Prepared by, Approved by,
Mine Plan Project Manager
PT. PWP PT. PWP
Approved by,
PT. SINGLURUS PRATAMA
-Weekly Plan – 08
PLAN WEEKLY – 08
(Periode 22 - 28 Februari 2023)
Working Hours OB & Coal Week 08 PT. PWP
Working Hours (07.00 - 18.00)
TOTAL
2 SHIFT WORKING OB DATE 22 23 24 25 26 27 28
DAYS Wed Thu Fri Sat Sun Mon Tue 7
Schedule Hours (MOHH) 24.00 24.00 24.00 24.00 24.00 24.00 24.00 24.00 168.00
Available Hours 22.00 22.00 22.00 22.00 22.00 22.00 22.00 22.00 154.00
Rest & Meal 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 14.00
Safety Talk 0.50 - - - 0.50 - - - 0.50
P2H/Daily Check Unit 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 1.05
Rain 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 14.00
Idle Hours
Slippery 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 7.00
Friday Praying 1.00 - 1.00 - - - - - 1.00
Mobilization 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.35
Holiday 1.00 - - - - - - - 0.00
Total Delay Hours 5.20 6.20 5.20 5.70 5.20 5.20 5.20 37.90
Effective Working Hours / Day 16.80 15.80 16.80 16.30 16.80 16.80 16.80 16.59
Working Hours (07.00 - 17.00)
TOTAL
2 SHIFT WORKING COAL DATE 22 23 24 25 26 27 28
DAYS Wed Thu Fri Sat Sun Mon Tue 7
Schedule Hours (MOHH) 24.00 24.00 24.00 24.00 24.00 24.00 24.00 24.00 168.00
Available Hours 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 140.00
Rest & Meal 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 14.00
Safety Talk 0.50 0.50 - - - - - - 0.50
P2H/Daily Check Unit 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 1.05
Rain 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 7.00
Idle Hours
Slippery 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 5.25
Friday Praying 1.00 - 1.00 - - - - - 1.00
Mobilization 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.35
Holiday 1.00 - - - - - - - 0.00
Total Delay Hours 4.45 4.95 3.95 3.95 3.95 3.95 3.95 29.15
Effective Working Hours / Day 15.55 15.05 16.05 16.05 16.05 16.05 16.05 15.84
Plan Fleet OB & COAL Capacity Week 08 Coal PT. PWP
PLAN FLEET OB CAPACITY
FLEET CONFIGURATION DAYS
No. Prod'ty Distance Weekly
PIT Nomor Unit Type Unit ADT Wed Thu Fri Sat Sun Mon Tue
1 EX - 38 KOBELCO SK550 3 x ADT 205 330 3,444 3,239 3,444 3,342 3,444 3,444 3,444 23,801
2 EX - 40 VOLVO EC 480 DL 3 x ADT 200 330 3,360 3,160 3,360 3,260 3,360 3,360 3,360 23,220
3 EX - 43 KOBELCO SK330 3 x DT 170 330 2,856 2,686 2,856 2,771 2,856 2,856 2,856 19,737
4 Pit AG50_1 EX - 44 VOLVO EC 480 DL 3 x ADT 210 330 3,528 3,318 3,528 3,423 3,528 3,528 3,528 24,381
5 EX - 52 KOBELCO SK550 3 x ADT 210 330 3,528 3,318 3,528 3,423 3,528 3,528 3,528 24,381
6 EX - 39 VOLVO EC 480 DL 4 x DT 170 330 2,856 2,686 2,856 2,771 2,856 2,856 2,856 19,737
7 EX - 50 KOBELCO SK550 3 x ADT 200 330 3,360 3,160 3,360 3,260 3,360 3,360 3,360 23,220
TOTAL 7 Fleet 15 ADT 7 DT Average 330 22,932 21,567 22,932 22,250 22,932 22,932 22,932 158,477
FLEET COAL CAPACITY
FLEET CONFIGURATION DAYS
No. Jumlah (unit) Weekly REMARKS
Nomor Unit Type Unit DUMP TRUCK Wed Thu Fri Sat Sun Mon Tue
1 EX - 45 VOLVO EC 480 DL Nisssan CWA & Hino 16 5,225 5,057 5,393 5,393 5,393 5,393 5,393 37,246
