Generator CB Interruption of Current With Non-Zero Passage
Generator CB Interruption of Current With Non-Zero Passage
by
Alstom T&D
(France)
Summary Keywords
The last ten years have seen the development of Generator circuit breaker – Self blast – TRV –
the self-blast technique of interruption for SF6 HV Delayed current zero – Cable connection
circuit breakers. This technique has proved to be
very efficient and has been widely applied for high
voltage circuit breakers up to 800 kV. The paper 1 Introduction
shows the application of the same technique to
the development of SF6 generator circuit breakers Generator circuit breakers, located between the
with spring-operated mechanisms. generator and the step-up transformer, have
proved to be an economical and efficient solution
A particular characteristic of generator circuit
for the protection of generators and transformers.
breakers is their mandatory capability to interrupt
They are widely used nowadays for generator
short-circuit currents with delayed current zeros.
ratings ranging from 100 MVA to 1300 MVA.
This requirement of ANSI/IEEE Standard C37-013
is explained in section 3 of this paper with SF6 circuit breakers are generally applied when
examples of breaking tests and simulations of interrupting capabilities of 63 kA to 120 kA are
current interruption. specified, while air-blast generator circuit breakers
are dominant when a higher interrupting capability
In 1997 the IEEE Switchgear Committee has
is required.
issued a new edition of its standard C37-013 for
generator circuit breakers, which covers mainly the The last ten years have seen the development of
applications with power transformers rated the self-blast technique of interruption for SF6
100MVA and above [1]. A revision of this standard breaking chambers. It has allowed the
is done by the IEEE Switchgear Committee in development of new ranges of circuit breakers
order to extend its scope to applications of less operated by low energy spring-operated
than 100MVA rated power. This paper presents mechanisms [1] [2].
calculations that have been made to calculate
The same technique has led to the development of
TRVs for system fed faults in the case of small
generator circuit breakers connected to the step-up SF6 generator circuit breakers with spring-operated
mechanisms (Figure 1)
transformer by cables.
- Test n°10.
Fig. 4 Inherent short-circuit current of test n°9 If the setting of contacts separation is delayed, arc
has less influence on current evolution, as arc
The percentage dc component is equal to 150%, voltage is smaller when current reaches its
the first current zero occurs 40 ms after initiation of minimum value. It follows that arc voltage could be
short circuit. insufficient to force current through zero. Figure 7
The oscillogram of fig. 5 shows that the Generator shows that in this case interruption is obtained
circuit breaker is able to force the current through after the second loop of current. This test shows
zero and to interrupt with an arcing time of 18 ms. that this Generator circuit breaker can interrupt
with long arcing times, thanks to the prolonged
blast produced by thermal blast.
Uarc
0 10 20 30 40 50 60 [ms] 70
(file 8013B.pl4; x-var t) v:SIMARC-OUTARC c:SIMARC-OUTARC
3,2 1,25
Issf=10kA
3 1,2
Issf=20kA Issf=15kA
2,8 1,15
1,1
2,6
1,05 Issf=20kA
Issf=10kA Issf=15kA
2,4
1
2,2
0,95
2 0,9
0 1000 2000 3000 4000 5000 6000 7000 0 1000 2000 3000 4000 5000 6000 7000
Fig. 11. TRV rate : Case V = 13.8 kV I = 10-15- Fig. 12. E2 Multiplier : Case V = 13.8 kV I = 10-
20kA P≤ 50MVA 15-20 kA P≤ 50 MVA
The cable introduces a capacitance between the 4.2.2 Rated maximum voltage V = 25.7 kV
system and the circuit breaker, which lowers the
frequency of the TRV. - TRV rate of rise
With decreasing short-circuit currents, and as the Figure 13 gives the rate of rise of TRV as a
system frequency is assumed to be constant, the function of the short-circuit current and the cable
supply capacitance Cs is decreasing. For a given capacitance.
cable, the ratio of cable capacitance/source
TRV rate TRV rate for system-source faults : Case Ur= 25,7kV
kV/µs Issf = 7-10-13kA Transformer <= 50MVA
3,4
3,2
3
Issf=13kA
2,8
2,6 Issf=10kA
Issf=7kA
2,4
2,2
2
0 1000 2000 3000 4000 5000 6000 7000
Fig. 13 TRV rate: Case V = 25.7 kV I = 7 – 10 – TRV RATE FOR SYSTEM FED FAULTS TRANSFORMER <=50MVA
13kA P≤ 50MVA
3,4
3,2
- Peak value E2
3
33,4MV
2,2
E2 Multiplier E2 Multiplier for system-source faults : Case Ur= 25,7kV
p.u. Issf = 7kA-10kA-13kA Transformer <= 50MVA 2
1,3
26,6MVA
1,8
1,25
1,6
Issf=7kA
1,2
1,4
Issf=10kA
1,15
0 2000 4000 6000 8000 10000 12000
1,1 CABLE CAPACITANCE (pF)
1,05
1
Issf=13kA Fig15. TRV rate as function of transformer power
0,95
and cable capacitance, P ≤ 50MVA.
