Bar Chart

Uploaded by

Attyub
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
14 views1 page

Bar Chart

Uploaded by

Attyub
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Reverse Osmosis Unit - Bar Chart

ID Major Milestone After Receipt of Order Early Finish Late Finish Sep '13 Oct '13 Nov '13 Dec '13 Jan '14 Feb '1 Mar '14 Apr '14 May '14 Jun '14 Jul '14 Aug '14 Sep '14 Oct '14 Nov '14
1 BOD Aapproval

2 Formal RFQ - RO Unit

3 Placement of Order - RO Unit - 12/1/2013 12/1/2013

4 Preparation and submission of 4-12 Weeks 12/27/2013 2/20/2014


approval documents
5 Formal RFQ for Pre fab shed 3 week

6 Placement of Order - Pre Fab 1 week


Shed
7 Shipment of Materilas for Pre-Fab 4 weeks
shed
8 Erection of Pre-Fab shed 6 weeks

9 Fabrication at Vendor Site 14-28 Weeks 3/7/2014 6/12/2014

10 Testing and Inspection 24-34 Weeks 5/16/2014 7/10/2014

11 Packing/crating, premitting and 30-34 Weeks 6/27/2014 7/24/2014


routing for shipment
12 Complete delivery FOB 34-34Weeks 7/24/2014 7/24/2014
destination
13 Submission of Complete 30-34 Weeks 6/27/2014 7/24/2014
Certified/ Record Drawings
14 Shipment and clearance 34-42 Weeks 7/24/2014 9/18/14

15 Construction 8 weeks

16 Hook ups 1 week

Task Summary Rolled Up Progress Project Summary


Project: RO bar chart
Progress Rolled Up Task Split Group By Summary
Date: Tue 9/17/13
Milestone Rolled Up Milestone External Tasks Deadline

Page 1