Professional Documents
Culture Documents
DRAINS
21.01 Excavation for Open Drains
21.01(a) Excavate soft material depth up to 1.5m below the m3 112,000.00 4.51 489,966.40 4,500 6,006.00 10,506.00 20,295.00 27,087.06 47,382.06 444,005.80 101,494.00
surface level
21.01(b) Extra over Subitem 21.01 (a) for excavation in rock as m3 5,000.00 19.15 92,877.50 0 0.00 0.00 0.00 0.00 92,877.50 5,000.00
defined in Ciause 3603, irrespective of depth
21.03 Excavation for Subsoil Drainage Systems
21.03(a)(i) Excavating soft material situated up to 1.5 m below the m3 150.00 10.85 1,578.68 0 0.00 0.00 0.00 0.00 1,578.68 150.00
surface level
21.03(a)(ii) Excavating soft material Exceeding 1.5 m and up to 3.0 m3 150.00 13.55 1,971.53 0 0.00 0.00 0.00 0.00 0.00 1,971.53 150.00
m below the surface level
21.04 Impermeable backfilling to subsoil drainage system m3 255.00 20.64 5,105.30 0 0.00 0.00 0.00 0.00 5,105.30 255.00
21.06 Natural permeable material in subsoil drainage
systems(crushed stone)
21.06(a) Crushed stone obtained from approved sources on the m3 45.00 52.39 2,286.82 0 0.00 0.00 0.00 0.00 2,286.82 45.00
site, Type A
21.08 Pipes in subsoil drainage systems
21.08(b) Unplasticised PVC pipes and fittings, normal duty, m 200.00 26.66 5,172.04 0 0.00 0.00 0.00 0.00 5,172.04 200.00
complete with couplings, 150mm diameter, slotted.
21.09 Polyethylene sheeting, 0.15 mm thick, or similar m2 380.00 6.27 2,311.12 0 0.00 0.00 0.00 0.00 2,311.12 380.00
approved material, for lining subsoil drainage system
PREFABRICATED CULVERTS
22.01 Excavation
22.01(a)(i) Excavate soft material depth up to 1.5m below the m3 60,000.00 8.11 472,002.00 12,059.70 959.80 13,019.50 94,870.04 7,550.46 102,420.50 369,581.50 46,980.50
surface level
22.01(a)(ii) Excavate soft materia! depth exceeding 1.5m and up to m 3
30,000.00 9.73 283,143.00 3,073.59 146.90 3,220.49 29,008.85 1,386.46 30,395.31 252,747.69 26,779.51
3.0m below the surface level
22.01(a)(iii) Excavate soft material depth exceeding 3.0m and up to m 3
15,000.00 12.16 176,928.00 508.80 0.00 508.80 6,001.40 0.00 6,001.40 170,926.60 14,491.20
4.5m below the surface level
22.01(b) Extra over Subitem 22.01(a) for excavation in rock as m3 110.00 20.83 2,222.56 0 0.00 0.00 0.00 0.00 2,222.56 110.00
defined in Clause 3603, irrespective of depth
22.02 Backfilling
22.02(a) Using excavated material m3 180.00 8.48 1,480.61 180.00 180.00 1,480.61 0.00 1,480.61 0.00 0.00
22.02(b) Using imported selected material m3 90,000.00 14.26 1,244,898.00 13,309.79 956.30 14,266.09 184,103.68 13,227.73 197,331.41 1,047,566.59 75,733.91
22.03 Concrete Pipe Culverts
22.03(a)(i) New concrete pipe culvert 600mm dia. on Class A m 2,000.00 149.05 289,157.00 0.00 0.00 0.00 0.00 0.00 289,157.00 2,000.00
bedding
22.03(a)(ii) New concrete pipe culvert 900mm dia. on Class A m 5,500.00 245.23 1,308,302.05 1,669.00 103.00 1,772.00 397,010.20 24,500.93 421,511.13 886,790.92 3,728.00
bedding
22.03(a)(iii) Extend concrete culvert pipes 600mm dia. on Class A m 0.00 203.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
bedding
22.03(a)(iv) Extend concrete culvert pipes 900mm dia. on Class A m 0.00 417.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
bedding
22.04 Metal Culverts
22.04(a)(i) Extend metal culvert pipes 500mm dia. m 0.00 257.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
