You are on page 1of 33

API 510 Preparatory Class

Lesson 11
Corrosion Calculations
Corrosion Example Problems

A 60 foot tower consisting of four (4) shell courses was


found to have varying corrosion rates in each course.
Minimum wall thickness readings were taken after 4 years
and 6 months of service. All original wall thicknesses
included a 1/8" corrosion allowance.
The top course's original thickness was .3125". The present
thickness is .3000". The second course downward had an
original thickness of .375".
During the inspection it was found to have a minimum wall
thickness of .349". The third course was measured at .440"
its original thickness was .500". The bottom course had an
original thickness of .625" and measured to be .595".
Corrosion Example Problems

Determine the metal loss for the top course, the corrosion
rate for the second course, the corrosion allowance
remaining in the third course, the retirement date for the
bottom course.
Corrosion Example Problems

Solution A:

TOP COURSE:
Metal loss equals the previous thickness minus the present
thickness.

Previous .3125"
Present -.3000"
.0125" Metal Loss
Corrosion Example Problems

SECOND COURSE:
Corrosion rate equals metal loss per given unit of time.

Previous .3750
Present - .3490"
.0260"

Loss .0260"
Metal Loss = = .006"/ Per Year
Time 4.5 years
Corrosion Example Problems

THIRD COURSE:

Remaining Corrosion Allowance equals the actual thickness


minus the required thickness.

Original Thickness .500"


Original C. A. -.125"
Required Wall Thickness .375"

Actual Wall Thickness .440"


Required Wall -.375"
Remaining C.A. .065
Corrosion Example Problems

BOTTOM COURSE

Remaining life equals the remaining corrosion allowance


divided by the corrosion rate.

1. Required Thickness

Original Thickness .625"


Original C. A. -.125"
Required Thickness .500
Corrosion Example Problems

2.Remaining Corrosion Allowance


Actual Wall Thickness .595
Required Thickness -.500"
Remaining Corr. Allow .095

3.Corrosion Rate
Original Thickness .625"
Present Thickness -.595
Metal Loss .030"

Metal Loss .030 = Corrosion Rate = .0067"/Yr.


Time 4.5 Years
Corrosion Example Problems

4. Remaining Life

Corrosion Allowance.095 = 14.2 Yrs. Remaining Life


Corrosion Rate .0067"/Yr.
Corrosion
Just Milling Around

In the previous examples we calculated using decimal


fractions of an inch such as .006. However questions
on the exam often have the format of Mils or
thousandths of and inch. So if you are not familiar with
this terminology here are some examples.
.1 = 1/10th of an inch
.01 = 1/100th of an inch
.001 = 1/000th of an inch or 1 Mil. this is what is used.
Take our example above .006 this translates to 6 Mils.
.0067 translates to 6.7 Mils.
Class Quiz
Just Milling Around

1. Convert the following decimal fractions into Mils.


.195 = _____ Mils
. 023 = _____ Mils
.009 = _____ Mils.
.0011 =______Mils.

2. Calculate or previous Remaining Life problem using Mils.


Corrosion Allowance.095 = 14.2 Yrs. Remaining Life
Corrosion Rate .0067"/Yr.
Solution
Just Milling Around

Converting the following decimal fractions into Mils.


.195 = 195 Mils
.023 = 23 Mils
.009 = 9 Mils.
.0011 = 1.1 Mils.

Corrosion Allowance 95 Mils = 14.2 Yrs. Rem. Life


Corrosion Rate 6.7 Mils/Yr.
Time
A year has 12 parts

The next issue is how do you handle the odd months in


a year. Its all good when it has been an even number of
years. However what about 2 years and 5 months?
Five months is 5/12th of a year. 5/12 = .416 years
rounded to 3 places. Of course 6 months is then 6/12 or
.5 years.
Example: Based on 4.416 years and a metal loss of 50
Mils we have;
Metal Loss 50 Mils = Corrosion Rate = 11.3 Mils/Yr.
Time 4.416 Years
Class Quiz
Time
A vessel shell course was replaced in October of 1980.
The initial or, baseline thickness was .505. The most
recent actual thickness measured was .485 in January
1991. What is the corrosion rate, based in Mils per year
in January of 1991.
Solution

