BILL OF MATERIALS
Item No. Item Description Quantity Unit Unit Price, Php Amount, Php
I. GENERAL REQUIREMENTS
• Design (1 set tracing & 7 complete sets blue print) (all signed and sealed) lot 200,000.00 -
• Building Permit lot 30,000.00 -
• Provision of temporary board up, covers, safety signages lot 20,000.00 -
• Temfacil lot 25,000.00 -
• Mobilization/Demobilization/Site Clearing lot 45,000.00 -
• Excavation m³ 350.00 -
• Backfill Works m³ 250.00 -
• Lot Relocation lot 8,000.00 -
• Staking out/layout lot 2,500.00 -
• Termites and Pesticides Treatment for structural preparation lot 25,000.00 -
• Occupancy Permits (Owner's Supply -
• Construction Permits (owner's supply) -
Sub Total = -
II. CIVIL /STRUCTURAL WORKS
II.i. CONCRETING/MASONRY WORKS/REINFORCEMENTS
RC Footings (3000 PSI) m³
• Cement bgs 250.00 -
• Sand m³ 1,200.00 -
• Gravel 3/4" m³ 2,000.00 -
• 16 mmø def bar (6meters) pcs 400.00 -
• 10 mmø def bar (Grade 33) pcs 220.00 -
• GI Tie Wire # 16 kgs 85.00 -
-
RC Columns (3000 PSI) m³
• Cement bgs 250.00 -
• Sand m³ 1,200.00 -
• Gravel 3/4" m³ 2,000.00 -
• 16 mmø def bar (Grade 33) pcs 400.00 -
• 10 mmø def bar (Grade 33) pcs 220.00 -
• GI Tie Wire # 16 kgs 85.00 -
-
Tie beams (3000 PSI) m³
• Cement bgs 250.00 -
• Sand m³ 1,200.00 -
• Gravel 3/4" m³ 2,000.00 -
• 12 mmø def bar (Grade 33) pcs 350.00 -
• 10 mmø def bar (Grade 33) pcs 250.00 -
• GI Tie Wire # 16 kgs 85.00 -
BILL OF MATERIALS
Item No. Item Description Quantity Unit Unit Price, Php Amount, Php
Suspended Slab (3000 PSI) m³
• Cement bgs 250.00 -
• Sand m³ 1,200.00 -
• Gravel 3/4" m³ 2,000.00 -
• 12 mmø def bar (Grade 33) top bars pcs 350.00 -
• 12 mmø def bar (Grade 33) bottom bars pcs 350.00 -
• GI Tie Wire # 16 kgs 85.00 -
BILL OF MATERIALS
Item No. Item Description Quantity Unit Unit Price, Php Amount, Php
III. ARCHITECTURAL WORKS
III.i CEILING WORKS
• Metal Furring (JEAMaxx G.24) pcs 110.00 -
• Carrying Channel (JEAMaxx G.24) pcs 130.00 -
• Double U-Clip (JEAMAxx) pcs 5.00 -
• Wall Angle (JEAMaxx G.24) pcs 80.00 -
• Blind rivets 1/8" dia. X 1/2" (1000 PCS PER BOX) boxes 450.00 -
• Gypsum Board (9mm) pcs 750.00 -
• Gypsum Mesh Tape pcs 150.00 -
• black screw pcs 1.00 -
• consumables lot 7,000.00 -
Sub Total =
III.ii DOORS & GLASSES
GLASSES .
• GLASS ENCLOSURE set 15,000.00 -
• Sliding Door (2-panel 95W x 280H in 1/4 Bronze glass & analok finish) set 25,000.00 -
• Awning Windows & Fixed (0.6 x 0.6) set 5,000.00 -
• Exterior Windows (1.0 x 1.2 ) set 5,000.00 -
• Exterior Windows (1.0 x 1.0) set 3,500.00 -
• Fixed Window With Glass (5.4 x 0.6 ) set 25,000.00 -
DOORS .
