Professional Documents
Culture Documents
Calculation
Engine
( Critical Path
Scheduling
Engine )
Monte Carlo simulations use distributions as inputs, which are also the
results
Monte Carlo Schedule Analysis
1 2 3 4 5 6 7 2 3 4 5 6 7 8 1 2 3 4 5 6 7
Task 1
Task 3
Task 2
7
6
5
4
3
2
1
8 9 10 11 12 13 14 15 16
Distribution-based approach
Event-based approach
Monte Carlo can be used to simulate the
results of discrete risk events with
probability and impact on multiple activities
What Distribution Should Be Used?
The correct answer is close to 4%, however, most people would think
that answer is a little bit lower than 80%.
Role of Emotions
Pose a direct question: What is the probability that the project will be
canceled due to budgetary problems?
Ask the experts two opposing questions: (1) What is the probability that
the project will be canceled? and (2) What is the probability the
project will be completed? The sum of these two assessments should
be 100%.
Break compound events into simple events and review them separately.
Probability Wheel
Use of visual aids like a probability wheel can aid in the increasing
validity of estimates
Eliciting Judgment: Probability Method
Probability
Frequency 20 100%
16 80%
12 60%
8 40%
4 20%
Question: What is the chance that duration
is less than 3 days?
2 3 4 5 6
Task Duration
(days)
Eliciting Judgment: Method of Relative Heights
Probability
Frequency
10 50%
8 40%
6 30%
4 20%
2 10%
2 3 4 5 6
Question: How many times the duration
will be between 2 and 3 days? Task Duration
(days)
6 days
100%
80%
60%
Chance to meet a deadline
is reducing as a results of events
40%
20%
0%
0 2 4 6 8 10 12 14
Project Duration (weeks)
When Monte Carlo Is Useful
Project Decisions:
The Art and Science
Management Concepts, Vienna, VA, 2007
Project Think:
Why Good Managers Make Poor Project
Choices
Gower, 2013
Questions?