Professional Documents
Culture Documents
(WBS)
Task4 8
Task5 2
Task6 4
Task7 2
Task8 1
Personnel Symbol
Project Manager PM
Team Member 1 TM1
Team member 2 TM2
Contractor C
Engineer E
PLANNING TABLES
A table is another simple planning tool. The activities
are placed in logical order and time, for example:
2. Review and confirm Architects’ and Consultants 1 months Oct. 2003 Oct. 2003
Users Briefs for the proposed facilities
3. Confirmation of design requirements Consultants and 1/2 months Oct. 2003 Oct. 2003
presented by Consultants TTECO
4. Design of facilities, preparation of Consultants, 3 months Nov. 2003 Jan. 2004
tender documents and costing (submit TTECO review
documents for review) and request
revisions
5. Contract Construction Firms for the Consultants and 3 months Jan. 2004 May 2004
construction TTECO
6. Construction works Contractors 10 months May 2004 Feb. 2005
7. Supervise, monitor, evaluate work Consultants 10 months May 2004 Feb. 2005
carried out and make recommendations provide site
for payment supervision,
monitored by
TTECO
MILESTONES
CRTICAL PATHhas
A milestone NETWORKS
zero durationAND PERT
and no effort DIAGRAMS
-- there is
no work associated with a milestone. It is a flag in the
work plan to signify some other work has been
completed; for example:
Milestone Initial Estimated Completion Date
Draft Terms of Reference April 21, 2010
Review and edit April 30, 2010
Issue RFP to Bidders May5,2010
CRITICAL PATH AND PERT DIAGRAMS
Project Background
Project Strategy
Procurement Plan / Contract for services
Procurement Timeline/Schedule
The Evaluation Methodology
Evaluation Criteria
Evaluation Committee Plan
Award process