Paul A. Jensen
Operations Research Models and Methods
8/27/04 Copyright 2004 - All rights reserved
Topics
Dependent Events
Statistical Fluctuations
Drum, Buffer, Rope Scheduling
2
Dependent Events
3
What are dependent events?
8 4 12 6 9
Finished
Raw
D B2 C B1 A
Goods
Materials
4
What happens if we ask
everyone to be efficient?
8 4 12 6 9
Finished
Raw
D B2 C B1 A
Goods
Materials
5
How can we control a system
with dependent events?
Step 1: Identify the system’s bottleneck
Step 2: Exploit the system’s bottleneck
Step 3: Subordinate everything else to the
bottleneck
6
How can we improve a system
with dependent events?
Step 4: Elevate the system’s constraint.
7
Focus on the bottleneck
What is time worth on the bottleneck?
What is time worth on the non-
bottlenecks?
8
What are the benefits of this
process?
Better process
control
Reduced
inventories
Reduced operating
expenses
Increased
throughput
9
Concepts: Dependent Events
Can we have bottlenecks in systems
with independent events?
What is a bottleneck?
How do we control with a bottleneck?
What are the benefits of this control?
Where should we focus improvement
efforts?
Should we have a bottleneck?
10
Statistical Fluctuations
11
Should we balance the
capacities in the line?
8 4 8 4 8
Finished
Raw
D B2 C B1 A
Goods
Materials
12
What is the effect of statistical
fluctuation?
8 4 8 4 8
Finished
Raw
D B2 C B1 A
Goods
Materials
14
Concepts: Statistical
Fluctuations
What is the effect of statistical
fluctuation?
Is it good to balance the capacities in
the line?
Why is it helpful to have a bottleneck in
the line?
15
Drum, Buffer, Rope
Scheduling
16
What happens if Herbie cannot
be put at the front of the line?
8 4 12 6 9
Finished
Raw
D B2 C B1 A
Goods
Materials
17
We need some way to control
those who are in front of Herbie
Finished
Raw
D B2 C B1 A
Goods
Materials
Lot Size = 25
Time
19
Drum, Buffer, Rope
Scheduling System
Drum: A schedule for the
Constraint resource Rope
Buffer
A
Buffer = 425
Finished
Raw
D B2 C B1 A
Goods
Materials
21
How does the rope affect the
cycle time?
What happens when we increase the rope?
Do we want the rope large or small?
22
How does the cycle time affect
work in process (inventory)?
Work in Process = (cycle time)*(Flow Rate)
Time in machine C = 12 minutes.
Flow rate = (1/12) units per minute.
Cycle time = 1500 minutes.
Work in Process = (1/12) units per minute*1500
minutes
= 125 Units.
8 4 12 6 9
Finished
Raw
D B2 C B1 A
Goods
Materials
23
How do we select the length
(time) of the rope?
Why would we like to keep the rope
relatively long?
Why would we like to keep the rope
relatively short?
Which is the most important effect?
24
Concepts (D, B, R)
What is the drum?
What is the rope?
What is the buffer
How do we select the length (time) of
the rope?
25