.505(t-initial) - .485(t-actual) = .020 = 20 Mils


Oct.1990 Oct.1980 = 10 years plus November, December
of 1990 and January of 1991 so; 10 yrs. 3 Mos.
10 - 3/12th (3/12 = .250) = 10.25 years
Therefore;
Metal Loss 20 Mils = Corrosion Rate = 1.95 Mils/Yr.
Time 10.25 Years
Can there be two Corrosion Rates?

Yes, in the API 510 there are, the Long Term and Short
Term. Here is the Long Term. From API 510 6.4 page 6-3

The long term (L.T.) corrosion rate shall be calculated from


the following formula:

t(inital) - t(actual)
Corrosion rate (L.T.) = time(years ) between t(inital) and t(actual)
Corrosion Example Problems

The short term (S.T.) corrosion rate shall be calculated from the
following formula:

t previous - t actual
Corrosion rate (S.T.) = time (years) between t previous and t actual
Corrosion Example Problems

tinitial = the thickness, in inches(millimeters), at the same


location as t actual measured at the initial installation or at
the commencement of a new corrosion rate environment.

tprevious = the thickness, in inches(millimeters), at the same


location as t actual measured during a previous inspection.

Long-term and short-term corrosion rates should be


compared to as part of the data assessment. The authorized
inspector, in consultation with a corrosion specialist, shall
select the corrosion rate that best reflects the current
process.
Corrosion Example Problems

Example:
A vessel shell had a second set of ultrasonic thickness
measurements after 1 year of service, the original baseline
wall thickness was 0.500, and the second set revealed that
the shell was now at 0.489. Five years later a third set of
wall readings were taken and the shell was measured to be
0.459.
What value should be used in the Remaining Life
calculations? Comparing short term to long term corrosion
we find the following values. Normally the most aggressive
will be used and in this case it will be the Long Term
Corrosion Rate.
Corrosion Example Problems

0.500- 0.459
L.T. = = 6.8 Mils/ year
6 years

0.489 - 0.459
S.T. = = 6 Mils/ year
5 years
The remaining life of the vessel shall be calculated from the
following formula:
t actual - t required
Remaining life (years) = corrosion rate (6.4)
Corrosion Example Problems

tactual = the actual minimum thickness, in inches determined


at the time of inspection for a given location or component.
trequired = the required thickness in inches at the same
location or component as the t actual measurement
computed by the design formulas (e.g. , pressure and
structural) before corrosion allowance and manufacturers.

Example: Determine Remaining life of the vessel shell


course in the example above. T required thickness of the
shell course is 0.388 (known as t minimum). Compare S.T.
and L.T. corrosion rates as follows:

S.T. rate = 0.006 or 6 Mils a year


L.T. rate = 0.0068 or 6.8 Mils a year
Corrosion Example Problems

Therefore we will use the most aggressive corrosion rate


found to be the Long Term Rate.

Remaining life (years)


0.459"- 0.338" 0.121" 121Mils
17.79Yrs
0.0068"a year 0.0068" 6.8 Mils

What would be the maximum length of time before the next


inspection?

ANS: the Remaining Life or 10 years whichever is less.