22.04(a)(ii) Extend metal culvert pipes 600mm dia. m 0.00 199.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
22.04(a)(iii) Extend metal culvert pipes 900mm dia. m 450.00 247.66 108,103.59 39.00 4.00 43.00 9,368.98 960.92 10,329.90 97,773.69 407.00
22.07 Cast In Situ Concrete and Formwork
22.07(a) In Class A bedding, screeds, haunching and encasing m 3
5,000.00 189.04 916,844.00 1,447.40 113.20 1,560.60 265,408.00 20,757.35 286,165.35 630,678.65 3,439.40
for pipes, including formwork, Class 20/40
22.07(c)(i) In inlet and outlet structures, catchpits, manholes, thrust m 3
1,400.00 176.39 239,537.62 225.45 37.20 262.65 38,574.11 6,364.86 44,938.97 194,598.65 1,137.35
and anchor blocks, excluding formwork but including
Class U2 surface finish, Class 25/20
22.07(c)(ii) In extension of rectangular culverts, excluding formwork m3 5.00 344.65 1,671.55 0.00 0.00 0.00 0.00 0.00 1,671.55 5.00
but including Class U2 surface finish, Class 25/20
CONTRACTOR: Reynolds Construction Company (NIG) Ltd
Contract No: EH/HW/C004
23.01(b) Type B 150mm by 75mm footpath edging (drawing no. m 11,850.00 10.18 117,014.01 0.00 0.00 0.00 0.00 0.00 117,014.01 11,850.00
Gen/09/2)
23.07 Trimming of Excavations for Concrete Lined Open
Drains
23.07(a) In soft material as defined in Clause 3603 m2 30,900.00 1.59 47,657.07 0.00 0.00 0.00 0.00 0.00 47,657.07 30,900.00
23.07(b) In rock as defined in Clause 3503 m2 3,700.00 10.80 38,761.20 0.00 0.00 0.00 0.00 0.00 38,761.20 3,700.00
23.08(a) Insitu concrete lining to standard lined open drains or m3 3,700.00 150.38 539,713.82 0.00 0.00 0.00 0.00 0.00 539,713.82 3,700.00
channel drains class 25/20
23.09 Formwork to insitu concrete lining for open drains class
F2 finish
23.09(a) To sides with formwork on the internal face only m2 23,300.00 7.21 162,953.21 0.00 0.00 0.00 0.00 0.00 162,953.21 23,300.00
23.12 Steel Reinforcement
23.12(a) Mild steel bars t 8.00 1,261.04 9,785.67 0.00 0.00 0.00 0.00 0.00 9,785.67 8.00
23.12(c) Welded steel fabric t 2.00 2,507.65 4,864.84 0.00 0.00 0.00 0.00 0.00 4,864.84 2.00
23.16(i) Small Side drain pedestrian crossing no. 18.00 132.65 2,316.07 0.00 0.00 0.00 0.00 0.00 2,316.07 18.00
23.16(ii) Large Side drain pedestrian crossing no. 72.00 159.17 11,116.43 0.00 0.00 0.00 0.00 0.00 11,116.43 72.00
23.17 Precast cover slabs to channel drains no. 140.00 113.69 15,439.10 0.00 0.00 0.00 0.00 0.00 15,439.10 140.00
PITCHING, STONEWORK AND PROTECTION
AGAINST EROSION
25.01 Stone Pitching
25.01(b) Grouted stone pitching 250mm thick m2 1,700.00 25.08 41,356.92 60.00 468.80 528.80 1,459.66 11,404.78 12,864.43 28,492.49 1,171.20
25.03 Stone Masonry Wall
25.03(b) Cement-mortared stone walls m 3
20.00 108.09 2,096.95 0.00 0.00 0.00 0.00 0.00 2,096.95 20.00
25.04 Concrete pitching and Block Paving
25.04(d) Prefabricated concrete paving blocks for sidewalk m 2
1,445.00 25.08 35,153.38 0.00 0.00 0.00 0.00 0.00 35,153.38 1,445.00
pavement (50mm thick)
CONTRACTOR: Reynolds Construction Company (NIG) Ltd
Contract No: EH/HW/C004
26.02 Surface preparation for bedding gabions m2 600.00 3.65 2,124.30 0 0.00 0.00 0.00 0.00 2,124.30 600.00
26.03(a) Galvanised Gabion boxes, of any size m3 150.00 78.42 11,410.11 0 0.00 0.00 0.00 0.00 11,410.11 150.00
26.03(c) Galvanised Gabion mattresses, of any size m3 150.00 113.96 16,581.18 0 0.00 0.00 0.00 0.00 16,581.18 150.00
CLEARING, GRUBBING AND REMOVAL OF
