Rastanura New Building Renovation Expenses

SL Description Cost (SAR) Total Amount (SAR)


1 Key Chain 15 15.00
2 Transport Charge 100 115.00
3 Labour Charge 250 365.00
4 Electric & Plumbing Labour Charge 700 1065.00
5 Painting Labour Charge 2700 3765.00
6 Arm strong (Fall ceiling) 3690 7455.00
7 Carpet 1187.54 8,642.54
8 Painting Material 2283 10,925.54
9 Plumbering & Electrical Material 1983 12,908.54

Amount Balance Amount


Advance payment
8000.00 4,908.54

Received Amount Balance Amount


Final Payment
4,908.54 0.00