Therefore: 17.79/2 = 8.895 years


Corrosion Example Problems

What would be the maximum length of time before the next


inspection? From: API 510 page 6-2
6.4 Internal An On-Stream Inspection
The period between internal or on-stream inspections shall
not exceed one half the estimated remaining life of the
vessel based on corrosion rate or 10 years, whichever is
less. In cases where the remaining safe operating life is
estimated to be less than 4 years, the inspection interval
may be the full remaining safe operating life up to a
maximum of 2 years.
ANS: the Remaining Life or 10 years whichever is less.
Therefore: 17.79/2 = 8.895 years
Example 5.7 Page 5-3
Corrosion
(a) (the second a) For a corroded area of considerable size
in which the Circumferential Stress Govern, the least
thickness along the most critical element of the area may be
averaged over a length not exceeding the following:
1. For vessels with the inside diameters less than or equal to
60 inches one half the vessel diameter or 20 inches
whichever is less.
2. For vessels with the inside diameters greater than 60
inches one third the vessel diameter or 40 inches whichever
is less.
Corrosion and Minimum Thickness Evaluation
5.7
For a corroded area of considerable size in which the
Circumferential Stress Govern, the least thickness along
the most critical element of the area may be averaged over
a length not exceeding the following:
1. For vessels with the inside diameters less than or equal to
60 inches one half the vessel diameter or 20 inches
whichever is less.
2. For vessels with the inside diameters greater than 60
inches one third the vessel diameter or 40 inches whichever
is less.
Corrosion and Minimum Thickness
Evaluation

When the area contains an opening the distance on either side


of the opening within which the thicknesses are averaged shall
not extend beyond the limits of the reinforcement as defined in
the ASME Code.

See Fig. UG-37 and refer to reinforcement calculations for


determining the extra metal in the shell.
For Limits:
d ( t tr) or 2(t + tn) ( t tr)
Use the Larger
Corrosion and Minimum Thickness
Evaluation
Widely scattered pits may be ignored as long as the
following are true:

1. The remaining thickness below the pit is greater than one-


half the required thickness. (1/2 t required)
1.0 0.125 = 0.875 the required thickness
Therefore no pit equal to 0.875/2 = 0.4375 or greater!
Pit #3 0.402 < 0.4375 Acceptable.
Corrosion and Minimum Thickness Evaluation
2. The total area of the pits does not exceed 7 square inches
(45 sq. centimeters) within any 8 inch (20 centimeter)
diameter circle.
We will assume the pits to be circles and use the formula Pi
x Radius Squared to determine the area of each pit.
Pit # One 3.141 x (0.170/2) 2 = 0.085 2 = 0.0226 sq.
in.
Pit # Two 3.141 x (0.330/2) 2 = 0.165 2 = 0.0855 sq.
in.
Pit # Three 3.141 x (0.250/2) 2 = 0.125 2 = 0.0490 sq.
in.
Pit # Four 3.141 x (0.377/2) 2 = 0.1185 2 = 0.1116 sq.
in.
Total: 0.2678 sq. in.
less than 7 sq. inches Acceptable!
Corrosion and Minimum Thickness
Evaluation

3. The sum of their dimensions along any straight line within


the circle does not exceed 2 inches
Straight line for pits 1-3-4
#1. 0.170
#3. 0.250
#4. 0.377
Total 0.797 < 2 inches Acceptable
When the surface at a weld with a joint factor other than 1.0
as well as the surfaces remote from the weld is corroded, an
independent calculation using the appropriate weld joint
factor must be made to determine if thickness at the weld or
remote from the weld governs the allowable working
pressure.
Corrosion and Minimum Thickness
Evaluation
For this calculation the surface at a weld includes 1 inch on
either side of the weld, (measured from the toe of the weld),
or twice the minimum thickness on either side of the weld,
whichever is greater.
Corrosion and Minimum Thickness
Evaluation

When measuring the corroded thickness of ellipsoidal


and torispherical heads the governing thickness may be
as follows:

1. The thickness of the knuckle region with the head rating


calculated by the appropriate head formula.

2. The thickness of the central portion of the dished region in


which case the dished region may be considered to be a
spherical segment whose allowable pressure is
calculated by the Code formula for spherical shells.
Corrosion and Minimum Thickness
Evaluation

3. For calculating the spherical portion using the spherical


formula the following applies to find the spherical radius L:
a. L = the OD of the Torispherical head
b. L = the ID of the shell times 90% for 2 to 1 Ellipsoidal
heads
See 5.7 second e.
Corrosion Over
And Out

You might also like