• Matwood Solid Panel Doors (1.0 x 2.1 ) WITH ACCESSORIES set 25,000.00 -
• Matwood Panel Type Doors (0.8 x 2.1) set 18,000.00 -
• Matwood Panel Type Doors (0.7 x 2.1) set 15,000.00 -
• CR Door - Painted Flush Door (0.8 x 2.1) set 10,000.00 -
• (OTHERS SPECIFY) lot -
Sub Total = -
III.iii TILE WORKS (Supply and installation of wall and floor tiles) sqm
• Balcony Tiles (60 x 60 tiles) pcs 250.00 -
• Tile Adhesive bags 550.00 -
• Cement bags 250.00 -
• Sand m³ 500.00 -
• Tile Grout (2kg) bags 99.00 -
• tile spacers pcs 2.00 -
• Consumables lot 10,000.00 -
Sub Total =
III.iv PAINTING WORKS
• Flat latex (Boysen) gallons 850.00 -
• Semi gloss latex 2nd and final coating (Boysen) gallons 850.00 -
• Skim Coat bags 550.00 -
• # 7 paint roller pcs 75.00 -
• # 2 paint brush pcs 75.00 -
• Sand Paper pcs 35.00 -
• Consumables( sandpaper, rollers, paint brush) lot 20,000.00 -
Sub Total =
MST CONNECT BUILDERS
Date: Floor Area: 113.88 sqm Lot area: 160 sqm
Project: PROPOSED TWO STOREY RESIDENCE Location : MANILA PH
Owner Elon Musk
BILL OF MATERIALS
Item No. Item Description Quantity Unit Unit Price, Php Amount, Php
IV. PLUMBING WORKS
SEWERLINE
• 4''Ø uPVC Pipe (Neltex-orange) pcs 750.00 -
• 4''Ø uPVC Pipe elbow (Neltex-orange) pcs 750.00 -
• 4''Ø uPVC clean out pcs 175.00 -
• 4''ØX 2" Reducer uPVC WYE pcs 175.00 -
• 3''Ø uPVC Pipe (Neltex-orange) pcs 750.00 -
• Floor drains pcs 500.00 -
• Pipe Fittings lot 10,000.00 -
• 6 inches pvc pcs 800.00 -
• 2''Ø uPVC Clean out (Neltex) pcs 200.00 -
• 2''Ø uPVC Pipe (Neltex-orange) pcs 280.00 -
• 2''Ø uPVC p-trap (Neltex) pcs 150.00 -
WATER LINE
• 1/2''Ø uPVC Pipe (Neltex-blue) (3m) pcs 130.00 -
• 1/2''Ø uPVC Elbow pcs 25.00 -
• 1/2'' Ø uPVC Tee (Neltex) pcs 25.00 -
• 1/2'' Ø uPVC Coupling (Neltex) pcs 25.00 -
• Check Valve pcs 350.00 -
• Gate Valve pcs 350.00 -
• Water Meter pcs 2,000.00 -
• Pipe Fittings (consumables) lot 15,000.00 -
• Teflon Tape pcs 25.00 -
PLUMBING FIXTURES
• Kitchen Stainless Sink ( FRANKE SSX-110-45) (OSM) unit 9,000.00 -
• Goose Neck Faucet (KASCH ) pcs 2,000.00 -
• Sink Drain and Accessories pcs 800.00 -
• Lavatory (Pozzi Chegda) unit 5,000.00 -
• Faucet (KASCH LJ-5003, faucet 304 SS) pcs 3,000.00 -
• Lavatory Accessories lot 2,000.00 -
• Water Closet (Pozzi) unit 12,000.00 -
• Stainless Bidet pcs 2,000.00 -
• Angle Valves pcs 500.00 -
• Flexible Hoses pcs 750.00 -
• Shower with accessories set 10,000.00 -
• Pipe Fittings lot 15,000.00 -
• Water Heater Panasonic unit 9,000.00 -
• Septic Tank and Catch Basin lot
6 INCHES CHB pcs 15.00 -
Cement bgs 250.00 -
Sand m³ 800.00 -
Gravel 3/4" m³ 1,600.00 -
12 mmø def bar (Grade 33) pcs 350.00 -
10 mmø def bar (Grade 33) pcs 250.00 -
GI WIRE No. 16 kgs 85.00 -
4INCHES PVC PIPE pcs 750.00 -
4 INCHES CLEAN OUT pcs 250.00 -
4 INCHES TEE pcs 200.00 -
