You are on page 1of 13

BALAMBAN

CONSTRUCTION &
MARINE SERVICES LTD.CO.
Owak,Asturias,Cebu

BALCON
WEEKLY KICK-OFF MEETING
SEPTEMBER 12,2019
CONSTRUCTION OF
PERIMETER FENCE-
ASTURIAS PLANT
Location: Republic Cement & Building
Materials, Inc.
Tubigagmanok, Asturias, Cebu
Balamban Construction & Marine Services Ltd.Co.
MILESTONE FENCING SITE MAP
LEGEND :
- NOT YET STARTED
- ON-GOING
- COMPLETED
- NOT INCLUDED

- GATE

2 – Milestone 2
3 - Milestone 3
4 – Milestone 4
5 - Milestone 5
6 - Milestone 6
7 - Milestone 7

Balamban Construction & Marine Services Ltd.Co.


SAFETY REPORT
SAFETY STATISTIC PREVIOUS CURRENT UP TO REMARKS
DATE
Staff = 4 Laborer = 23
Total Manpower 1431 27 1458

Total Manhour 303,480 216 334,036


Lost Time Injury (LTI) 0 0 0
None Lost Time Injury 0 0 0

First Aid Injury 0 0 0

Near Miss Incident 0 0 0

Balamban Construction & Marine Services Ltd.Co.


SAFETY REPORT
SAFETY STATISTIC PREVIOUS CURRENT UP TO REMARKS
DATE

Property Damage 0 0 0

HPLE 0 0 0

Safety Violation
(apprehended by 0 0 0
BALCON)
Safety Violation 1. To put wheel stopper on every
(apprehended by 2 0 2 vehicle entering the plant.
RCBMI) 2. To wear proper PPE’s.

Balamban Construction & Marine Services Ltd.Co.


SAFETY REPORT
SAFETY STATISTIC PREVIOUS CURRENT UP TO REMARKS
DATE
Behavioral Safety Audit
(BSA)
0 0 0

**No Sunday operation


Number of Work Days 45 5 50 **No operations o holidays

Balamban Construction & Marine Services Ltd.Co.


PROJECT STATUS
 COMPLETED WORKS:
Target Target
%
Target Completio Planned Start Finish
complet
ACTIVITY Duration n Date Start Date Date Date Remarks
e

1. Milestone 1 100% 6 days Aug.3,2019 July 29, 2019 July 29, Aug. 3, Date Started – July
2019 2019 29,2019
Date Finished –
August 3, 2019

2. Milestone 2 60% 18 days Aug.28, Aug.3, 2019 Aug.4, Aug.28, Delayed due to
2019 2019 2019 immediate
stoppage of work.

3.Milestone 3 60% 18 days Sept.18, Aug.28, Aug. Sept.18, On-going


2019 2019 29,2019 2019

4. Milestone 4 60% 18 days Oct. 9,2019 Sept.18,2019 Sept.19 Oct.9 On-going


,2019 ,2019

Balamban Construction & Marine Services Ltd.Co.


PROJECT STATUS
 COMPLETED WORKS:
Target Target
%
Target Completion Planned Start Finish
complet
ACTIVITY Duration Date Start Date Date Date Remarks
e

5. Milestone 5 30% 20 days Nov.1,2019 Oct.9,2019 Oct.10 Nov.1 On-going.


,2019 ,2019

6. Milestone 6 0% 20 days Nov.21,2019 Nov.2,2019 Nov.3,2019 Nov.21 Not yet started.


,2019

7. Milestone 7 0% 20 days Dec.14,2019 Nov. Nov.22 Dec.14, Not yet started.


21,2019 ,2019 2019

Balamban Construction & Marine Services Ltd.Co.


RCBMI-Asturias Plant Perimeter
Fence

ACTUAL PHOTOS
MOUNTAIN SIDE (MILESTONE 3-NEIGHBORING AREA )

AUGUST 27,2019 AUGUST 28,2019

Balamban Construction & Marine Services Ltd.Co.


RCBMI-Asturias Plant Perimeter
Fence
ACTUAL PHOTOS
SEA SIDE AREA (MILESTONE 4)

AUGUST 19,2019 AUGUST 27,2019

Balamban Construction & Marine Services Ltd.Co.


RCBMI-Asturias Plant Perimeter Fence

ALMOST 50 % ACCOMPLISHED – READY FOR


FINISHING TOUCHES

AUGUST 28,2019

Balamban Construction & Marine Services Ltd.Co.


RCBMI-Asturias Plant Perimeter Fence
REMOVAL OF TREES (MOUNTAIN SIDE AREA-
MILESTONE 3)

BEFORE AFTER
AUGUST 20,2019 AUGUST 28,2019

Balamban Construction & Marine Services Ltd.Co.


- Thank
You -

Balamban Construction & Marine Services Ltd.Co.