TOPSOIL
31.01 Clearing, Grubbing and Removal of Topsail
31.01(a) Clearing and grubbing ha 236.00 4,248.41 972,546.02 90.18 0.72 90.90 240,638.79 133,936.15 374,574.94 597,971.07 145.10
31.01(b) Removal of topsoil m3 240,000.00 4.83 1,124,424.00 112,287.00 6,059.41 118,346.41 526,075.82 28,388.94 554,464.77 569,959.23 121,653.59
31.04 Re-erection of fences and gates m 20,000.00 31.35 608,190.00 18,915.00 1,400.00 20,315.00 575,195.69 42,573.30 617,768.99 -9,578.99 -315.00
31.05 Re-erection of signboards no. 2,000.00 156.73 304,056.20 36.00 0.00 36.00 5,473.01 0.00 5,473.01 298,583.19 1,964.00
REMOVAL OF EXISTING STRUCTURES
32.01 Removal of Existing Structures
32.01(a) Removal of existing pipe culverts of any size m 3,500.00 62.94 213,681.30 1,292.83 90.10 1,382.93 78,929.60 5,500.77 84,430.37 129,250.93 2,117.07
BREAKING UP EXISTING PAVEMENT LAYERS
33.01 Excavating or Milling of Material from an Existing
Pavement
33.01(a) Granular material m3 0.00 5.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
33.01(b) Bituminous material m3 0.00 11.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
33.04 Scarifying and recompaction of existing pavement m3 346,500.00 4.90 1,646,914.50 67,249.60 1,766.66 69,016.26 319,637.35 8,396.93 328,034.28 1,318,880.22 277,483.74
layers, depth as shown on drawings, compaction to
95% BS-heavy density
EARTHWORKS
36.01 Excavations
36.01(a) Common excavation to spoil m3 300,000.00 3.96 1,152,360.00 205,862.46 13,818.42 219,680.88 790,758.88 53,079.31 843,838.20 308,521.80 80,319.12
36.01(b) Excavation in swamps or wetlands to spoil m3 70,000.00 8.72 592,088.00 10,350.50 0.00 10,350.50 87,548.67 0.00 87,548.67 504,539.33 59,649.50
36.01(c) Rock excavation m3 9,000.00 21.62 188,742.60 165.00 0.00 165.00 3,460.28 0.00 3,460.28 185,282.32 8,835.00
36.02 Fill and Improved Subgrade Layers
36.02(a) Improved subgrade layer as specified in the drawings to m3 85,775.00 5.85 486,730.24 88,563.15 2,146.83 90,709.98 502,551.59 12,182.19 514,733.78 -28,003.54 -4,934.98
require minimum G15 quality
36.02(b) Fill as specified in the drawings to require minimum G7 m3 500,000.00 5.26 2,551,100.00 197,447.81 3,930.36 201,378.17 1,007,418.22 20,053.48 1,027,471.70 1,523,628.30 298,621.83
quality material
36.02(d) Fill or improved subgrade layer using rock fill (swamp m 3
45,000.00 26.21 1,144,066.50 2,352.30 0.00 2,352.30 59,804.17 0.00 59,804.17 1,084,262.33 42,647.70
areas)
36.02(h) Pioneer layer m 3
5,000.00 29.15 141,377.50 165.00 0.00 165.00 4,665.46 0.00 4,665.46 136,712.04 4,835.00
36.03 Roadbed Preparation and Compaction of Material
36.03(a) Compaction to 97% of BS-Heavy Density m 3
108,700.00 3.09 325,806.51 0.00 0.00 0.00 0.00 0.00 325,806.51 108,700.00
36.03(c) Compaction to 93% of BS-Heavy Density m3 330,000.00 2.65 848,265.00 100,215.60 1,246.07 101,461.67 257,604.20 3,203.02 260,807.22 587,457.78 228,538.33
36.04 Swamp Treatment
36.04(a) Scrape off existing bituminous surface at specified m2 31,000.00 0.78 23,454.60 0.00 0.00 0.00 0.00 0.00 23,454.60 31,000.00
swamps and dispose
36.04(b) Provide and place filter layer of crushed rock at m 3
18,000.00 36.03 629,083.80 0.00 0.00 0.00 0.00 0.00 629,083.80 18,000.00
specified swamps
36.04(c) Provide gravel regulating layer over filter layer at m3 6,200.00 10.09 60,681.26 0.00 0.00 0.00 0.00 0.00 60,681.26 6,200.00
specified swamps.
