NTDC INTERNSHIP TEST 2023
1. NTDC was incorporated as Public Limited Company in .......... .
a) 1998
b) 1999
c) 2001
d) 2002
2. NTDC unbundled from .......... .
a) NEPRA
b) PEPCO
c) WAPDA
d) Ministry of Energy
3. NTDC is an autonomous body under the .......... .
a) Ministry of Energy (Power Division)
b) Ministry of Interior
c) Ministry of Finance (Consumer Division)
d) Ministry of Transmission & Networks
4. Current Minister of Energy is .......... .
a) Shah Mahmood Qureshi
b) Asad Umar
c) Fawad Chaudhry
d) Khurram Dastagir (Federal Minister)
(And Federal Secretary (Power Division) is Mr. Rashid Mahmood Langrial)
5. Chief Executive Head of NTDC is .......... .
a) Company Secretary NTDC
b) Chairman BoD NTDC
c) Managing Director NTDC
d) All of them
6. Current Managing Director of NTDC is .......... .
a) Eng. Dr. Rana Abdul Jabbar Khan
b) --
c) --
d) --
7. There are .......... Deputy Managing Directors in NTDC.
a) 2
b) 3
c) 1
d) 4
8. There are .......... number of Director Generals under GM HR.
a) One
b) Three
c) Five
d) None of them
(Correct Answer is Two)
9. Functional Head of NTDC Finance Department is .......... .
a) Chief Audit Officer
b) Chief Budget Officer
c) Chief Accounts Officer
d) Chief Financial Officer
10.NTDC is responsible for evacuation of power from .......... to the Power
Distribution Companies through Transmission Network.
a) Hydroelectric Power Plants
b) Thermal Units (GENCOs)
c) Private Sectors (IPPs)
d) All of them
(GENCOs stands for Generation Companies & IPPs stands for Independent
Power Producers)
11.The Largest Dam of Pakistan is .......... .
a) Diamer-Bhasha Dam
b) Mangla Dam
c) Tarbela Dam
d) Hub Dam
12.NTDC is .......... .
a) Power Producer
b) Power Regulator
c) Transmission Network Operator
d) All of them
13.NTDC was organized to take over all the properties, rights and assets
obligations and liabilities of .......... .
a) 220kV Grid Stations & Transmission Lines
b) 500kV Grid Stations & Transmission Lines
c) Both of them
d) None of them
14.NEPRA stands for .......... .
a) National Electric Power Rules Authority
b) National Electric Power Rules Agency
c) National Electric Power Regulatory Authority
d) National Electronic Power Regulatory Authority
15.NPCC stands for .......... .
a) National Procurement Control Center
b) National Production Control Center
c) National Power Control Center
d) None of them
16.TSG stands for .......... .
a) Technical Services Group
b) Transmission Services Group
c) Training Services Group
d) None of them
17.AD&M stands for .......... .
a) Asset Development & Management
b) Asset Monitoring & Development
c) Asset Management & Design
d) Asset Monitoring & Design
18.Total No. of Distribution Companies are .......... .
a) 9
b) 7
c) 11
d) 8
19.NTDC formation which looks after the operations and maintenance activities
of Grid Stations and Transmission Lines is .......... .
a) Project Delivery / GSC
b) Network Operation
c) T.S.G
d) Assest Managemnet / GSO
20.General Manager (Power System Planning) reports to .......... .
a) DMD (P&E)
b) MD
c) DMD (SO)
d) DMD (AD&M)
21.Rating of Auto-Transformer is specified in .......... .
a) Percentage (%)
b) Kilo Volts (kV)
c) Amperes (A)
d) MVA
22.In transformers, winding temperatures are always .......... than oil
temperature.
a) Higher
b) Lower
c) Equal
d) Unrelated
23.Tertiary Winding in Auto-Transformer is used for suppression of .......... .
a) 2nd Harmonics
b) 3rd Harmonics
c) 10th Harmonics
d) 9th Harmonics
24.Radiator Tubes in the transformer are meant for .......... .
a) Support of the Transformer
b) Providing Additional Insulation
c) Cooling the Transformer Oil
d) Reducing the Magnetizing Current
25.The purpose of Silica Gel in the breather of the transformer is to
remove .......... from the air.
a) Moisture
b) Dust
c) Carbon Dioxide
d) Oxygen
26.Tap-Changer is installed on .......... side of the Power Transformer.
a) High-Voltage
b) Low-Voltage
c) Primary
d) Secondary
27.The Principle Tap of the Power Transformer is .......... .
a) 1
b) 14
c) 27
d) None of the above
28.Differential Relay is installed on .......... .
a) Busbar
b) Transformer
c) Both a & b
d) Transmission Line
29.Buchholz Relay is installed on .......... .
a) Transformer
b) Transmission Line
c) Isolator
d) None of the above
30.The sequence of opening operation in the Grid Station is .......... .
