Professional Documents
Culture Documents
The single phase to ground faults followed by a single phase tripping and System Parameters
high speed retlosing were the first full scale staged fault tests of this type on A simplified one linre diagram of the 243 km Kammer-Marysville 765 kV
the AEP 765 kV network. The tests represented the first trial for the switched,
or modified, reactor compensation scheme which minimizes the secondbry arc untransposed transmission line used for the tests is shown in Figure 2. The
currentand recovery voltage on untransposed EHV lines5,6. line, with 300 MVAr shunt reactor banks at, each end, had a compensation factor
of 0.86. The source strength behind the Kammer 765 kV bus was 20,000 MVA
Compensatibn Schemes and behind the Marysville 765 kV bus was 16,000 MVA. Two cycle air blast
circuit breakers were used for single phase switching operations. The positions
Two switched four legged reactor compensation schemes presented in of all circuit breakers at both stations during the tests are shown in Figure 2.
Figure 1 were tested: one with neutral or low side switches (NS) and the other
using high side reactor switches (RS). By inspection, one can see that both
schemes result in the same interphase as well as faulted phase to ground FORT MARTIN
equivalent impedances and, therefore, correspond to identical single phase MARYSVILLE
switching compensation parameters for a given line.
300VA
A A
and 60 degrees (B). Faults on an outer phase. 195A
Neutral reactors of 400 Ohms at
Kammer and 300 Ohms at Marysville.
to - breaker opening
A0 0-
.z v- __j %- __j %.- --.O
te - arc extinction
arc current reached 720 A and 840 A in tests A and B respectively (Fig. 5) while
the 60 Hz calculated current value is 35 A as mentioned above.
170A
The secondary arc current decreases rapidly during the first part of the
transient process. The second part of the secondary arc current is determined Al A
v
A A A AI
by the compensation scheme parameters but still contains the initial dc offset of
the fault current whose magnitude depends on the fault initiation angle. The dc
offset diminishes with a 20-30 msec time constant. This means that even at the
end of the first part of the transient process, about 5060 msec after fault
initiation, the dc offset component may still be comparable with the 60 Hz value
of the secondary arc current. This affects, in turn, the moment of the first zero
crossing of the secondary arc current during the second part of the transient
process. For example, in test B the initial dc offset was greater than in test A A2 130A 0../ 'O.,
(Fig. 5) and led to a slightly longer (about 1.5 cycles), arc burning time before %0"" "10-
the arc first attempted to extinguish. In both tests the arc extinguished in about
40 msec after breaker opening. At the same time it is interesting to notice that
in test A the first arc interruption attempt took place practically immediately
after the end of the first part of the transient process. This attempt was un-
successful and led to a single arc restrike after which the arc existed for about
10 msec. In test B the first current zero crossing resulted in the final arc IIOA
interruption. Summing up the description of the tests given in Fig. 5, it is im- A3 .ff W-
c2S24
portant to underline that despite the fact that the 60 Hz component of the sec-
m
ondary arc current affects implicitly the actual secondary arc current wave shape,
the latter is also dependent on theinitial conditions as wellas the arc parameters.
Fig. 6 Secondary arc current in compensation scheme corresponding to
a
Four unsuccessful single phase switching tests with reclosing times of the 60 Hz component equal to 113 A. Fault on the middle phase.
30 cycles were utilized to analyze the quasi steady state wave shapes of the AO intermittent arc, line energized from Kammer
-
secondary arc current. Calculated 60 Hz secondary arc current values (11) in Al faulted phase solidly grounded, line energized from Kammer.
-
these tests were 45 A rms, 50 A rms (two tests) and 80 A rms. A typical sec- A2 - faulted phase solidly grounded, line energized from both stations
ondary arc current wave shape for these tests is presented by oscillogram AO A3 - faulted phase solidly grounded, line energized from Marysville
in Fig. 6. In all of the unsuccessful single phase switching tests the arc had an
intermittent character, resulting in futile attempts to extinguish at each zero
crossing of the current. Currents 11, 13 and 15 in Table 2 are as before, the fundamental or 60 Hz,
third and fifth harmonic components. Magnitudes of other harmonics in the sec-
Sharp nonlinearity of the equivalent arc resistance facilitated the presence ondary arc current in this series of tests were insignificant and did not exceed
of the third harmonic (13) in the secondary arc current. Harmonic content of the 5 percent of 11. The third and fifth harmonics of the secondary arc current, in
quasi steady state current wave shapes is given in Table 1. This Table shows contrast to the 60 Hz component,were very much dependent on the test conditions.
that the magnitude of 13 is equal to about 40 percent of 11, at least in a limited Thus, tests AO and A 1 which differ one from another only by arc parameters,
current range. The results presented in the Table also indicate that the measured show that the arc resistance suppresses the fifth harmonic (15) to 17 A from 67 A.