• consumables lot 5,000.00 -
Sub Total = -
MST CONNECT BUILDERS
Date: Floor Area: 113.88 sqm Lot area: 160 sqm
Project: PROPOSED TWO STOREY RESIDENCE Location : MANILA PH
Owner Elon Musk
BILL OF MATERIALS
Item No. Item Description Quantity Unit Unit Price, Php Amount, Php
V. ELECTRICAL WORKS
• Wiring And Piping -
• 20mmØ PVC Pipe (Neltex) pcs 200.00 -
• 5.5 mm² THHN (Phelps Dodge) boxes 4,500.00 -
• 3.5 mm² THHN (Phelps Dodge) mtrs 120.00 -
• Switches -
• 1 gang switch (Panasonic) pcs 250.00 -
• 2 gang switch (Panasonic) pcs 250.00 -
• 3 gang switch (Panasonic) pcs 250.00 -
• Outlets -
• 2 gang Convenience Outlet Universal (Panasonic) pcs 350.00 -
• AC .WH, Ref Outlets pcs 350.00 -
• Lighting Fixtures -
• Ceiling Mounted Light (40watts) pcs 500.00 -
• Centerlights pcs 1,000.00 -
• 1x18W PHILIPS FS 13804 GLASS RECESSED WHITE W/ 9W ESS LEDBULB E27 pcs 250.00 -
• Ceiling Mounted Light pcs 250.00 -
• Panel Board (GE or Specs. Of the Bldg. Admin.) -
• 100A pcs 2,000.00 -
BRANCHES
• 30AT/50AF pcs 750.00 -
• 20AT/50AF pcs 500.00 -
PANEL BOARD SET 5,000.00 -
• Electrical Tape pcs 80.00 -
• Pvc Pipe Fittings lot 15,000.00 -
• Utility Box pcs 25.00 -
• Junction Box pcs 35.00 -
• Exhaust Fan {XFC - 300 OMNI (12 inches)} pcs 1,200.00 -
Service Entrance Installation
• 1" RSC PIPE pcs 1,250.00 -
• 1" RECEPTICLE pcs 120.00 -
• Pipe Clamps pcs 200.00 -
• 30 mm² THHN (Phelps Dodge) mtrs 380.00 -
• Base meter pcs 1,500.00 -
Sub Total =
labor cost
VII. TINSMITHRY/ROOFING WORKS
• Roof framing and Roof Installation lot
C-Purlins (2" x 3") pcs 650.00 -
LONG SPAN lm 450.00 -
Epoxy Painted Tubular Framing gal 350.00 -
Ga 22 Gutter/Flashing pcs 800.00 -
18mm Hardiflex Senepa pcs 450.00 -
2" x 6" x 1.5mm thck Tubular Rafter pcs 1,200.00 -
1.5 ROOF SCREWS pcs 2.00 -
10mm double foil insulation (50meters) roll 3,000.00 -
• consumables lot 16,000.00 -
Sub Total =
MST CONNECT BUILDERS
Date: Floor Area: 113.88 sqm Lot area: 160 sqm
Project: PROPOSED TWO STOREY RESIDENCE Location : MANILA PH
Owner Elon Musk
BILL OF MATERIALS
Item No. Item Description Quantity Unit Unit Price, Php Amount, Php
VIII. Metal Works
• Metal Entrance Gate and Side Gate (2x4 Tubular Painted) & Handrails lot 15,000.00 15,000.00
• Stair Railings lot 35,000.00 35,000.00
• Balcony Railings lot 15,000.00 15,000.00
• (OTHERS SPECIFY) lot -
Sub Total =
BILL OF MATERIALS
Item No. Item Description Quantity Unit Unit Price, Php Amount, Php
Material Cost = -
Labor Cost= -
SUBTOTAL= -
Miscellaneous cost= -
Vats/Taxes=
Overhead/Profit= -
Grand Total= -
Date
TARGET ACCOMPLISHMENT
(Please indicated the days if working or
calendar)
____210____ WORKING DAYS
________CALENDAR DAYS
EXCLUSION
• FURNITURES
• AIRCONS
• WATER HEATER
• SWIMMING POOL
• (OTHERS SPECIFY)
• (OTHERS SPECIFY)
• (OTHERS SPECIFY)
APPROVED/ACKOWLEDGE BY
NAME
OWNER
Date