0,9
0 1000 2000 3000 4000 5000 6000 7000 Figure 16 gives the corresponding values of the
Cable capacitance (pF) peak voltage multiplier.
26,5MVA
If a short-circuit p.u. reactance of 14% is assumed, 1,25
1,1
1,05
as follows : 3,2
81MVA
100MVA
2,8
with V = rated maximum voltage
2,6
3
1,25
- Peak value E2
Figure 18 gives the multiplying factor of E2 as a
function of the cable capacitance and for three Fig 20 E2 Multiplier as function of transformer
values of the short circuit current. power and cable capacitance, 50MVA< P ≤
100MVA
E2 Multiplier E2 Multiplier for sys tem-source faults : Case Ur= 13.8kV
p.u. Issf = 25 -31.5-45kA Transformer 50<<= 100MVA 4.4 Analysis of calculation results
1,3
0,9
This means that a higher performance is required
0 1000 2000 3000 4000 5000 6000 7000 for generator circuit-breakers, and that circuit-
Cable capacitance (pF)
breakers rated according to ANSI C37.04 and
C37.06 (or IEC 62271-100) can only be applied as
generator circuit-breakers if they are used at a
Fig. 18. E2 Multiplier: Case V = 13.8 kV I = 25- reduced percentage of their rated short-circuit
31.5-45 kA , 50MVA< P ≤ 100MVA current (60% or less) or fitted with additional
4.3.2 TRV parameters as function of transformer capacitors. In addition such circuit breakers must
rated power be capable of interrupting short-circuit current with
delayed current zeros as required in the present
Figure 19 gives the TRV rate as function of the edition of Standard C37.013.
transformer rated power and cable capacitance
5 Conclusion [2] D.Dufournet, J.Ozil, F.Sciullo, A.Ludwig. New
interrupting and drive techniques to increase high
The last decade has seen great progress in
voltage circuit-breaker performance and reliability.
interrupting techniques and computation of many
(CIGRE Session 1998, Report 13-104) .
aspects of circuit breaker behaviour (dynamic
operation, gas flow in the interrupting chamber, [3] IEEE Std C37-013-1997. IEEE Standard for
interruption at current zero, arc voltage). It has lead AC High-Voltage Generator Circuit Breakers Rated
to the development of new SF6 Generator circuit on a Symmetrical Current Basis.
breakers characterised by a high interrupting
[4] G.Seyrling, E.Thuries. Development of a
capability and a low operating energy.
generator circuit breaker using the SF6 interrupting
Generator circuit breakers have some features that technique. (GEC ALSTHOM T&D Technical review
distinguish them from other types of circuit N°11-1993) .
breakers. In particular, they must be able to
[5] D.Dufournet. Short-line-fault Interruption in
interrupt, in a relatively short time, short-circuit
Medium Voltage Networks. (Report 1.5 presented
currents with delayed current zeros. This
at CIGRE SC13 Colloquium in Florianopolis
performance must be demonstrated by tests and/or
(Brazil), September 1995) .
calculations supported by test evidence as
specified in ANSI/IEEE standard C37-013.
This paper has shown the tests performed to
demonstrate the capability of a Generator circuit-
breaker to interrupt short-circuit currents with
delayed current zeros, and calculations which
reproduced the arc voltage and current waveforms
due to arc-circuit interaction.
A study of TRV parameters has been done in the
case of system-source fault interruption by
generator circuit breakers connected by cable(s) to
the step-up transformer.
More than 70 simulations have been done to cover
many cases of applications for different rated
maximum voltages, short-circuit current ranging
from 7kA to 45kA and cable capacitances up to
12000 pF.
TRV parameters for cases not covered in this
document can be obtained easily by interpolation
or extrapolation.
Even in cases with long cable lengths, the rate of
rise of TRV is much higher than the value required
for standard circuit breakers rated and tested
according to IEC 62271-100 or ANSI-IEEE C37.04
and C07.06. Derating of such circuit breakers is
necessary if they are intended to be used as
generator circuit breakers.
Generator circuit breakers must also be able to
make and break in out-of phase conditions with a
TRV rate of rise higher than the value given in
ANSI C37.04/06 and IEC 62271-100 for other
types of circuit breakers.
6 References