36.04(d) Provide and place geotextile filter fabric PROVISIONAL m2 500,000.00 6.20 3,100,000.00 33,480.00 0.00 33,480.00 207,576.00 0.00 207,576.00 2,892,424.00 466,520.00
42.01(b) Bitumen for asphalt concrete surfacing, 60/70 t 6,660.00 698.98 4,515,550.60 0.00 0.00 0.00 0.00 0.00 4,515,550.60 6,660.00
penetration grade
42.03 Tack coat of K1-70 emulsion (0.4 litre/m 2) I 921,500.00 0.90 804,469.50 0.00 0.00 0.00 0.00 0.00 804,469.50 921,500.00
42.06 Variations in active filler content t Rate only 231.59 0.00 0.00 0.00 0.00 0.00 0.00
42.05 DBM Binder Course
42.05(a) Provide and lay Dense Bitumen Macadam as binder m3 119,200.00 72.06 8,331,865.44 5,920.00 3,861.27 9,781.27 413,797.34 269,895.82 683,693.17 7,648,172.27 109,418.73
course (nominal binder content 4.5%)
42.05(b) Bitumen for DBM Binder Course, 60/70 penetration t 12,016.00 698.98 8,146,975.37 605.08 372.03 977.11 410,250.65 252,242.56 662,493.22 7,484,482.15 11,038.89
grade
SINGLE SURFACE DRESSINGS
Single seal surface treatment
44.01 Single seals, 80/100 penetration bitumen binder, hot
sprayed application rate 1.10 Mm1
44.01(b) Using 10mm aggregate m2 625,200.00 1.64 994,568.16 0.00 0.00 0.00 0.00 0.00 994,568.16 625,200.00
44.02 Single Seals Bituminous Binder Variations
44.02(b) 80/100 penetration grade bitumen I Rate only 0.71 0.00 0.00 0.00 0.00 0.00 0.00
44.02(h) Precoating fluid, kerosene and diesoline I Rate only 2.02 0.00 0.00 0.00 0.00 0.00 0.00
44.03 Single Seals Aggregate Variations
44.03(b) Using 10mm aggregate t Rate only 16.62 0.00 0.00 0.00 0.00 0.00 0.00
44.05 Precoating of aggregates (precoating fluid kerosene t 688.00 1,405.16 937,747.58 0 0.00 0.00 0.00 0.00 937,747.58 688.00
and diesoline applied at 85 litres/tonne)
DOUBLE SURFACE DRESSINGS
45.01 Double Surface Dressing Using:
45.01(b) 14mm & 7mm aggregate in 1st & 2nd layers respectively m2 34,900.00 5.04 170,619.12 0 0.00 0.00 0.00 0.00 170,619.12 34,900.00
and 80/100 penetration bitumen binder, application
rates 1.4 l/m2 & 0.9 Urn2 for 1st & 2nd layers respectively
45.02 Bituminous Binder Variation:
45.02(c) 80/100 penetration grade bitumen I Rate only 0.78 0 0.00 0.00 0.00 0.00
45.03 Aggregate Variation:
45.03(b) 14mm nominal size aggregate t Rate only 16.62 0 0.00 0.00 0.00 0.00
45.03(c) 7mm nominal size aggregate t Rate only 12.40 0 0.00 0.00 0.00 0.00
CONTRACTOR: Reynolds Construction Company (NIG) Ltd
Contract No: EH/HW/C004
52.06 Remove existing guardrails m 9,560.00 5.44 50,446.21 1,823.0 1,823.00 9,619.61 0.00 9,619.61 40,826.60 7,737.00
ROAD SIGNS
54.01(a)(i) Triangular warning road sign, 0.35m2 on single post no. 12.00 204.79 2,383.76 0 0.00 0.00 0.00 0.00 2,383.76 12.00
54.01(a)(ii) Triangular warning road sign, 0.52m2 on single post no. 20.00 204.79 3,972.93 0 0.00 0.00 0.00 0.00 3,972.93 20.00
54.01(b)(i) Circular regulatory road sign, 0.44m 2 on single post no. 7.00 216.29 1,468.61 0 0.00 0.00 0.00 0.00 1,468.61 7.00
54.01(b)(ii) Circular regulatory road sign, 0.64m 2 on single post no. 19.00 216.29 3,986.22 0 0.00 0.00 0.00 0.00 3,986.22 19.00
