The document is a Material Inspection Request (MIR) for the Rock Anchor Work project at MLCP Sec 11 Palava 2, submitted by Devansh Enterprises. It details the approval status, material description, quantity, supplier information, and inspection results for 60 bags of Ultra tech Power Grout Ns2. The engineer's decision indicates that the materials were inspected and found satisfactory for use on site.

Uploaded by

hyatn8500
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
186 views2 pages

MIR1

The document is a Material Inspection Request (MIR) for the Rock Anchor Work project at MLCP Sec 11 Palava 2, submitted by Devansh Enterprises. It details the approval status, material description, quantity, supplier information, and inspection results for 60 bags of Ultra tech Power Grout Ns2. The engineer's decision indicates that the materials were inspected and found satisfactory for use on site.

Uploaded by

hyatn8500
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

MATERIAL INSPECTION REQUEST - (MIR)

Project Name Rock Anchor Work at, [Link] 11 Palava 2 MIR [Link] MIR-MLCP-DE-STR-PK

Project Code Material Code


Request submission
Client/Employer 25/04/2025
(Date & Time)
Inspection
PMC/Engineer
(Date & Time) 24/04/2025

Contractor Devansh Enterprises MIR Submitted To Lodha

Vendor Code 30014613 Material code

Civil Arch / Finishing Landscape Mechanical Electrical Plumbing ID Facade Others

Part A: By the Contractor

Material Submittal approved (Yes/NO). if Yes,Approval Reference No: Yes

Description of Supplied Materials: Ultra tech Power Grout Ns2


Quantity: Current : 60 Bag
BOQ Reference :
Manufacturer - Country of Origin: Ultra tech Cement Ltd

Supplier : Ultra tech Cement Ltd

Supplied Quantity and Delivery Note Number: 60 Bags

Date of Receipt of Material On Site: 23/04/2025

Storage Location: MLCP Area

Any material which requires test certificate shall be delivered along with the MTC:
Any material which requires field test is conducted and test results are complying with the
acceptance criteria/values:
Any material which requires third party test, is it under contractor scope? (Yes/No) if
Yes, attach the certiifcate and confirm it is complying with the acceptance criteria/values) :
Any material which requires third party test, is it under Lodha's scope? (Yes/No) if
Yes, attach the certiifcate and confirm it is complying with the acceptance criteria/values) :

Contractor:
Name: Signature: Date:
Part B: By the Engineer (Lodha/PMC)
Inspection Reports:
Physical Damage? Yes No
Details Given in Delivery Note Correct? (Type, Size, Wt., Qty. etc.) Yes No
Conform with Approved Material Submittal Yes No
Any material which requires test certificate shall be delivered along with the MTC: Yes No
Any material which requires field test is conducted and test results are complying with Yes No
the acceptance criteria/values
Any material which requires third party test, is it under contractor scope? (Yes/No) Yes No
if Yes, verify the attached certiifcate and confirm it is complying with the acceptance
criteria/values) :
Any material which requires third party test, is it under Lodha's scope? (Yes/No) if Yes, Yes No
verify the attached certiifcate and confirm it is complying with the acceptance
criteria/values) :

Template Ref: CCO-LOD-GENE-QU-CN-TMT-008, Rev- R1, Date: 09-09-2023


MATERIAL INSPECTION REQUEST - (MIR)
Project Name MIR [Link]
Project Code Material Code

Civil & Finishing Materials - Project Quality Manager Landscape Materials - Landscape Architect
Façade Materials - Façade Manager MEP Materials (MEP Manager)
Comments:

Engineer's Decision (Lodha/PMC)


The above materials have been inspected on site and found, at time of inspection, to be:
A - Approved - Fully satisfactory and can be used for permanent works at site.
B - Approved with Comments - Partially satisfactory and can be used for permanent works after taking into
consideration our comments mentioned in remarks

C - Revise and Resubmit - Correct documents / provide additional information requested


D - Rejected - Can not be used for permanent works at site
Name: Signature: Date:

Distribution: Lodha Contractor Others …………………………

Template Ref: CCO-LOD-GENE-QU-CN-TMT-008, Rev- R1, Date: 09-09-2023