Professional Documents
Culture Documents
Ch08 Project Scheduling
Ch08 Project Scheduling
INTRODUCTION
Schedule converts action plan into operating
time table
Basis for monitoring and controlling project
Scheduling more important in projects than
in production, because unique nature
Sometimes customer specified/approved
requirement-e.g: JKR projects
Based on Work Breakdown Structure (WBS)
PERT CPM
-Program Evaluation and Critical Path Method
Review Technique Developed by El Dupont
- developed by the US for Chemical Plant
Navy with Booz Shutdown Project- about
Hamilton Lockheed same time as PERT
- on the Polaris
Missile/Submarine
program 1958
PRECEEDING SUCCESSOR
ACTIVITY
EVENT
WRONG !!!
CORRECT
Chapter 8 Scheduling, PERT, Critical Path Analysis 8
Example 1- A simple network
Consider the list of four activities for making a simple product:
A D
1 3 4
B C
A D
1 3 4
E
B
C 5
2
We need to introduce
a dummy activity
1 2 1 Dummy
b 3
b
WRONG!!! RIGHT
a d a d
1 1
b e b
2 2 4
e
c f c f
3 3
a precedes d.
a and b precede e,
b and c precede f (a does not precede f)
Activity
1
t = expected activity
time
7
4
1 6
Activity
2
LF = latest finish time
LS = latest start time
7
4
1 6
LF-EF = 12 –9 =3
LS-ES = 8 – 5 = 3
LF-ES-t = 12-5-4 = 3
A 0 0 5 5 0 Yes
B 0 6 6 12 6
C 5 8 9 12 3
D 5 7 8 10 2
E 5 5 6 6 0 Yes
F 6 6 10 10 0 Yes
G 10 10 24 24 0 Yes
H 9 12 21 24 3
I 24 24 26 26 0 Yes
Chapter 8 Scheduling, PERT, Critical Path Analysis 25
IMPORTANT QUESTIONS
What is the total time to complete the project?
26 weeks if the individual activities are completed on schedule.
What are the scheduled start and completion times for each activity?
ES, EF, LS, LF are given for each activity.
How long can non-critical activities be delayed before they cause a delay
in the project’s completion time
Slack time available for all activities are given.
a - 10 22 22 20 4 2
b - 20 20 20 20 0 0
c - 4 10 16 10 4 2
d a 2 14 32 15 25 5
e b,c 8 8 20 10 4 2
f b,c 8 14 20 14 4 2
g b,c 4 4 4 4 0 0
h c 2 12 16 11 5.4 2.32
I g,h 6 16 38 18 28.4 5.33
j d,e 2 8 14 8 4 2
d 6
2
(15,25)
j
a (8,4)
(20,4) e
(10,4)
1 f 7
3
b (14,4)
(20,0)
g
c
(4,0)
(10,4) i
(18,28.4)
h 5
4
(11,5.4)
EF=20 35
d 6
2
a (15,25) j
(20,4) (8,4)
b e
20 43
(20,0) (10,4)
f CRIT. TIME = 43
1 3 7
(14,4)
g
c (4,0)
(10,4) i
(18,28.4)
h 5
4
(11,5.4)
10 24
b 1 0 1
c 4 0 4
d 20 20 0 Yes
e 25 20 5
f 29 20 9
g 21 20 1
h 14 10 4
i 25 24 1
j 35 35 0 Yes
Z = (D-S) / V
Example,
D = 50; S(Scheduled date) = 20+15+8 =43; V = (4+25+4) =33
Z = (50 – 43) / 5.745
= 1.22 standard deviations.
1.22
D = S + 5.745 (1.645)
= 43 + 9.45
= 52.45 days
3 Used where times can be estimated Used where times cannot be estimated
with confidence, familiar activities with confidence.
Unfamiliar or new activities
a d
1 2 6 7 Legend
e
Scheduled Start
3 Scheduled Finish
Actual Progress
f Unavailable
3
Current Date
b Milestone
1 3 5 Scheduled
Milestone
Achieved
c dummy
1 4
h
4
0 5 10 15 20 25 30 35 40 45
Days
D 22222222
E 222222
Activity
F 22
G 2222
H 4 4 44 444 44444
0 5 10 15 20
Time
Add up across all activities to get the total number of men
required.
Chapter 8 Scheduling, PERT, Critical Path Analysis 46
Convert the bar chart to a histogram
D 22222222
E 222222
Activity
F 22
G 2222
H 4 4 44 444 44444
0 5 10 15 20
Time
Revised Schedule:
D 22222222
E 222222
Activity
F 22
G 2222
H 4 4 44 444 44444
0 5 10 15 20
Time
Smaller variations:
1. Easier control of the job
2. Better utilization of resources
Big variations:
1. Frequent moving of manpower
2. Require close control
3. Affect efficiency
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Time