REPAIR WORK AT OBAYAN STREET YABA
Dear Sir,
Please find below both the Internal and External repair work.
QUOTATION FOR INTERNAL WORK
S/ DESCRIPTION AMOUNT (₦)
N
1 Remove the old plastering of the affected area in all the 150,000
flats and cart away
2 Re-plaster the affected area (Cement 15bags @ 8,300) 124,500
3 Provide Water Proof Solution 64,000
4 Provide P.O.P cement for re-screeding the affected area 69,000
5 Provide P.O.P paint 72,000
6 Provide Screeding Gum 96,000
7 Paint all the whole surface of the affected wall in all the 845,000
flats – 8 drums of quality paint @ 65,000 (Note: Ceiling
Painting not included)
8 Transportation 50,000
WORKMANSHIP
Mason 250,000
Screeder 200,000
Painter 750,000
Professional Charges 700,000
GRAND TOTAL 3,370,500
QUOTATION FOR EXTERNAL WORK
This includes:
- Change all the spoilt plumbing pipes
- Connect all the A.C. water into soakaway
- Re-Construct crack pillar
- Cast the entire compound
S/ DESCRIPTION AMOUNT (₦)
N
1 Provide 50 bags of Cement @ 8,300 415,000
2 Provide 45tons of Granite 975,000
3 Provide 40tons of Sharp/Sand 330,000
4 Remove the crack pillar cast new base, set new block & 250,000
plaster
5 Break all the crack area on the compound floor to fill the 150,000
vacuum below the hardcore before casting
6 Casting the surface to a depth of 75mm – 100mm 350,000
respectively
TOTAL 2470000
PLUMBING WORK
S/ DESCRIPTION AMOUNT (₦)
N
1 16 Pcs of 4" imported tee @ 1500 24,000
2 30 Length of 4" thick pipe @ 4,500 135,000
3 12 Pcs of 4" imported bend @ 1,200 14,400
4 6 Length of 2" thick pipe @ 2,500 15,000
5 30 Pcs of 2" imported bend @ 250 7,500
6 25 Pcs of 2" imported tee @ 300 7,500
7 20 Length of 1" pipe @ 1,500 30,000
8 10 Pcs of 1" pipe @ 1,500 2,500
9 14 Pcs of 1" tee @ 250 3,500
10 20 Pcs of 1" Socket @ 200 4,000
11 1 Big Abro Gum @ 12,000 12,000
Transportation 20,000
Workmanship 650,000
Supervision On All External Work 650,000
TOTAL 1575400