60 Hz component of the secondary arc current in the four tests under discussion At the same time, the intermittent character of the secondary arc with a change of
agrees closely with the corresponding calculated values. In addition, the 300 Hz arc resistance from tens of ohms to practical infinity during each half-cycle
component (15) was also found present in the secondary arc current wave shape results in a wave shape with a strongly pronounced third harmonic. In the tests
and was approximately equal to 15 percent of 11. Higher order harmonics were A1, A2 and A3 (Fig. 6) with zero arc resistance, the third harmonic does not
practically absent in the secondary arc current wave shape. exceed 10 percent of 11.
1732
Table 2 Harmonics content of the secondary arc current
Test Line Calcu- Measurements
According Type of Arc Energized IA 1s/1 |
13l | 151
lations 131
to Fig.6 at I,A 1'
Ao intermittent Kammer 108 .43 .16
A1 solidly Kammer 108 .10 .62 ENS
grounded
113
A2 solidly Kammer and 108 .05 .27
grounded Marysvi lle
A3 solidly Marysville 108 .07 .16
grounded 15 A
The magnitude of the fifth harmonic (15) in the tests with zero arc resistance
is mainly a function of the nonlinear characteristics of reactors and transformers,
the line parameters and bus voltages. Thus, the magnitude of the secondary arc
current 15 was only 17 A in test A3 when the line was energized from Marysville,
29 A in test A2 with the line energized from both ends, and 67 A in test A1
when the line was energized from Kammer.
ERS _
Unlike the quasi steady state secondary arc current, the harmonic content 155A
of the secondary current with a solidly grounded phase varies with a change of
single phase switching compensation parameters. This can be illustrated by a
comparison of the secondary arc currents presented in Figs. 6 and 7. The cal-
culated 60 Hz component of the secondary arc current in the tests shown in Fig. 7
is equal to 53 A. The harmonic analysis of the tests E1-E3 with a solidly
grounded phase is presented in Table 3. It is interesting to note that in the test
E1 when the line was energized from Kammer, the second and fourth harmonics
reach noticeable magnitudes in addition to greater relative values of the third IOA
and fifth harmonics in comparison to the tests analyzed in Table 2. Also, as E I / - A A AA AA
before, all of the harmonics diminished significantly when.the line was energized ?OvA
VAv A
from Marysville station. At the same time, the absolute values of the secondary
arc current harmonics may be quite different for different 60 Hz components.
For example, the currents 13 and 15 were equal to 11 A and 67 A, respectively, 70A { s / { '
in test A1 compared to 13 of 25 A and 15 of 44 A in test El.
A-720A
1/
0
I
10
I
20
I
30
I
40
t_msecI
30.5 msec
Fig. 9 Rate of rise of the recovery voltage. Fault on the middle phase.
Neutral reactors of 400 Ohms at Kammer and 150 Ohms at Marysville.
60 Hz component of the secondary arc current equals 53 A.
Arc extinction time
*- 60 msec
o - 160 msec
tests (24 out of 27) and 20 percent in the rest of the tests. It is clear that this
voltage-current dependency is valid only for the initial part of the recovery
G voltage which in the discussed case does not exceed 50 msec.At the same time,
the presence of strong correlation between the rate of rise of recovery voltage
and the secondary arc current magnitude represents a quantitative characteristic
of the compensation scheme.
Secondary arc interruptions and restrikes which took place in about a third
of the tests represent a unique opportunity to analyze and determine the rate of
rise of the withstand voltage (V ) of the air gap which was ionized by the fault
and secondary arcs. One such rest is shown in Fig. 10 where the 60 Hz sec-
ondary arc current was 70 A and single phase reclosing was unsuccessful. The
V. v_ 830 s arc restrikes which occurred during the tests are summarized in Fig. 11. In this
figure, the restrike voltages are presented as a function of the time from a sec-
Fig. 8 Secondary arc currents for outer (F) and middle (G) phase faults ondary arc current interruption to the following arc restrike. Figure 11 also
with 950 MW pre-test power flow along the line. includes peak values of the recovery voltages which approached but did not
to - breaker opening reach corresponding flashover levels of the test air gap.
