Professional Documents
Culture Documents
Pile cap
Piles
Weak soil
Bearing stratum
Pilling Steps
Survey: The surveyor set out the center of the bored pile location.
Utility diversion: A circular pit of diameter 1700mm and depth 1500 mm shall be manually excavated at the location to ensure
that the utilities are present.
Checks for Pile vertically and position: During the process of boring following checks should be made:
Check the verticality of the casing during installation by plumbing from two perpendicular directions.
Check of the eccentricity of the borehole after installation of casing. If the eccentricity is more than 50mm then reinstallation is
done.
The verticality of the casing is checked continuously until the toe is reached and is kept within a tolerance of 50mm.
Variation in dimension is limited to +50mm and - 10mm.
Boring of soil-Boring is carried out with the help of a rig up to the required depth. The verticality of the hole to be bored is kept
on monitored and later checked before the lowering of the reinforcement cage.
Installation of temporary casing to stabilize the upper bore, a temporary steel casing of length 2.5- 3m is installed:
A 1000mm diameter hole is drilled using hydraulic boring machine up to a depth of 3-4m.
The casing should then be lowered in the hole with the help of a crane.
The casing is then driven in to the ground with the help of a rotatory machine until about 300mm is left above the ground. The
rig is then used to progress the excavation to the bottom of the casing pipe and then suitable polymer system is added before
further excavation.
Bentonite should be added continuously during excavation. And the depth is measured with the help of the sounding tape.
Cleaning of base:
Boring is stopped when the toe of the pile level is reached. The borehole is cleaned carefully and the soil is removed.
The depth is checked before the lowering of the cage.
Cutting and bending of bars shall be carried out with approved schedule in fabrication yard or on the site. Tie wires shall be
used for binding the bars. Circular concrete spacers shall be provided of the same grade of the pile. Vertical distance between
each layer of spacers shall be 4m. The reinforcement cages shall be lowered in the borehole using steel slings and shackles.
Cages shall be spliced on the fabrication bed and lowered in the trench.
Concrete with slump in the range 175+25mm shall be supplied from batching plant. All concrete delivered shall be visually
inspected and checked against delivery note before being tested and used. Before a pouring is started two delivery trucks
should be available at site.
Pipes are joined towards into the hole. The end of the pipe should not be more than 300 mm above the bottom of the pile to
ensure that free fall of concrete shall not be more than 1.5m.
The concrete shall be discharged from the delivery truck to a hopper connected to the pipes. As the level of the concrete in
the borehole rises, the s shall be withdrawn accordingly to aid the flow of concrete. Section of the pipe shall be dismantled
from the top as the pipe is withdrawn.
During concreting, the level of concrete inside the borehole shall be monitored either with a weighted tape or chain. Encasing
shall be withdrawn after initial setting of concrete
Casing in pile
20mm dia bars are used.
pitch of helical striupps are 200mm
4 master ring, 3 pair square ring, 16 longitudional bar
dia of helical bar 10mm
length of cage – 8.8mm
dia of cage – 1050mm
Size of helical bar – 10mm
lap length – 72* dia of bar
Pile load test
Done after 28 days of construction.
Acceptable limit of penetration should not be less than
12mm.
There should be a overbound of 1 or 2 mm.
Loads applied as per loading of girder.
Reinforcement in pile cap
Batching plant
Signature bridge batching plant has a capacity to deliver a 60 cubic
meter per hour. The batching mixer mixes the following cement, sand,
aggregate , admixture, fly ash and water.
Casting Yard
In casting Yard, deck slab and bridge kerb, welding works were made.
Deck Slab
deck slab used in site comprised of M50 grade concrete. 32mm steel
bars of Fe500.
Kerbs
kerb is a stone or concrete forming an edge between a pavement and a roadway, so
that the pavement is somewhat above the level of road.