Standard SOP
www.huawei.com
Installation Tools
(5 mm [0.20 in.])
(M3 to M6)
(M3 to M6)
Diagonal pliers Cable cutter Wire stripper RJ45 crimping tool Network cable tester Torque screwdriver
(M12)
(M6)
Soldering iron Ladder Hex key Optical power meter Brush File
(Ф16)
2. Check whether there is a barcode label starting with 212102 on the inner left
wall of the cabinet, as shown by illustration 1 in figure 1.
-If there is such a barcode label on the inner left wall of the cabinet, proceed with
the next step.
-If there is no such a barcode label on the inner left wall of the cabinet, record
the number on the barcode label (shown by illustration 2 in figure 1) that is stuck
on the front door, and stick a barcode label carrying the same number to the
position shown by illustration 1 in figure 1.
(1) Position of the barcode 4
label on an inner wall of the 3. Power off the fan in the front door. Remove the tool-less female connector
cabinet (pressfit type) at one end of the power cable for the fan assembly from the
(2) Position of the barcode
label on the front door of the LOAD0 DC power output port on the EPS.
cabinet
5. Install a new front door, and tighten the six M4 screws for hinges to 1.2 N·m
(10.62 lbf·in.), as shown in figure 5.
6. Connect the other end of the equipotential cable to the ground screw on the
inner wall of the cabinet.
2. Optional: Remove the fan assembly power cable to power off the fan
assembly. Skip this step if this cable has been disconnected during the
replacement of the front door.
4. Place the removed fan assembly into the ESD box or bag.
5. Install a new fan assembly. Slide the new fan assembly into the
installation position and tighten the four M6x12 screws on the mounting
ears on both sides of the fan assembly, and tighten the screws to 2
N•m (17.70 lbf•in.), as shown in figure 2.
2. Lay out the input power cables for the APM30H, as shown in
the figure "Routing of the AC input power cables."
Route the power cables for the APM30H into the cabinet along
the left side of the cabinet, and use cable ties to bind the cables
properly.
BVDC (EPU02D)
5. After powering on the cabinet, ask the element management system (EMS)
administrator to query the electronic label information of the cabinet. Then, check
whether the information is consistent with the nameplate in the upgrade package.
If the information is consistent, the ELU has been successfully installed. If the
information is inconsistent, the ELU has not been installed successfully. In this
case, locate the cause and reinstall the ELU.
4. Pastikan selalu pakai ESD wrap dan sepatu ketika install equipment baru
11. Telpon integrator untuk check alarm after dan service after
Determine whether the RFUs need to be replaced based on the actual requirements.
To be replaced If DRFUs are configured, upgrade them to GRFUs or MRFUs, and remove the
GATMs and Bias-Tee before upgrading the DRFUs.
To be replaced Replace the FAN unit with the FAN 03C unit.
Before replacing the ELU, remove the filler plane. Reinstalled the filler plane after the
To be replaced
replacement.
If DRFUs are configured in the cabinet, remove the two GATMs and the Bias-Tee
To be removed
before upgrading the DRFUs.
1. Turn off the FAN switch on the DCDU-01 and remove the power cable for the
fan assembly.
2. Record the monitoring signal cable connection on the panel of the fan
assembly, and then remove the cable.
3. Cut off the cable ties on the cable trough.
4. Loosen the captive screws in the front of the adjustable cable trough, and lift the
adjustable cable trough.
5. Remove the four M6 screws on the fan assembly, use the handle to pull the fan
assembly outwards till one-third of its length. Support the bottom of the fan
assembly with the other hand and pull it until it is completely removed from the
cabinet. Then, place the fan assembly into an ESD box.
6. Install a new fan assembly, and tighten the four M6x12 screws to 3 N·m (26.55
lbf·in.).
7. Install the adjustable cable trough to the original position, and secure the
captive screws in the front of it.
8. Reconnect the monitoring signal cable to the port on the panel of the new fan
assembly based on the label.
2. Lay out the input power cables for the APM30H, as shown in
the figure "Routing of the AC input power cables."
Route the power cables for the APM30H into the cabinet along
the left side of the cabinet, and use cable ties to bind the cables
properly.
BVDC (EPU02D)
2. If any floating nut in the 2 U space at the bottom of the cabinet is missed, install
a new one and then use a flat-head screwdriver to tighten the six M6×16 screws.
2. If any floating nut in the 2 U space at the bottom of the cabinet is missed, install
a new one and then use a flat-head screwdriver to tighten the six M6×16 screws.
Option Description
Connect the RJ45 connector at one end of the fan assembly monitoring signal cable
Single cabinet to the COM IN port on the fan assembly, and the RJ45 connector at the other end to
the MON0 port on the UPEU in the BBU.
Connect the RJ45 connector at one end of the fan assembly monitoring signal cable
Cabinets installed side to the COM IN port on the fan assembly in the primary cabinet, and the RJ45
by side or stacked connector at the other end to the MON0 port on the UPEU in the BBU in the primary
cabinet.
10. Telpon integrator untuk check alarm after dan service after