te - arc extinction
voltage depend mainly on line and reactor parameters and, therefore, on the
transmission line compensation factor. Parameters such as fault initiation angle
and primary fault and secondary arc burning times do not affect the recovery
voltage to a significant extent.Thus, for example, Fig. 9 shows the peak voltages
in each half cycle versus time from the moment of arc extinction in two similar
tests with neutral reactors of 400 Ohms at Kammer and 150 Ohms at Marysville
ItI
and corresponding to the same 60 Hz secondary arc current of 53 A. Despite the
fact that the arc extinction time in these two tests was quite different (60 msec
and 160 msec) the rate of rise of recovery voltage, as it can be seen in Fig. 9,
was practically the same. The independence of the rate of rise of recovery
voltage from the secondary arc burning time, and its explicit dependence on
transmission line and reactor parameters, makes the rate of rise of this voltage
a very important and practical parameter in predicting the success of single
phase switching operations.
REFERENCES
1. Knudsen, N. - "Single Phase Switching on Transmission Lines Using Re-
actors for Extinction of the Secondary Arc", CIGRE, Report 310, 1962.
2. Kimbark, E. W. - "Suppression of Ground-Fault Arcs on Single Pole-Switched
EHV Lines by Shunt Reactors", IEEE Transactions, Vol. PAS-83, March
1964, pp. 285-290.
3. Kimbark, E. W. - "Charts of Three Quantities Associated with Single-Pole
0 10 20 30 40 msec Switching", IEEE Transactions, Vol. PAS-94, March/April 1975, pp. 388-394.
Fig. 11 Rate of rise of the withstand voltage for an air gap with 4.2m 4. Edwards, L., Chadwick, Jr., J. W., Reich, H. A., and Smith, L. E. - "Single-
clearance after secondary arc interruptions. Pole Switching on TVA's Paradise-Davidson 500 kV Line. Design Concepts
e - flashover voltage and Staged Fault Test Results", IEEE Transactions, PAS-90, November/
o - withstand voltage December 1971, pp. 2436-2450.
5. Shperling, B. R., Fakheri, A., and Ware, B. J. - "Compensation Scheme for
dependency on time can be used to predict the success of single phase switching Single-Pole Switching on Untransposed Transmission Lines", IEEE Trans-
operations.lt should be notedthatthe dependency discussed above wasdetermined actions, Vol. PAS-97, July/August 1978, pp. 1421-1429.
for compensated lines where the voltage buildup after arc extinction is relatively
slow. For lines without shunt reactors and, therefore, with fast rates of rise of 6. Shperling, B. R., and Fakheri, A. - "Single Phase Switching Parameters for
recovery voltage, more information is needed to determine the withstand strength Untransposed EHV Transmission Lines", IEEE Transactions, Vol. PAS-98,
during the first few milliseconds after arc interruption. March/April 1979, pp. 643-654.
CONCLUSIONS 7. Sakshaug, E. C., Kresge, J. C., and Miske Jr., S. A. - "A New Concept in
Station Arrester Design", IEEE Transactions, Vol. PAS-96, March/April
1. Staged fault tests demonstrated the applicability of high speed single 1977, pp. 647-656.
phase reclosing on EHV transmission lines. Both reactor switching schemes,
with neutral switches and high side reactor switches, were effective in reducing 8. Malewski, R., and Nourse, G. R. - "Transient Measurement Techniques in
secondary arc current and recovery voltage. EHV Systems", IEEE Transactions, Vol. PAS-97, May/June 1978, pp. 893-902.
2. The rate of rise of the withstand voltage across the arc path after 9. Nourse, G. R., Thomas, D. G., and Marshall, N. A. - "An Automatic Transient
secondary arc interruption was determined for a simulated 765 kV air gap with Recording System - The CLD Monitor Station", IEEE PES Summer Meeting,
4.2 m clearance. The withstand voltage reached 425 kV in 45 msec and its Los Angeles, July 16-21, 1978, Paper A78 577-9.
dependency on time can be used in conjunction with the rate of rise of recovery
voltage for analyzing the application of various single phase switching com- 10. Haubrich, H. J., Hoseman, G., and Thomas, R. - "Single Phase Auto-Re-
pensation schemes. closing in EHV System", CIGRE, Report 31-09, 1974.
