Professional Documents
Culture Documents
Christopher Havens
Spring 2012
Presentation Outline
I. Project Background
VI. Recommendations
VII.Acknowledgements
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Project Background
Christopher Havens | Construction Management Christopher Havens | Construction Management
Presentation Outline
I. Project Background Building Information:
VII.Acknowledgements
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Presentation Outline
I. Project Background Reason for Analysis:
II. Analysis 1: Replacing the PEMB PEMB for Industrial/Commercial Project… But Why?
I. Structural Breadth Cost?
Schedule?
III. Analysis 2: Design-Build Phase 2 & 3
Ease of Construction?
Standard Steel
IV. Analysis 3: Horizontal Expansion vs.
Vertical Expansion How Do Other Structural Systems Compare?
Standard Steel
V. Analysis 4: Geothermal System Cast-In-Place Concrete Cast-In-Place Concrete
I. Mechanical Breadth Tilt-Up Concrete
Pre-Engineered Metal Building
VI. Recommendations
VII.Acknowledgements
Tilt-Up Concrete
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Presentation Outline
I. Project Background Criteria for Study:
VI. Recommendations
Presentation Outline
I. Project Background Criteria for Study: Results:
II. Analysis 1: Replacing the PEMB Schedule & Cost No Major Advantages/Disadvantages
I. Structural Breadth Constructability Schedule & Cost
Regional Constraints Constructability
III. Analysis 2: Design-Build Phase 2 & 3
Delivery Issues Impacts on Other Building Systems
IV. Analysis 3: Horizontal Expansion vs. Weather Constraints
Vertical Expansion Typical Construction Projects
Impact on Other Building Systems
V. Analysis 4: Geothermal System Environmental Impact
I. Mechanical Breadth
VI. Recommendations
Presentation Outline
I. Project Background Results:
Regional Constraints
II. Analysis 1: Replacing the PEMB Higher $ to Heat Concrete
I. Structural Breadth Cast-In-Place
Tilt-Up
III. Analysis 2: Design-Build Phase 2 & 3
Presentation Outline
I. Project Background Results:
Regional Constraints
II. Analysis 1: Replacing the PEMB Higher $ to Heat Concrete
I. Structural Breadth Cast-In-Place
Tilt-Up
III. Analysis 2: Design-Build Phase 2 & 3
Presentation Outline
I. Project Background Results: Results:
Regional Constraints Standard Cast-In-Place Tilt-Up Precast
II. Analysis 1: Replacing the PEMB Higher $ to Heat Concrete Steel Concrete Concrete
I. Structural Breadth Cast-In-Place
Schedule & Cost X X X
Tilt-Up
III. Analysis 2: Design-Build Phase 2 & 3 Constructability X X X
IV. Analysis 3: Horizontal Expansion vs. Common Structures in Area Regional Constraints X
Vertical Expansion Steel Impact on Other X X X
Building Systems
V. Analysis 4: Geothermal System Environmental Impact
I. Mechanical Breadth Fewer Harmful Emissions Environmental X
Steel Impact
VI. Recommendations
Lesser Depletion of Natural Resources
VII.Acknowledgements Pre-Engineered Metal Building
Steel
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Presentation Outline
I. Project Background Results: Results:
Regional Constraints Standard Cast-In-Place Tilt-Up Precast
II. Analysis 1: Replacing the PEMB Higher $ to Heat Concrete Steel Concrete Concrete
I. Structural Breadth Cast-In-Place
Schedule & Cost X X X
Tilt-Up
III. Analysis 2: Design-Build Phase 2 & 3 Constructability X X X
IV. Analysis 3: Horizontal Expansion vs. Common Structures in Area Regional Constraints X
Vertical Expansion Steel Impact on Other X X X
Building Systems
V. Analysis 4: Geothermal System Environmental Impact
I. Mechanical Breadth Fewer Harmful Emissions Environmental X
Steel Impact
VI. Recommendations
Lesser Depletion of Natural Resources Best Alternate Structure: Standard Steel
VII.Acknowledgements Pre-Engineered Metal Building
Steel
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Structural Breadth
Christopher Havens | Construction Management Christopher Havens | Construction Management
Presentation Outline
I. Project Background Office Frame: Shop Frame:
Structural Breadth
Christopher Havens | Construction Management Christopher Havens | Construction Management
Presentation Outline
I. Project Background Load Combination:
1.2D + 1.6S
II. Analysis 1: Replacing the PEMB
I. Structural Breadth
VII.Acknowledgements
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Structural Breadth
Christopher Havens | Construction Management Christopher Havens | Construction Management
Presentation Outline
I. Project Background Load Combination:
1.2D + 1.6S
