Objective:
How To Measure Simply the
Progress Payment of
U98 Master Control Tower Building and
Administration Building
(Concreting - Forms / Rebar’s / Pouring)
Area to Consider:
Focus only on Foundation Level until GF Slabs (see page 3)
Foundation Layout
Security Building Section
Foundation Level
MCTB Section
Foundation Level
INITIAL STEPS ARE NEEDED TO BE DONE FIRST 1 1
Note: PCM Planning Team has
1. Calculate Concrete Volume. 2 the Volume computation if
2. Compare and Determine the Difference. PMC request for verification.
3. Decide which Volume to use. PCM Construction
Planning Team Team
Difference bet
Concrete Concrete
Floor Location Item Unit Planning and Remarks
Volume Volume Const. Team
RC Foundation & MF1 m3 1,832.83 1,766.39 66.44
1st RC Slab MF2 m3 719.85 719.85 (0.00)
(until Elev. 105.95) Tie Girder m3 39.39 48.87 (9.48)
Harbour Master's Control
Column (EL 105.95) m3 11.76 14.00 (2.24)
Tower Building
RC Wall (EL 105.95) m3 55.15 60.07 (4.92)
Grade Slab m3 134.62 149.22 (14.60)
Suspended Slab m3 17.08 20.04 (2.96)
Holding Tank Box m3 22.53 21.76 0.77
Sub-total m3 2,833.20 2,800.20 33.00 Normal
MF3 m3 355.54 353.55 1.99
Isolated Footing and FTB m3 231.95 209.44 22.51
Tie Girder m3 42.28 109.57 (67.29)
Maintenance and
Column (EL 105.95) m3 39.53 39.53 (0.00)
Operations Building
RC Wall (EL 105.95) m3 126.89 121.01 5.88
Grade Slab m3 502.97 219.93 283.04
Because revision is
Suspended Slab m3 98.24 50.37 47.87
not yet Finalized
Holding Tank Box m3 17.02 17.52 (0.50)
Sub-total m3 1,414.42 1,120.92 293.50
Isolated Footing and FTB m3 88.98 96.00 (7.03)
Tie Girder m3 29.39 30.80 (1.41)
Security Building
Column (EL 105.95) m3 7.35 7.35 0.00
Grade Slab m3 96.01 94.65 1.36
Holding Tank Box m3 9.95 10.57 (0.62) 3
Sub-total m3 231.68 239.37 (7.69) Normal
Grand Total m3 4,479.30 4,160.49 318.81 We can use PCM Qty
4 5
4. Simplify the MAIN ITEMS needed for progress
measurement by combining associated items into one.
5. Using the Selected and Combined Volume,
determine the Percentage Weight of the concrete.
Determining Percentage Weight
9. Back Ups for Forms (MS-1) and Pouring (MS-3) are separate. Back Up Material [1/2]
Rebar Installation Progress [MS-2] [Sample Only]
Main Item Percentage Quantity of This
Floor Location Unit Previous %
Considered Weight Main Item Month Cumulative - MF2 Rebar:
RC Foundation & MF1 40.92% 5 parts 0.00%
50% was
1st RC Slab MF2 16.07% 1 part 0.50 0.50 8.04%
considered
(until Elev. 105.95) Column
Installed
Harbour Master's Control 1.14% 37 pcs 10.00 10.00 0.31% (bottom bars /
(w/ TG)
Tower Building
RC Wall 1.23% 14 span 0.00% top bars etc.)
Slab 3.39% 30 bay 0.00%
- Column Rebar:
10 Nos.
Quantity of Installed
Item are
indicated in
Marked
Numbers Measured Items
are Highlighted In
Yellow Color
THIS IS
IMPORTANT!
9
OTHER EXAMPLES OF BACK UP MATERIAL SHEET [2/2]
By Nos
By Span By Bay
Quantity of Quantity of
Item are Item are
indicated in indicated in
Marked Marked
Numbers Numbers