Predictability
Daniel S. Vacanti
ActionableAgileTM
daniel@actionableagile.com
@danvacanti
“When will it be done?”
“When will it be done?”
Elapsed Time
“When will it be done?”
Here’s
a spot!!
Try an experiment for
me…
Elapsed Time
Calendar Time
Try the same thing
for your process
Start Timer Stop Timer
12.5%
Does that mean 12.5% was the
only possible outcome?
Start Timer Stop Timer
2
Backlog Design Develop Test Deployed
Will Item #3
2
end up as…
Or Exactly
Exactly
this dot?
Exactly this dot?
this dot?
Backlog Design Develop Test Deployed
40
50th Percentile = 6 days or less
41
85th Percentile = 15 days or less
42
95th Percentile = 22 days or less
43
Scatterplot Percentiles (making a forecast)
44
85th Percentile = 33 days or less
85th Percentile = 13 days or less
What factors
affect
Cycle Time?
WIP
Avg WIP
Avg Cycle Time =
Avg Throughput
What else?
Poor Pull Policies,
Blockers,
External Dependencies,
…
“Actionable Agile
Metrics for
Predictability”
https://leanpub.com/actionableagilemetrics
For next time…
What does a 19th century
Yorkshire cotton
industrialist have to do
with the Manhattan
Project?
QUESTIONS?
Daniel S. Vacanti
http://www.actionableagile.com
daniel@actionableagile.com
@danvacanti
Thank-you!