Professional Documents
Culture Documents
Earned Value Analysis: Whatisit? Whydoineedit? Howdoidoit?
Earned Value Analysis: Whatisit? Whydoineedit? Howdoidoit?
What Is It ?
Why Do I Need It ?
How Do I Do It?
1
Todays Situation
2
Theres Room For Improvement
3
How to answer the
question: Have we done what
we said wed do?
% complete
estimating % of
Budget spent % of
work done % of
time elapsed
subjective, incomplete
draws false
conclusions
4
Enter Earned Value
Analysis
Earned Value Analysis is:
an industry standard way to:
measure a projects progress,
forecast its completion date and final cost,
and
provide schedule and budget variances
along the way.
5
Whats more Important?
6
EVA Integrates All Three
7
Earned Value needed
because...
8
Earned Value needed
because...
9
And One More
Reason
Why You Need EVA
? 10
Because You Gotta !
These Set the Stage:
GPRA; 1993
FASA, Title V; 1994
Clinger-Cohen Act; 1996
12
So, Is This Stuff New ?
13
Examples of informal Earned Value
Analysis
Cost comparisons
Budget vs. Actual
14
Hows this project doing?
120000
100000
80000
Projected
60000
Actual
40000
20000
0
Jan-03 Feb-03 Mar-03 Apr-03 May-03 Jun-03 Jul-03 Aug-03 Sep-03 Oct-03 Nov-03 Dec-03
15
Lets Take A Look Under The
Hood
16
But First! - We gotta get
organized
Obviously in small
bites.
18
Proper WBS Design
19
A sample Work Breakdown
Structure
Serve Pizzas to Customers
20
WBS Units are Work Packages
21
Control Account Plans
24
Earned Value Definitions
25
BCWS - Budgeted Cost of Work
Scheduled
120000
100000
80000
60000 BCWS
40000
20000
Nov-03
Jan-03
Jun-03
Jul-03
Aug-03
Feb-03
Mar-03
Apr-03
May-03
Sep-03
Oct-03
Dec-03
26
Earned Value Definitions
(cont.)
27
ACWP - Actual Cost of Work Performed
120000
100000
80000
56000 BCWP
60000
ACWP
49000
40000
20000
Nov-03
Jan-03
Jun-03
Jul-03
Aug-03
Dec-03
Mar-03
Apr-03
Sep-03
Oct-03
Feb-03
May-03
28
Earned Value Definitions
(cont.)
29
BCWP - Budgeted Cost of Work
Performed
120000
100000
80000
55000 BCWP
60000
49000 BCWS
40000
20000
Nov-03
Jan-03
Jun-03
Jul-03
May-03
Feb-03
Mar-03
Apr-03
Sep-03
Oct-03
Dec-03
Aug-03
30
The Whole Story
120000
100000
80000
56000 BCWS
60000 BCWP
55000
49000 ACWP
40000
20000
Nov-03
Jul-03
Jan-03
Jun-03
Feb-03
Mar-03
May-03
Aug-03
Sep-03
Oct-03
Dec-03
Apr-03
31
Some Derived Metrics
behind schedule
budget.
32
Schedule Variance & Cost Variance
33
Some More Derived Metrics
34
Performance Metrics
SPI: BCWP/BCWS
49,000/55,000 = 0.891
CPI: BCWP/ACWP
49,000/56000 = 0.875
35
Making Projections
Once a project is 10% complete, the
overrun at completion will not be less
than the current overrun.
20000
Nov-03
Jul-03
Jan-03
Jun-03
Feb-03
Mar-03
May-03
Aug-03
Sep-03
Oct-03
Dec-03
Apr-03
37
Estimate to Complete
140000
120000 116,571
100000 102000
Today BCWS
80000
BCWP
60000
ACWP
40000
20000
0
38
A New Criteria
39
Value of Earned Value
Schedule Status
Reporting
Cost Status Reporting
Forecasting
40
But How Do I Do All This Stuff
?
Quantifying/measuring work
progress can be difficult.
45
Summary
EVA & EVMS will help reduce guesswork in:
Measuring performance
forecasting
Need to get beyond misleading measures
of progress.
Reasons to use EVA and EVMS:
Good project management practice
OMB requirement
Incorporate into contracts
46
Earned Value
Resources
http://www.pmi.org/
http://www.acq.osd.mil/pm/
47
Some Compliant Systems
Welcom Cobra http://www.welcom.com/
Schedulemaker http://www.schedulemaker.com/
Winsight http://www.cs-solutions.com
48
Earned Value Analysis
Questions/Discussion
49