A.CIRCUIT BREAKER IS OPENED, B. EARTH SWITCH IS CLOSED, C. ISOLATOR IS
OPENED.
a) ABC
b) ACB
c) BAC
d) BCA
31.The opening time of Circuit Breaker is approximately .......... .
a) 1 millisecond
b) 30 milliseconds
c) 5 second
d) 10 second
32.Trip Coil in the circuit breaker is to .......... the circuit breaker.
a) Close
b) Open
c) Lock
d) None of the above
33.Auto-Recloser recloses .......... .
a) Isolator
b) Circuit Breaker
c) Earth Switch
d) Transformer
34.In Extra High Voltage Circuit Breaker, .......... gas is used as a Quenching
Media.
a) Nitrogen
b) Sulfur Hexafluoride (SF6)
c) Carbon dioxide
d) Oxygen
35.In One and a Half Breaker Scheme, there are .......... breakers in one dia.
a) 1
b) 1.5
c) 2
d) 3
36.In One and a Half Breaker Scheme, there are .......... isolators in one dia.
a) 1
b) 1.5
c) 6
d) 10
37.Isolator is .......... device.
a) On Load
b) Off Load
c) Protective
d) All of the above
38.CT stands for .......... .
a) Current Transformer
b) Coil Transformer
c) Current Tap
d) Conversion Transformer
39.Current Transformer is used for .......... purpose.
a) Voltage Regulation
b) Power Factor Improvement
c) Current Measurement
d) Voltage Measurement
40.CVT is connected in .......... with the transmission line.
a) Series
b) Parallel
c) Star
d) Delta
41........... is used to measure the specific gravity of the Electrolyte of the DC
Battery.
a) Hygrometer
b) Tachometer
c) Hydrometer
d) Wattmeter
42.Phase-to-Phase voltages are always .......... than Phase-to-Ground voltage.
a) Greater
b) Less
c) Equal
d) Unrelated
(Not specify here, either it is for Delta connection or Star connection)
43.DC voltages will be increased when batteries are connected in .......... .
a) Series
b) Parallel
c) Star
d) Delta
44.C&DF stands for .......... .
a) Current & Distribution Factor
b) Capacitance & Dissipation Factor
c) Control & Data Flow
d) Conduction & Diffusion Factor
45.DGA stands for .......... .
a) Differential Gas Analyzer
b) Dissolved Gas Analysis
c) Distribution Grid Assessment
d) Dynamic Grid Algorithm
46.Megawatt is the unit of .......... .
a) Energy
b) Current
c) Voltage
d) Power
47.The unit of Frequency is .......... .
a) Ohm
b) Volt
c) Hz
d) Ampere
48.The input of the Frequency Meter is .......... .
a) P.T
b) C.T
c) Both a & b
d) None of the above
49.Accuracy Class of Energy Meter is specified as .......... .
a) CL 0.2
b) 5M
c) 50Z
d) All of the above
50.Heater is a constant .......... load.
a) Resistive
b) Inductive
c) Capacitive
d) Reactive
INTERNAL TEST OF GRID
NTDC was incorporated as Public Limited Company in November 06, 1998
(license allocated) but started its commercial operations from March 01,
1999.
In NTDC, there are 03 Deputy Managing Directors (D.M.Ds). These are
includes Asset Development & Management (AD&M), Planning &
Engineering (P&E), and System Operation (S.O).
NTDC have two Regional Control Centers (R.C.Cs), one is located in
Islamabad called as Regional Control Center North (R.C.C.N) & second is
located in Jamshoro called as Regional Control Center South (R.C.C.S).
NTDC have total 16 grids of 500kV (with 22,350MVA capacity & 5970km
length of transmission line) & 45 grids of 220kV (with 31,060MVA capacity
& 11,322km length of transmission line).
DRAKE & GREELEY types of conductor used in 500kV line, RAIL &
GREELEY types of conductor used in 220kV line, HAWTHORN type of
conductor used in 132kV line, and DOG type of conductor used in 33kV to
66kV lines.
HAWTHORN (900A capacity) & COREOPSIS types of conductor used in
Busbar.
PTW stands for Permit To Work.
SCADA stands for Supervisory Control And Data Acquisition.
Leakage Current Monitoring (L.C.M) Test used to check Leakage Current of
Lightning Arrester.
Transformer Turn Ratio (T.T.R) Test used to check Healthiness of Winding
& Tap-Changer.
Timing Test done for Circuit Breaker (C.B).
Wave Traps (W.T) are used to Capture Telecom Signals.
Circuit Breaker (C.B) gives protection against Switching Transient
(Switching Transient becomes due to Surge on Lightning Arrester (L.A)).
Gravels in yard are used to Reduce Step Potential & Provides Easy Path for
leakage current.
Grounding is done for Live Part of Equipment (like Neutral conductor of
Transformer) & also always having leakage current.
Earthing is done for Dead Part of Equipment (like Body of Transformer for
Human Protection) & it have leakage current only when any fault occurs.
The ratio of Maximum Demand to the Connected Load is called as Demand
Factor.
The total length of Insulator or Bushing is called as Creepage Distance/Path.
Capacity of battery shows in Ampere-hour (Ah).
The Tolerance of Frequency is ±1%.