Jade Residences Project Scope Matrix

Uploaded by

ldpolides90
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Project : JADE RESIDENCES

Location : Chino Roces Avenue, Brgy. Bangkal, Makati City


Client : SM Development Corporation
Date : November 21, 2023
Subject : Matrix of Scope

ANNEX TQ-A

EEI OWNER NSC


ITEM DESCRIPTION REMARKS
MATERIAL LABOR MATERIAL LABOR MATERIAL LABOR

I SITE WORKS
1.0 Site Clearing & Grubbing 
Demolition and relocation of any
obstruction not visible during the site
2.0 Demolition Works (based on actual physical site condition)  inspection such as, but not limited to,
underground utilities and structures shall
be charged separately.
3.0 Dewatering Works 
4.0 Bulk & Structural Excavation 
5.0 Hauling & Disposal of Excavated Materials 
6.0 Trimming Works 
7.0 Backfill and Compaction  
8.0 Slope Protection  
9.0 Gravel Bedding  
10.0 Lean Concrete  
11.0 Soil Treatment  

II STRUCTURAL WORKS
1.0 Ready- Mixed Concrete (Batching Only)    Cement - OSM
2.0 Reinforcement Bars   Rebar - OSM
3.0 Formworks  

III PRECAST AND MASONRY WORKS


1.0 Precast Wall Panel (Exterior)  
2.0 Shotcrete  
3.0 150mm thick Concrete Hollow Blocks  
4.0 100mm thick Concrete Hollow Blocks  

IV METAL WORKS AND STRUCTURAL STEEL


1.0 Stair Railings
1.01 Floor Mounted Hand Railing and Post   Finish up to Primer Paint only
1.02 Wall Mounted Railing   Finish up to Primer Paint only
2.0 Stair Nosing   Finish up to Primer Paint only
3.0 Trench Gratings   Finish up to Primer Paint only
4.0 Column Guard   Finish up to Primer Paint only
5.0 Ladder Rung
5.01 For Tanks   Finish up to Primer Paint only
5.02 For Elevator Pit   Finish up to Primer Paint only
6.0 Manhole Cover   Finish up to Primer Paint only
7.0 Hoisting Beam   Finish up to Primer Paint only
8.0 Steel Bollards   Finish up to Primer Paint only
9.0 Elevator Separator Beam   By Others
10.0 Balcony Railings   Finish up to Primer Paint only
11.0 ACCU Aluminum cover   Finish up to Primer Paint only
12.0 Structural Steel Framings for Canopies, if any Excluded. Insufficient Details
13.0 Hand/Grab Rail at Swimming Pool and Amenity Area   By Others

V THERMAL AND MOISTURE PROTECTION


1.0 Bentonite Waterproofing  
2.0 Integral Waterproofing  
3.0 Capillary Waterproofing  
4.0 Epoxy Tank Lining  
5.0 3mm Modified Polyurethane  
6.0 4.5 kg Torch Applied Waterproofing  
7.0 Anti-Root Waterproofing  
8.0 Thermal Insulation at Roof Deck  
9.0 Sound Insulation to Genset   By Others

VI ARCHITECTURAL FINISHES
1.0 Floor Finishes
1.01 Straight to Finish  
On areas to protect waterproofing to be
1.02 Concrete Topping to protect waterproofing  
installed by EEI only
1.03 Concrete Topping to receive tiles only   By Others
2.0 Wall Finishes
2.01 Rubbed Finish to Concrete Walls  
2.02 Plaster Finish to CHB Walls  
3.0 Ceiling Finishes
3.01 Rubbed Finish to Exposed Concrete Ceiling  

VII MISCELLANEOUS WORKS


1.0 Toilet Partition   By Others
2.0 Urinal Partitions   By Others
3.0 Toilet Accessories   By Others
4.0 Toilet Granite Countertop   By Others
5.0 Facial Mirror   By Others
6.0 Ficem Board Cladding   By Others
7.0 Interior and Exterior Signage   By Others
8.0 Fixed and Loose Furnitures   By Others
9.0 Isolation Pad to Genset   By Others
10.0 Ticket Booth including Parking Boom   By Others
11.0 Guard Houses   By Others
12.0 Aluminum and Glazing Works   By Others
13.0 Bumper Guard   By Others
14.0 Interior and Exterior Vertical Pipe Cladding   By Others

TECHNICAL QUALIFCATIONS PAGE 1 OF 2


"TQ"
EEI CORPORATION
Project : JADE RESIDENCES
Location : Chino Roces Avenue, Brgy. Bangkal, Makati City
Client : SM Development Corporation
Date : November 21, 2023
Subject : Matrix of Scope

ANNEX TQ-A

EEI OWNER NSC


ITEM DESCRIPTION REMARKS
MATERIAL LABOR MATERIAL LABOR MATERIAL LABOR

VIII EXCLUSIONS
A. General Works
1.0 All documents and bid bulletins received from September 20, 2023 and beyond.
2.0 Requirement for Covid-19 protocols intended for Client and Client's Representative.
3.0 Testing & Commissioning
4.0 Loading & unloading of OSM to be installed by NSC including distribution to designated areas.
5.0 Warehousing of OSM to be installed by NSC.
6.0 Embeds of NSC Requirements
7.0 MEPF embeds and roughing-ins
8.0 Modification of perimeter fence. See ANNEX TQ - D
9.0 Provision for Surge Tank at Amenity Level. Insufficient details.
10.0 Ground settlement monitoring during construction, if required
11.0 Demolition works and relocation of underground utilities and structures not visible during Site Inspection due to absence of as-built plans.
12.0 Mechanical Couplers
13.0 Trellis at Amenity Level. By Landscape Contractor
14.0 Trellis Base at 2nd Floor
15.0 Trellis Structural ( Insufficient Details )
16.0 Gondola and Other Components ( By others )
17.0 Relocation of Electrical Post
18.0 Fencing Permit If Required

B. Architectural Works
1.0 W-13 Plain Cement finish for Elevator Shaft and Pipe Chase
2.0 Finish paint to Metals
3.0 Swimming pool railing and finishes. By Others
4.0 Concrete topping to areas to receive tiles only. By Others.
5.0 Isolation Pad to Genset. By Others
6.0 Sound Insulation to Genset. By Others
7.0 Ticket Booth including Parking Boom. By Others
8.0 Interior and exterior Vertical Pipe Cladding. By Others
9.0 W78 and W78A Fully Louvered Walls, and other louver panels/cladding.
10.0 Wall Type W-91 or Retail/Commercial Temporary Board-up. See ANNEX TQ - H
11.0 WP06 High Grade Oil Resistant Epoxy Paint. By Paint Contractor.
12.0 WP08 Epoxy Hi Kote Paint. By Paint Contractor.
13.0 Waterproofing on Washing Machine Area. Not reflected in waterproofing key plan.
14.0 100mm thick Sound Insulation Wall Lining to Entertainment Hub.
15.0 Skim coating. By Painting Contractor

C. MEPF Works
1.0 Pipe Sleeving, block-outs and roughing-ins

TECHNICAL QUALIFCATIONS PAGE 2 OF 2


"TQ"
EEI CORPORATION