Professional Documents
Culture Documents
2019-01-18 - Construction Errors and Intervention in Design
2019-01-18 - Construction Errors and Intervention in Design
Jitendra Bothara
FENGNZ, FNEA, CPEng, IntPE (NZ)
2019 January 21
House Rules
Experiences
• Construction errors
• Errors and implications
• Design intervention
• Modular construction/ Standardisation
General
• Goal
• Minimise errors
• Minimise supervision/ monitoring activity
Architectural
Door
• Door hinges with long arm revolve 180o
Doors
• Note door opening obstructing corridor (exit way)
• Use parliament hinge
Section
• Canopy provided on all sides
Railing and drip
Door/ Window
• Sizes of door/ windows standardised
Door/ window
Roof slope
• All roof slabs to be provided with 1% slope
Structural
Quality of materials
Choosing aggregates
• Concrete: 30 min
• Mortar: 2 hrs
Once water is poured, concrete/
mortar shall be used before initial
setting.
• Provide proper:
• Drainage
• Catch drain
Foundation excavation in sloping ground
7-8m
Foundation excavation in sloping ground
• Provide stepped
foundation system
• Goal
• Avoid creating new
environmental hazard
• Reduce excavation
• Communicate with Standard design
• Note:
• Is foundation base stable?
• Is concrete quality acceptable?
• Only solution
• Be diligent on site
• No manual or training can replace intuition!!!!
Foundation and foundation beams
Foundation for
foundation beam Floor slab thickening
Foundation
230mm thick wall for 230mm thick wall
Pad Foundation
• No more trapezoidal foundation
section
• Use rectangular foundation
section
Column Details
• Same stirrup through out the height of column
• Note: beam-column joint area
• Column bars must be lapped at the mid-height column
Columns
• No solution other than diligence on site!!!!!!!!!
Cover blocks
• Requirements of clear covers to rebars clearly defined
• Use cover blocks for foundation, columns, beams and slabs
Honey combing in concrete
• Honey combing at the bottom/ top of the column
• Concrete drop from 8’ height leading to segregation of concrete at the base,
• Lack of compaction
• Bleeding (loss) of slurry
• Cast column in two stages
with joint at mid height!!!
• Use chute
Cover to rebars in column
Ground floor slab concreting
Beam Column joint
• Beam rebar congestion in end or corner columns – quality of concrete
• Column casing in two states – upper stages usually inferior concrete
• Lack of beam bar anchorage
Column Plan
Column details
Beams
• Brick kicker
• Steel railing
Railing/ Parapet
Railing/ Parapet - Details
Electrical
Power Ducting in beams