54.01(c)(i) Rectangular informatory road sign, 0.24m 2 on single no. 6.00 219.42 1,277.02 0 0.00 0.00 0.00 0.00 1,277.02 6.00
post
54.01(c)(ii) Rectangular informatory road sign, 0.25m 2 on single no. 7.00 219.42 1,489.86 0 0.00 0.00 0.00 0.00 1,489.86 7.00
post
54.01(c)(iii) Rectangular informatory road sign, 0.77m 2 on two posts no. 20.00 360.48 6,993.31 0 0.00 0.00 0.00 0.00 6,993.31 20.00
54.01(d)(i) Rectangular supplentary plate, 0.88m 2 on existing posts no. 10.00 360.48 3,496.66 0 0.00 0.00 0.00 0.00 3,496.66 10.00
54.01(d)(ii) Rectangular supplentary plate, 1.2m 2 on existing posts no. 10.00 417.94 4,054.02 0 0.00 0.00 0.00 0.00 4,054.02 10.00
54.03 Guidance Signs m2 31.00 417.94 12,567.46 0 0.00 0.00 0.00 0.00 12,567.46 31.00
54.05 Removal of obsolete road signs no. 100.00 26.12 2,533.64 0 0.00 0.00 0.00 0.00 2,533.64 100.00
ROAD MARKINGS
53.03 Road Markings Using Thermo-plastic Road Marking
Material
55.03(a)(i) White lines, broken, 100mm wide m 1,000.00 1.44 1,396.80 0 0.00 0.00 0.00 0.00 1,396.80 1,000.00
55.03(a)(ii) White lines, unbroken, 100mm wide m 309,600.00 1.41 423,439.92 0 0.00 0.00 0.00 0.00 423,439.92 309,600.00
55.03(a)(iii) White lines, broken, 200mm wide m 460.00 2.40 1,070.88 0 0.00 0.00 0.00 0.00 1,070.88 460.00
55.03(a)(iv) White lines, broken, 400mm wide m 460.00 4.93 2,199.77 0 0.00 0.00 0.00 0.00 2,199.77 460.00
55.03(b)(i) Yellow lines, broken, 100mm wide m 126,840.00 1.49 183,321.85 0 0.00 0.00 0.00 0.00 183,321.85 126,840.00
55.03(b)(ii) Yellow lines, unbroken, 100mm wide m 27,360.00 1.46 38,747.23 0 0.00 0.00 0.00 0.00 38,747.23 27,360.00
55.03(d) White lettering or symbols m2 50.00 24.43 1,184.86 0 0.00 0.00 0.00 0.00 1,184.86 50.00
55.03(f) Traffic island markings, any colour m2 50.00 24.43 1,184.86 0 0.00 0.00 0.00 0.00 1,184.86 50.00
55.06 Setting out and pre-marking lines (excluding traffic m 465,720.00 0.23 103,902.13 0 0.00 0.00 0.00 0.00 103,902.13 465,720.00
island markings, lettering and symbols)
55.09 Rumble Strips and Speed Humps 0 0.00
55.09(a) Rumble Strips, 500mm wide and 15mm high (drawing m 480.00 41.79 19,457.42 0 0.00 0.00 0.00 0.00 19,457.42 480.00
no. Gen/18)
55.09(b) Speed humps, 6000mm wide and 100mm high (drawing m 80.00 125.38 9,729.49 0 0.00 0.00 0.00 0.00 9,729.49 80.00
no. Gen/18)
LANDSCAPING AND GRASSING
56.03 Preparing the Area for Grassing
56.03(c)(i) Topsoiling embankments m3 28,000.00 4.49 121,948.40 3,168.40 3,168.40 13,799.33 0.00 13,799.33 108,149.07 24,831.60
56.04 Grassing
56.04(a) Planting of grass cuttings ha 38.00 4,179.45 154,054.53 0.00 0.00 0.00 0.00 0.00 154,054.53 38.00
64.26 Minor structural repairs to existing bridges Prov. 1.00 4,350.00 4,350.00 0 0.00 0.00 0.00 0.00 4,219.50 1.00
Sum
CONTRACTOR: Reynolds Construction Company (NIG) Ltd
Contract No: EH/HW/C004
81.16 Ditto but7.5-9.7 m3/min hr 100.00 22.16 2,149.52 0 0.00 0.00 0.00 0.00 2,149.52 100.00
81.17 Ditto but 9.8-25.5 m 3/min hr 50.00 86.06 4,173.91 0 0.00 0.00 0.00 0.00 4,173.91 50.00
81.18 Small dumpers, 751 kg - 1.2 tonne maker's rated hr 200.00 8.90 1,726.60 0 0.00 0.00 0.00 0.00 1,726.60 200.00
payload