1735
T. H. Lee (The New Brunswick Electric Power Commission, B. R. Shperling, A. J. Fakheri, C. H. Shih, and B. J. Ware: We would
Fredericton, N.B., Canada): The authors have demonstrated the effec- like to thank Mr. Lee for his interesting addition to the paper.
tiveness of the four-leg switched reactor scheme to control the secon- Regarding Mr. Lee's first question, it is important to underline that
dary arc current due to single-pole switching in a series of field tests. all 230kV and 345kV transmission lines in his -company (including the
Even though the secondary arc current and the recovery voltage are not 317 km line he referred to in the discussion) do not require and
the only problem one faces for using SPS, the authors' results confirm therefore do not have shunt reactor compensation. At the same time in
our operating experience. NBEPC'currently has 510 km of 230 kV and' single phase switching the rate of rise of the recovery voltage on the
837 km of 345 kV (including neighbouring interties) transmission. All open phase after arc interruption depends significantly on line compen-
are equipped with SPS without compensation. The longest is a'317 km, sation. Thus, the rate of rise of the recovery voltage is much faster on
345 kV line with four in-span transpositions (using polymer insulators) uncompensated lines in comparison with the lines equipped with shunt
at the guyed portal suspension tower (see Fig. 2). The two end terminals reactors. This in its turn, results in longer arc extinction time on un-
are equipped with SPS and the middle of this line is tapped with a compensated lines if, of course, other single phase switching parameters
345/138 kV transformer through only one breaker on the transformer are kept similar.
side. This breaker is currently operated three pole (see Fig.' 1).' TNA Accordingly to numerous laboratory and field test results the upper
studies show that' the above line has secondary arc current in the range boundary for arc extinction time dependency on secondary arc current
of 21.7 to 40A rms and recovery voltage of 52 kV to 94 kV peak. We set for'uncompensated lines can be estimated as t(msec) = .0251 (A rms),
dead-time'at 41.5 cycles instead of approximately-27 cycles used by the where I is calculated value of the secondary arc current.1O01 Using this
authors and have experienced three SPS operations in the last 16 mon- approximation for the secondary arc current varying from 21.7 A rms
ths without having any unsuccessful reclosings. to 40 A rms, the corresponding upper limit of the arc extinction time
The transposition is not only for reducing the secondary arc current, changes from 32 to 60 cycles. The lower limit of arc extinction time does
but also to avoid system steady state unbalance under some system not depend appreciably on the secondary arc current and equals ap-
operation conditions. We do understand that the authors' compensa- proximately 0.1 sec (6 cycles) for the current range mentioned above.
tion scheme is not' conceived as an alternative to line transposition for Therefore, the dead time of 41.5 cycles chosen by NBEPC for their
SPS (discussion of authors' reference 5). We, however, have some con- 345kV 317 km line looks reasonable since it practically insures arc ex-
cern about steady state motor operation with possible unbalance caused tinction for the secondary arc currents less than 30 A rms but for greater
by un-transposed EHV long transmission,'especially in the long term currents may lead to some probability of unsuccessful single phase
system expansion aspect. The incremental cost of our transposition at reclosings due to long arc burning time.
the guyed portal suspension tower scheme is almrost negligible (approx- With regard to Mr. Lee's second question, we would like to point out
imately $15,000 material per transposition). that line transposition requirements in a EHV system depend on a varie-
The authors' comments on the preceding two subjects will be sincere- ty of factors and may vary from one system to another. We agree that if
ly appreciated. transmission line asymmetry causes significant current imbalance
resulting, for example, in over heating of motor or generator windings,
line transposition is one of possible'measures to reduce the imbalance.
AEP has approximately 1400 miles of 765kV and 3600 miles of 345
kV untransposed transmission lines. The negative sequence current dur-
4SO MVA (0,V4F) ing steady state motor operations is about 3 percent in AEP system.
345//3S/34.s rV Io op.
/4 op. Thus, the effects of the untransposed transmission lines on the motor
Eli 3 op.
3
TO operations are not significant. It should be pointed out, however, that
the transmission line imbalance is mitigated at 765kV by connection of
CX~~~~ S
X7 fG, --- -
/ 60 -
-11 the spare reactors to proper phases'and at other voltage levels by con-
ColtESoA' S'4L/SfBUA'Y OASLOw ventional transformer connections.
COM) (A)
()
(a) ~~~~~A)(B) (c) Manuscript received September 23, 1980.
,LQ (4) CC) (a) (A) CC) (a)
.1sAosE Rq w%E REULDSE
I4
OfAI 3#
IIr T
OPEpG
f t
FAULT tO/
1/VSuj1AT0
HIql It
..
",. ,-/
2'~~~oJ
-soI I