Professional Documents
Culture Documents
– DEI-
Time has the least
amount of flexibility;
Schedule issues are the
main reason for
conflicts on projects,
especially during the
second half of projects
The processes required to
manage timely completion
of the project
Define Activities
Sequence Activities
Develop Schedule
Control Schedule
Monitoring &
Controlling Processes
Planning
Processes
Executing
Processes
Knowledge
Process
Area Monitoring &
Initiating Planning Executing Closing
Control
Plan Schedule
Activity Definition
Activity Sequencing
Scope Control time
Activity Duration
Estimating
Schedule Development
Plan Schedule
DEFINE ACTIVITIES
Outputs
Tools &
Inputs 1. Activity List
Techniques
1. Project 2. Activity
1. Expert Judgment Attributes
Management
2. Decompositions 3. Milestone List
Plan
3. Rolling Wave 4. Change
2. EEF Planning Requests
3. OPA 4. Meetings 5. Project
Management
Plan Updates
Rolling Wave
Planning: plan to a
higher level and then
develop more detailed
plan when the work is
to be done
Progressive
elaboration:
process clarifying and
refining plans as the
project progress
cake
put into
measure
mold
bake
put cake
Activity Atributes:
•Used to identify e.g. the unique activity
indetifier (ID), WBS ID, and activity label or name
Milestone List
• a significant point or event in the
project.
• required by contract
• historical information
• zero duration
SEQUENCE ACTIVITIES
A=15 B=5
Start to Finish
A B C
predecessor Successor
A
Leads
B
Applying Lags
B
To define sequence
among activity, we
need to understand
dependency
determination e.g
mandatory,
discretionary,
external, and
internal
Mandatory Discretionary
(hard logic) (knowledge base)
External Internal
(third party) organization
Dependency Determination
Example: The activity List and the sequence
ID activity predecessor
A Purchase the material -
B Measure the ingredients A
C Mixing B
D Pre heat the oven C
E Put the batter into mold C
F Bake the cake C,D
G Put the cake in the plate F
Cut the unnecessary side
H of the cake G
I Mix the cream B
J Garnish the cake G
K Put the cake into fridge J
L Package the cake K
M Delivery the cake L
D
start A B C J
F G
E H K
L
I
M
END
put into
measure garnish deliver
mold
put cake
Activity Resource Requirement
Resource duration
ID Activity predecessor
(man) (minute)
A Purchase the material - 2 30
Measure the
B A 2 15
ingredients
C Mixing B 1 15
D Pre heat the oven C 1 10
Put the batter into
E C 1 5
mold
F Bake the cake C,D 1 120
Resource Breakdown Structure
cake
Baking
powder
fruits
Effort is the number of Duration includes the
workdays or work hours actual amount of time
worked on an activity plus
required to complete a
elapsed time
task
EFFORT VS DURATION
Analogous Estimate
Use actual
duration of
previous activity
(historical) that
has similarity
RP.
100.000
RP.
200.000
Use statistical relationship or math analysis
between historical data and other
variables
Reserves Analysis
Reserves Analysis
BAD DESIGN
Reserves Analysis
49
PERT
•Beta Distribution (weighted average)
•uses probabilistic TIME & COST estimates
•tE = (tO + 4tM + tP) / 6
Expected Standard Variance
Deviation
P 4Μ Ο PΟ P Ο
2 SD variance
6 6 6
exercise
Beta
Expected activity
Activity range of the
activity P M O (Beta
standard estimation
distribution)
deviation
A 47 27 14
B 89 60 41
C 48 44 39
D 42 37 29
Answer
Beta
Expected
Activity range of the
Activity P M O activity (Beta min max
standard estimation
distribution)
deviation
22.67 to
A 47 27 14 28.167 5.5 22.667 33.667 33.667
28.167 +/-5.5
53.667 to
B 89 60 41 61.667 8 53.667 69.667 69.667
61.667+/-8
42.333 to
42.333 45.333 45.333
C 48 44 39 43.833 1.5
43.833 +/-
1.5
34.333 to
34.333 38.667 38.667
D 42 37 29 36.500 2.167
36.6 +/-
2.167
Develop Schedule
55
Resource Calendar
Information (skill, location, etc) in which
resource are potentially available.
Resource duration
ID Activity predecessor
(man) (minute)
A Purchase the material - 2 30
Measure the
B A 2 15
ingredients
C Mixing B 1 15
D Pre heat the oven C 1 10
Put the batter into
E C 1 5
mold
F Bake the cake C,D 1 120
Resource Calendar
Plot into Gant Chart format
D D,
E 1 Milestone : check
F F,1
B B,2
C C,1
D D,
E 1
F F,1
MAN
6 A,2 We need only 2 people work
5 this project
4
3 2 2 2
2 1 1
1
10 20 30 40 50 60 70 80 90 100 110 120
DURATION
Adding Milestones to Gantt Charts
Activity on
Arrow
(AOA)
Network
diagram
Activity on
Node
(PDM)
AON OR PDM RULES
Activity on
Arrow
(AON)
ES DUR EF
ACTIVITY NAME
LS TF LF
FLOAT (SCHEDULE FLEXIBILITY)
• Float/slack
• Total float amount of time an activity can be delayed
without delaying the project end date
• Float is an asset
AON OR PDM RULES
ES DUR EF EF = ES + D -1
LS = LF – D +1
ACTIVITY NAME Float (F) = LS – ES = LF – EF
LS TF LF
considers limited
resources when creating a
project schedule and
includes buffers to protect
the project completion date
67
Buffers and Critical Chain
69
Schedule Compression: Fast Tracking
activities cost
J and K 14000
J and N 5000
K and L 16000
L and N 7000
M 9000
Schedule shortening
• Fastrack always add risk and cost, may add
management time for PM
• Crash always add cost and risk, may add
management time for PM
• Reduce scope save cost, resource, time, may
negatively impact customer satisfaction, may
increase risk
• Cut quality requires good metrics on current
and desired levels of quality in order to be
effective, may negatively impact customer
satisfaction
Output Develop Schedule
• Show interdependencies between variables
network diagram
• To report senior management milestone
chart
• To track progress and to report to the team
bar chart
Control Schedule