Professional Documents
Culture Documents
2018
Seminar on Internship at Elevated service Reservoir,
& Cement Road Construction.
Presentation By-
Pawan Kalantri(112) Guide-
(VII Semester B.E. Civil Engineering) PROF. MS Laxmi
R. Gangwani
Chapters Description
1.0 Case Study 1
2.0 Case Study 2
3.0 Case Study 3
Builder: CENTRAL INDIA ENGINEERING
Structural designer: AQUADES STRUCTURAL CONSULTANTS
PVT. LTD.
Project Incharge: Mr. Devendra Jaisal
Type of building: Elevated Storage Reservoir
Location: ESR-1 – Chandrabhaga Nagar, Hudkeshwar, Nagpur
ESR-2 – Sambhaji Nagar, Narsada, Nagpur
ESR-3 – Bharatmata Nagar, Narsada, Nagpur
Status: In process
Project Cost: Approx. 9 Crores 38laks(for all 3 ESR’s)
Capacity of each tank was 22.22lakh Litres.
Trapezoidal Separate Footing of 3 metre depth.
Concrete grade – M30
Reinforcing Steel grade – Fe 500
Density of Sand – 777 kilograms per cubic meter.
Density of Aggregates – 700 kilograms per cubic meter.
Type of Cement – OPC43, ULTRATECH CEMENT.
Quantity of Admixture – 4.38 kilograms per cubic metre.
Seismic zone of ESR: Zone 3
DIFFERENT PARTS OF STRUCTURE:
1. FOUNDATION-The SBC (Soil Bearing Capacity) of the soil at the site
was 40 tonnes per meter square and for design consideration it was
taken as 20 tonnes per meter square. There were 38 columns and
each column was provided with individual trapezoidal footing with
maximum depth of 3 metres.
2 SUPERSTRUCTURE-
1. Columns- Out of 38 circular columns of height 21 metres, 1
column of diameter 300mm was provided for supporting the circular
staircase blocks and the rest 37 columns supported the overhead
tank. There were 21 columns of 500mm diameter and 16 columns of
400mm diameter.
1.SALIENT FEATURES OF THE STRUCTURE:
Dry Lean Concrete grade- M10
Pavement Quality Concrete grade- M45,
250mm thick.
Footpath tiles- 200mmx200mmx100mm
Kerb stone base- M10
Operation and maintenance period of 30
years
Separation Membrane of 250 micron
thickness
MILLING OF ROAD :- Milling is done to a thickness of 100mm with a
Milling machine.
LAYING OF DRY LEAN CONCRETE:-DLC is laid to provide firm base
to support traffic over PQC pavement. It is then compacted with roller.
The DLC of M10 grade was provided with a thickness of 100mm
(permissible thickness-75 to 125mm). Camber provided was 2.5% of
road width.
LAYING OF PAVEMENT QUALITY CONCRETE:-
Before laying PQC, a 250micron thick separation
membrane was laid on dry lean concrete(M IO). The
PQC of grade M45 was laid provided with dowel bar
sheets which was laid at each 3m distance. The
dowel bars used consists of 32/25mm diameter and
600mm long which had 300mm c/c spacing.
The purpose of dowel bar is to transfer panel to
panel loads.
Tie bars of 12mm diameter and 600mm long was
provided to tie the bays from both side.
COMPACTION AND FINISHING :-I
The concrete was then compacted with needle vibrator of
60mm diameter.
Slump test was carried out for RMC truck. It was found to be
35mm. The desired slump is between 40-60mm which is
permissible. For slip form paver machine, the slump should be
25 and for fixed form paver the slump required at site was
50mm.
After the concrete is placed, the road surface was again
compacted and smoothened or finished with the help of screed
vibrator.
The road is finished with floater and pole finisher.
After sometime, the texture is then given on smooth surface in order
to reduce friction with the help of saw tooth brush.
SLIP FORM PAVER:-
A slip form paver is a piece of construction
equipment used to lay concrete on roads. It lays the
concrete flat and also provides compaction, the one
used at site had a capacity to make a road of 10m
width at once, but due to space contraints only 5m
width was possible and the rest 2m was madey
manually. Large freeways are often paved with
concrete and is done using slip form paver. RMC
trucks dump loads of readymix concrete in heaps
along in front of this machine and then the slip form
paver spreads the concrete out and levels it off.
It uses low slump so that the PQC should hold shape
once the slip form paver has passed.
The paver usually performs screeding,consolidation
and initial finishing.
Site: RMC Plant
Location: Beside Oriental Plant, Outer Umred Road, Nagpur+