Professional Documents
Culture Documents
MANAGEMENT...
SUBMITTED TO : PROF
NARINDER SINGH
SUBMITTED BY : ANKITA
SHARMA(4713)
WHAT IS PROJECT COST
ESTIMATION?
1. Cost estimation in project management is the process of forecasting the
financial and other resources needed to complete a project within a defined
scope.
2. It is the process of predicting the
Quantity
Cost
Quality
of the resources required by the scope of a project.
3. Cost estimating utilizes many techniques that translate the project scope
into deliverables and develop an approximation of costs of the resources
needed to complete project activities.
IMPORTANCE OF COST ESTIMATION
STUDY ESTIMATE
PRELIMINARY ESTIMATE
DEFINITIVE ESTIMATE
DETAILED ESTIMATE
ORDER OF MAGNITUDE ESTIMATES
PRELIMINARY ESTIMATES
Created when a project’s deliverables are about halfway defined, a preliminary
estimate uses somewhat detailed scope information to incorporate unit costs.
Preliminary estimates are accurate enough to be used as a basis for project
financing. Some project budgets are authorized based on the preliminary
estimate.
• It is at this stage that the budget
allocation is frozen and a basis of
control is established.
• The accuracy even at this stage is
about +-20%. This means that
even if a project is managed well
cost can be over run by 20%.
• The fig. given depicts the
successive estimates and the
associated errors.
The preliminary estimate is based on the final technology
package. The following information is important at this stage:
Final process and instrumentation diagram
Overall plot plan
Preliminary equipment
Final equipment process specifications
Preliminary single line diagram
Preliminary motor list
Preliminary piping MTO
Final instrument list and spec
DEFINITIVE COST ESTIMATE:
This estimate is prepared after the zero date when the detailed engineering of a
project is in an advanced stage.
The following additional information adds to the accuracy of the estimate:
Equipment purchase specification
Schedule of items for work tenders
Reasonably accurate material take offs based on general arrangement
drawings
House general arrangement drawings
DETAILED ESTIMATE: