Kerbs installation works -Checklist
Project: LOCATION: Ref. No.
Work zone: LP #: DATE:
SI NO. Items/Activity FINDINGS
1 Are Kerbs from an approved supplier?
2 Kerbs are stored properly at the site.
3 Alignment and top level of kerb had been marked/set-out.
4 PCC is casted and cured properly.
The bedding top received 2 cm thick sand cement mortar(wet)
5
and kerbs fixed, and set to the lines and grade shown on drawing.
6 Kerbstone is installed properly.
7 Backing/haunching of concrete is casted and cured properly.
The 10 mm thick expansion joints in between kerbs provided after
8
every 9 meters.
Joint & Gap filling; the kerbs fixed with a spacer joint by width of
9
5-10 mm where mortar filled in the joints.
Name:
Signature: