Bill of Materials

Project : Carport
Location :
Date : July 6, 2023

No. Description Quantity Unit Cost Amount


1 EARTH WORKS
Excavation 4.69 cu. mtrs 150.00 703.80
Gravel Bed, Washed 3/4" - Ø 0.21 cu. mtr 1,200.00 253.20
2 CONCRETE WORKS - Wall Footing V= 0.27 cu. mtr
Cement - Portland, 40 kg/bag 2.01 bags 230.00 462.30
Sand, Coarse 0.13 cu. mtr 230.00 30.82
Gravel, Washed 3/4" - Ø 0.27 cu. mtr 1,200.00 321.60
DSB, 10 mm-Ø x 6.00m 3.00 pcs 140.00 420.00
DSB, 8 mm-Ø x 6.00m 2.00 pcs 90.00 180.00
GI Tie Wire #16 1 0.32 kg 70.00 22.18
3 CONCRETE WORKS - Column Footing V= 1.01 cu. mtrs
Cement - Portland, 40 kg/bag 7.56 bags 230.00 1,738.80
Sand, Coarse 0.50 cu. mtr 230.00 115.92
Gravel, Washed 3/4" - Ø 1.01 cu. mtrs 1,200.00 1,209.60
DSB, 12 mm-Ø x 6.00m 8.00 pcs 220.00 1,760.00
GI Tie Wire #16 1 0.85 kg 70.00 59.70
4 CONCRETE WORKS - Column V= 0.52 cu. mtr
Cement - Portland, 40 kg/bag 3.87 bags 230.00 890.10
Sand, Coarse 0.26 cu. mtr 230.00 59.34
Gravel, Washed 3/4" - Ø 0.52 cu. mtr 1,200.00 619.20
DSB, 12 mm-Ø x 6.00m 7.00 pcs 220.00 1,540.00
DSB, 8 mm-Ø x 6.00m 11.00 pcs 90.00 990.00
GI Tie Wire #16 1 1.27 kgs 70.00 88.73
5 CONCRETE WORKS - Slab V= 1.52 cu. mtrs
Cement - Portland, 40 kg/bag 11.42 bags 230.00 2,627.18
Sand, Coarse 0.76 cu. mtr 230.00 175.15
Gravel, Washed 3/4" - Ø 1.52 cu. mtrs 1,200.00 1,827.60
DSB, 10 mm-Ø x 6.00m 8.00 pcs 140.00 1,120.00
GI Tie Wire #16 1 0.59 kg 70.00 41.44
6 CONCRETE WORKS - Beams (B,LB,BB) V= 0.16 cu. mtrs
Cement - Portland, 40 kg/bag 1.23 bags 230.00 282.56
Sand, Coarse 0.08 cu. mtrs 230.00 18.84
Gravel, Washed 3/4" - Ø 0.16 cu. mtrs 1,200.00 196.56
DSB, 12 mm-Ø x 6.00m 3.00 pcs 220.00 660.00
DSB, 8 mm-Ø x 6.00m 5.00 pcs 90.00 450.00
GI Tie Wire #16 1 0.56 kgs 70.00 38.98
7 MASONRY - CHB Wall A= 13.00 sq. mtrs
CHB, 4" x 8" x 16" 13.00 170.00 pcs 7.50 1,275.00
Cement - Portland, 40 kg/bag 4.06 bags 230.00 934.38
Sand, Coarse 0.70 cu. mtrs 230.00 161.16
Gravel, Washed 3/8" - Ø 0.39 cu. mtrs 1,200.00 468.00
DSB, 10 mm-Ø x 6.00m 9.00 pcs 220.00 1,980.00
GI Tie Wire #16 1 0.67 kgs 70.00 46.62
8 MASONRY - Plastering A= 10.00 sq. mtrs
Cement - Portland, 40 kg/bag 2.02 bags 230.00 463.68
Sand, Fine 0.16 cu. mtrs 230.00 36.80
9 ROOFING 11.7
Rib-type (Eff. Width = 1.0m)
3.90 m 3.00 pcs. 858.00 2,574.00
10 ROOF FRAMING
C-Purlins, Ga.1.6 x 2" x 6" x 20' 127.12 2.00 pcs 900.00 1,800.00
C-Purlins, Ga.1.6 x 2" x 4" x 20' 5.50 1.00 pcs 653.00 653.00
Battens, 6.00m 106 4.00 pcs 420.00 1,680.00
Fascia Board, 3/8" x 12" x 8' 53.6 3.00 pcs 195.00 585.00
Pre-painted Gutter, 24" x 2.44m 16.5 2.00 pcs 565.00 1,130.00

Printed : 06/07/2023 6:38 am Page 1 of 2


Pre-painted Flashing Gutter, 24" x 2.44m 4.6 2.00 pcs 565.00 1,130.00
End Wall Flashing, 18" x 2.44m 4.00 pcs 397.50 1,590.00
Red - Oxide 1.12 ltrs 80.00 89.60
Paint Thinner 0.56 ltrs 65.00 36.40
Cutting Disk 1.00 pcs 120.00 120.00
Tekscrew 59.00 pcs 2.00 118.00
Metal Screw #8 x 3/4" 100.00 pcs 1.00 100.00
Ficem Screw #8 x 1-1/2" 48.00 pcs 1.00 48.00
Blind Rivets, 7mm x 50mm 96.00 pcs 1.00 96.00
Welding Rod, 1/8" - Ø 5.00 kgs 70.00 350.00
11 ELECTRICAL WORKS - Rough-Ins & Wiring
Moldflex, 1/2"-Ø x 100m 1.00 rolls 600.00 600.00
Utility Box, 2" x 4" 1.00 pcs 20.00 20.00
Junction Box, 4" x 4" 1.00 pcs 20.00 20.00
12 ELECTRICAL WORKS - Fixtures & Service Entrance
Bulb Socket 1.00 pcs 50.00 50.00
Switch, 1-Gang 1.00 sets 85.00 85.00
13 PAINTING WORKS
FWL Primer 3.00 ltrs 140.00 420.00
MAT FIN. Topcoat, (Common Wall) 4.00 ltrs 180.00 720.00
MAT FIN. Topcoat, (Ceiling, Fascia Board) 2.00 ltrs 180.00 360.00
Patching Compound 0.14 sack 320.00 43.20
Concrete Neutralizer 0.10 ltrs 35.00 3.50
Boysen Acrytex Cast 1.00 gals 450.00 450.00
Boysen Acrytex Reducer 0.50 gals 370.00 185.00
Sandpaper, #100 2.00 pcs 15.00 30.00
Sandpaper, #120 2.00 pcs 15.00 30.00
Stuffa 1.00 kgs 70.00 70.00
Old Newspaper 1.00 kgs 15.00 15.00

Projected Material Cost : 45,829.41


Projected Labor Cost : 19,035.56

Projected Construction Cost : 64,864.97