipment
Shipment 108 216
Value 116100 232200
29TH APR 2023 2ND JUN 2023 MSC RIONAWB317R 34 DAYS
88% Payment 102168 204336
Payment Date 5th May
Final Payment 2322 4644 2% Payment 2nd Week of June

6TH MAY 2023 10TH JUN 2023 YET TO DECLARE 34 DAYS

4th Shipment
Shipment 135 270
Value 145125 290250
13TH MAY 2023 17TH JUN 2023 YET TO DECLARE 34 DAYS
88% Payment 127710 255420
Payment Date 19th May
Final Payment 2902.5 5805 2% Payment 4th Week of June

20TH MAY 2023 23TH JUN 2023 YET TO DECLARE 34 DAYS

5th Shipment
Shipment 108 216
Value 116100 232200
27TH MAY 2023 30TH JUN 2023 YET TO DECLARE 34 DAYS
88% Payment 102168 204336
Payment Date 2nd June
Final Payment 2322 4644 2% Payment 1st Week of July

You might also like