81.19 Excavators, hydraulic crawler or wheel mounted, full hr 200.00 74.47 14,447.18 0 0.00 0.00 0.00 0.00 14,447.18 200.00
circle slew (back actor) 14.0 -17.0 t nominal weight of
machine
81.20 Excavators, hydraulic wheeled dual purpose backloader hr 100.00 28.69 2,782.93 0 0.00 0.00 0.00 0.00 2,782.93 100.00
with 0.6 - 0.8 m3 rated bucket capacity
81.21 Ditto but 0.81-1.0 m rated bucket capacity
3
hr 100.00 28.69 2,782.93 0 0.00 0.00 0.00 0.00 2,782.93 100.00
81.22 Pumps inclusive of all hoses, 50 - 76 mm diameter hr 100.00 4.09 396.73 0 0.00 0.00 0.00 0.00 396.73 100.00
delivery
81.23 Ditto but 77-101 mm diameter delivery hr 100.00 4.09 396.73 0 0.00 0.00 0.00 0.00 396.73 100.00
81.24 Tractors, rubber tyred including trailer, 50 -70 kw rated hr 200.00 15.03 2,915.82 0 0.00 0.00 0.00 0.00 2,915.82 200.00
flywheel
LOADERS: The basis of the loader classification is the
Society of Automotive Engineers of America (SAE)
rated capacity of the bucket. The classification is based
on the largest general purpose bucket offered by the
manufacturer
CONTRACTOR: Reynolds Construction Company (NIG) Ltd
Contract No: EH/HW/C004
15,270,965
* Previos months have been corrected to reflect the 3% discount.
7% 143,615.09
2,195,259.18
1.41 $3,095,315.44
CONTRACTOR: Reynolds Construction Company (NIG) Ltd
Contract No: EH/HW/C004
REMAIN TO EXCUTE
percent(%)
100.00%
100.00%
50.00%
0.00%
54.17%
57.22%
64.44%
59.44%
63.06%
50.00%
57.78%
56.67%
54.44%
100.00%
58.89%
CONTRACTOR: Reynolds Construction Company (NIG) Ltd
Contract No: EH/HW/C004
REMAIN TO EXCUTE
percent(%)
90.62%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
78.30%
89.27%
96.61%
100.00%
0.00%
84.15%
100.00%
67.78%
90.44%
68.79%
81.24%
100.00%
CONTRACTOR: Reynolds Construction Company (NIG) Ltd
Contract No: EH/HW/C004
REMAIN TO EXCUTE
percent(%)
100.00%
48.05%
100.00%
100.00%
68.88%
15.91%
69.55%
100.00%
100.00%
100.00%
95.29%
100.00%
65.35%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
68.89%
100.00%
100.00%
CONTRACTOR: Reynolds Construction Company (NIG) Ltd
Contract No: EH/HW/C004
REMAIN TO EXCUTE
percent(%)
100.00%
100.00%
100.00%
100.00%
100.00%
61.49%
50.69%
-1.58%
98.20%
60.49%
80.08%
26.77%
85.21%
98.17%
-5.75%
59.72%
94.77%
96.70%
100.00%
69.25%
100.00%
100.00%
100.00%
93.30%
0.00%
CONTRACTOR: Reynolds Construction Company (NIG) Ltd
Contract No: EH/HW/C004
REMAIN TO EXCUTE
percent(%)
85.18%
89.60%
-31.15%
100.00%
100.00%
100.00%
91.79%
91.87%
100.00%
100.00%
100.00%
CONTRACTOR: Reynolds Construction Company (NIG) Ltd
Contract No: EH/HW/C004
REMAIN TO EXCUTE
percent(%)
100.00%
100.00%
100.00%
100.00%
80.93%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
88.68%
100.00%
100.00%
CONTRACTOR: Reynolds Construction Company (NIG) Ltd
Contract No: EH/HW/C004
REMAIN TO EXCUTE
percent(%)
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
CONTRACTOR: Reynolds Construction Company (NIG) Ltd
Contract No: EH/HW/C004
REMAIN TO EXCUTE
percent(%)
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
CONTRACTOR: Reynolds Construction Company (NIG) Ltd
Contract No: EH/HW/C004
REMAIN TO EXCUTE
percent(%)
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%