You are on page 1of 68

Government of Nepal

National Reconstruction Authority


The Central Level Project Implementation Unit (Education)
Gyaneshwar, Kathmandu.

Disaster Resilience of Schools Project

Seminar on Errors and Remediation during Construction

“Construction errors and intervention in design”

Jitendra Bothara
FENGNZ, FNEA, CPEng, IntPE (NZ)
2019 January 21
House Rules
Experiences

• Construction errors
• Errors and implications
• Design intervention
• Modular construction/ Standardisation
General

• The design intervention is based on


• Extensive visit to school buildings under construction
• Review of existing construction drawings
• Review of design methodology
• Discussions with school building stakeholders.
• Goal
• Understand sources of errors
• Mitigate these at their source
General

• The focus of design intervention is:


• To develop a modular construction system
• Simplification of and improvement in design methodology
• Simplification of construction details
• Consistency/ Uniformity between details of the various buildings
• Economic structures
• Reduced confusion

• Goal
• Minimise errors
• Minimise supervision/ monitoring activity
Architectural
Door
• Door hinges with long arm revolve 180o
Doors
• Note door opening obstructing corridor (exit way)
• Use parliament hinge
Section
• Canopy provided on all sides
Railing and drip
Door/ Window
• Sizes of door/ windows standardised
Door/ window
Roof slope
• All roof slabs to be provided with 1% slope
Structural
Quality of materials
Choosing aggregates

Flaky ,elongated and riverbed aggregates shall not


be used.
Aggregate should be hard, coarse.
What about gradation of aggregates?
Initial setting time

• Concrete: 30 min
• Mortar: 2 hrs
Once water is poured, concrete/
mortar shall be used before initial
setting.

But what is our practice?


Compaction with a temping rod.
Is it good practice?
Notes and specifications
• All standard designs have been provided with:
• Same notes
• Same details
• No more 25mm ф bars
Site selection
Avoid
• Kholsa/ Khola/
• Rickfall/ landslide
Site selection
• Fill soil
Site preparation - Drainage

• Provide proper:
• Drainage
• Catch drain
Foundation excavation in sloping ground

7-8m
Foundation excavation in sloping ground
• Provide stepped
foundation system
• Goal
• Avoid creating new
environmental hazard
• Reduce excavation
• Communicate with Standard design

CLPIU Specific design


RC Wall
Classification of foundation soil
• Foundations provided
for safe bearing
capacity of:
• 100kPa
• 150kPa
• 200kPa
• In case of any doubt or
soft soil:
• Further investigation
required
• Communicate with
CLPIU

(Ref: NBC 202)


Foundation base

• Is the provided foundation base is


better than the original soil?
• If soft rock or better found, no need
to dig full foundation trench
• No stone soling required
• Only PCC required for clean surface
Foundation

• Note:
• Is foundation base stable?
• Is concrete quality acceptable?
• Only solution
• Be diligent on site
• No manual or training can replace intuition!!!!
Foundation and foundation beams

Concrete infill between


foundation and plinth
beams
Foundation and foundation beams
Foundation

Foundation for
foundation beam Floor slab thickening
Foundation
230mm thick wall for 230mm thick wall
Pad Foundation
• No more trapezoidal foundation
section
• Use rectangular foundation
section
Column Details
• Same stirrup through out the height of column
• Note: beam-column joint area
• Column bars must be lapped at the mid-height column
Columns
• No solution other than diligence on site!!!!!!!!!
Cover blocks
• Requirements of clear covers to rebars clearly defined
• Use cover blocks for foundation, columns, beams and slabs
Honey combing in concrete
• Honey combing at the bottom/ top of the column
• Concrete drop from 8’ height leading to segregation of concrete at the base,
• Lack of compaction
• Bleeding (loss) of slurry
• Cast column in two stages
with joint at mid height!!!
• Use chute
Cover to rebars in column
Ground floor slab concreting
Beam Column joint
• Beam rebar congestion in end or corner columns – quality of concrete
• Column casing in two states – upper stages usually inferior concrete
• Lack of beam bar anchorage
Column Plan
Column details
Beams

• All upper storey beams


provided with stubs
• To avoid rebar congestion in
end or corner columns
Beams
Slab

• Note the thickness of slab


• Note the difference in concrete
quality
Suspended Slab

• All upper floors have been


provided with canopy
(chhaji)
• Protect wall from rain
• Beam stubs
• All top main bars 10mm dia
Suspended slab
Slab section
Staircase
Staircase
Staircase
Stair details
• Isolation of landing beam
Bands

• Central part of wall not


restrained against toppling
Restraining walls with door openings
Restraining walls with door openings
Anchorage of band bars
Anchorage of band bars
• No bars/ straps installed outside of colunm
• Either Junge pillar or drill and install epoxy
Bands: Restraining solid walls and with window openings
Terminating column reinforcements

How the parapet wall


be protected?

≥12 largest beam bar


diameter
Terminating column reinforcements

Continue column bars in


stub!!
Railing/ Parapet

• Brick kicker
• Steel railing
Railing/ Parapet
Railing/ Parapet - Details
Electrical
Power Ducting in beams

• No power ducts in beams :


• Within 2xdepth of beam from
column face

• A few of ducts can be provided


in the midspan of beam (away
from columns) in an
unavoidable situation
• Provide separate duct for
power cables
Senitary/ Plumbing
Toilets
• Bathroom floor slope
• >1%
Toilets
• Sink slope
Thank you.

You might also like