2 EX - 46 VOLVO EC 480 DL Nisssan CWA & Hino 15 4,898 4,741 5,056 5,056 5,056 5,056 5,056 34,918
3 EX - 48 KOBELCO SK550 Nisssan CWA & Hino 14 4,572 4,425 4,719 4,719 4,719 4,719 4,719 32,590
4 Nisssan CWA & Hino 13 4,245 4,109 4,382 4,382 4,382 4,382 4,382 30,262
5 Nisssan CWA & Hino 12 3,919 3,793 4,045 4,045 4,045 4,045 4,045 27,934
6 Nisssan CWA & Hino 11 3,592 3,477 3,708 3,708 3,708 3,708 3,708 25,606
7 Nisssan CWA & Hino 10 3,266 3,161 3,371 3,371 3,371 3,371 3,371 23,279
8 Nisssan CWA & Hino 9 2,939 2,844 3,033 3,033 3,033 3,033 3,033 20,951 Pit AG44_1, Pit
AG44_2W & Pit
9 Nisssan CWA & Hino 8 2,612 2,528 2,696 2,696 2,696 2,696 2,696 18,623 AG50_1
10 Nisssan CWA & Hino 7 2,286 2,212 2,359 2,359 2,359 2,359 2,359 16,295
11 Nisssan CWA & Hino 6 1,959 1,896 2,022 2,022 2,022 2,022 2,022 13,967
12 Nisssan CWA & Hino 5 1,633 1,580 1,685 1,685 1,685 1,685 1,685 11,639
13 Nisssan CWA & Hino 4 1,306 1,264 1,348 1,348 1,348 1,348 1,348 9,311
14 Nisssan CWA & Hino 3 980 948 1,011 1,011 1,011 1,011 1,011 6,984
15 Nisssan CWA & Hino 2 653 632 674 674 674 674 674 4,656
16 Nisssan CWA & Hino 1 327 316 337 337 337 337 337 2,328
PLANNING SUMMARY
No. PLANNING SUMMARY UNIT Wed Thu Fri Sat Sun Mon Tue TOTAL REMARKS
1 TOTAL WASTE STRIPPING BCM 22,932 21,567 22,932 22,250 22,932 22,932 22,932 158,476.50
MAX COAL HAUL CAPACITY Ton 5,225 5,057 5,393 5,393 5,393 5,393 5,393 37,245.60
2 TOTAL COAL EXP COAL EXPOSED Ton 27,388.98 Pit AG44_1, Pit
27,388.98
AG44_2W & Pit
COAL HAULED Ton 4,898 4,741 5,056 5,056 5,056 5,056 5,056 34,917.75 AG50_1
3 COAL INVENTORY 398,753.91 Ton 398,754 421,245 416,504 411,448 406,392 401,337 396,281 391,225.14
4 STRIPPING RATIO 5.79
Plan Area Kerja PT. PWP
PIT SEAM INVENTORY Plan OB W08 Plan Expose W08 Hauling W08 Remain Inventory SR (OB/ Coal Haul) SR (OB/CO Expose)
PIT AG44_2W 44 329,491.18
PIT AG44_1 44 18,056.73
PIT AG76_S76 76 33,374.00
78 1,166.83
PIT AG76_S78
79 0.00
158,476.50 27,388.98 34,917.75 391,225.14 4.54 5.79
PIT_AG50 50 0.00
50 904.80
PIT AG50_1 51 15,760.37
52 0.00
TOTAL 398,753.91
Remain PIT AG44_2W
PIT SEAM CO (Mt) OB (Bcm) INVENTORY TS (%) GAR SR
PIT AG44_2W 44 34,333.89 42,484.79 329,491.18 0.00 0.00 0.12
Remain PIT AG44_1
PIT SEAM CO (Mt) OB (Bcm) INVENTORY TS (%) GAR SR
PIT AG44_1 44 0.00 0.00 18,056.73 0.00 0.00 0.00
Remain PIT AG50_1
PIT SEAM CO (Mt) OB (Bcm) INVENTORY TS (%) GAR SR
50 61,872.23 904.80 0.00 0.00
51 64,058.10 563,749.00 15,760.37 0.00 0.00
PIT AG50_1 Batas Lahan 3.74
52 8,335.98 0.00 0.00 0.00
Total 134,266.31 16,665.17
Remain PIT AG76_2
PIT SEAM CO (Mt) OB (Bcm) INVENTORY TS (%) GAR SR
PIT AG76_S76 76 0.00 0.00 33,374.00 0.35 4,331 0.00
78 25,169.54 1,166.83 1.78 4,059
Dalam Lahan Bebas 82,842.00 3.15
79 0.00 0.00 1.99 4,459
PIT AG76_S78
78 258,117.67 0.00 1.78 4,059
Di Luar Lahan Bebas 1,503,980.00 5.76
79 3,036.35 0.00 1.99 4,459
78 283,287.21 0.00 1.78 4,059
Sub Total Pit Ag76_2 S78 1,586,822.00 5.54
79 3,036.35 0.00 1.99 4,459
TOTAL 286,323.56 1,586,822.00 34,540.83 4.95
CO OB INVENTORY SR
TOTAL REMAIN PIT
454,923.77 2,193,055.79 398,753.91 2.57
Remain PIT Update 21 Februari 2023
Weekly Plan 08 PT. PWP
PIT OB (Bcm) COAL (Mt) SR
AG50_1 158,293.62 27,388.98 5.78
TOTAL 158,293.62 27,388.98 5.78
Update 21-02-2023