II. Analysis 1: Replacing the PEMB
I. Structural Breadth Building Loads:
III. Analysis 2: Design-Build Phase 2 & 3 Multiply by Trib. Area to Find Distributed Load
VII.Acknowledgements
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Structural Breadth
Christopher Havens | Construction Management Christopher Havens | Construction Management
Presentation Outline
I. Project Background Load Combination:
1.2D + 1.6S
II. Analysis 1: Replacing the PEMB
I. Structural Breadth Building Loads:
III. Analysis 2: Design-Build Phase 2 & 3 Multiply by Trib. Area to Find Distributed Load
VII.Acknowledgements
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Structural Breadth
Christopher Havens | Construction Management Christopher Havens | Construction Management
Presentation Outline
I. Project Background Load Combination:
1.2D + 1.6S
II. Analysis 1: Replacing the PEMB
I. Structural Breadth Building Loads:
III. Analysis 2: Design-Build Phase 2 & 3 Multiply by Trib. Area to Find Distributed Load
VII.Acknowledgements
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Structural Breadth
Christopher Havens | Construction Management Christopher Havens | Construction Management
Presentation Outline
I. Project Background Load Combination:
1.2D + 1.6S
II. Analysis 1: Replacing the PEMB
I. Structural Breadth Building Loads:
III. Analysis 2: Design-Build Phase 2 & 3 Multiply by Trib. Area to Find Distributed Load
Structural Breadth
Christopher Havens | Construction Management Christopher Havens | Construction Management
Presentation Outline
I. Project Background Load Combination: Estimate Cost & Schedule:
1.2D + 1.6S Use RS Means Building Construction Cost Data 2012
II. Analysis 1: Replacing the PEMB
I. Structural Breadth Building Loads:
Included in Structural Steel Estimate:
III. Analysis 2: Design-Build Phase 2 & 3 Multiply by Trib. Area to Find Distributed Load Steel Members
Bolts
IV. Analysis 3: Horizontal Expansion vs. Reactions:
Base Plates
Vertical Expansion Use Free Body Diagrams to Sum Forces & Moments Purlins
Metal Siding/Roofing
V. Analysis 4: Geothermal System Max. Shear & Moment:
I. Mechanical Breadth
Use FBD’s to Sum Forces & Moments on Each Member NOT Included in Estimate:
VI. Recommendations Pre-Engineered Metal Building Design Fees
Size Members: Fabrication Fees
VII.Acknowledgements Documentation Fees
Use Steel Manual Values to Determine Size of Each Member
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Presentation Outline
I. Project Background Results:
Presentation Outline
I. Project Background Results: Conclusion:
Steel (Without Fees) is $21,000 > PEMB
II. Analysis 1: Replacing the PEMB
I. Structural Breadth PEMB Structural Steel Steel is 8 Days < PEMB
III. Analysis 2: Design-Build Phase 2 & 3 Schedule June 14– Nov. 16 June 14– Nov. 4
Cost $661,500 $682,500
IV. Analysis 3: Horizontal Expansion vs.
Vertical Expansion
Note: Structural Steel Estimate Does Not Include: PEMB Should NOT Be Replaced By Standard Steel Structure
V. Analysis 4: Geothermal System Design Fees Schedule Acceleration is Not Expected to Cover Additional Cost
I. Mechanical Breadth Fabrication Fees
Documentation Fees
VI. Recommendations
Presentation Outline
I. Project Background Reason for Analysis:
II. Analysis 1: Replacing the PEMB Phase 2 & 3 are Nearly Identical to Phase 1
I. Structural Breadth
Could Later Phases Be Design-Build?
III.Analysis 2: Design-Build Phase 2
&3
If So, What are the Benefits?
IV. Analysis 3: Horizontal Expansion vs.
Vertical Expansion
VI. Recommendations
VII.Acknowledgements
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Presentation Outline
I. Project Background
Design-Bid-Build:
Presentation Outline
I. Project Background
Design-Bid-Build:
Presentation Outline
I. Project Background
Design-Bid-Build: Conclusion:
V. Analysis 4: Geothermal System Build Phase 2 & 3 SHOULD Be Delivered as Design-Build Projects
I. Mechanical Breadth
Bid Design 8 Mon.
VI. Recommendations 1 Mon. 4 Mon.
VII.Acknowledgements
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Presentation Outline
I. Project Background Reason for Analysis: Criteria for Study:
II. Analysis 1: Replacing the PEMB Schematic Phase of Design Based on Owner Interview:
I. Structural Breadth
Owner Wants to Double the Size of the Office Building 1.Schedule Impacts
III. Analysis 2: Design-Build Phase 2 & 3
2.Project Cost Impacts
IV. Analysis 3: Horizontal Two Options for Expansion 3.Limiting Change Orders
Expansion vs. Vertical Horizontal 4.Functionality
Expansion Vertical 5.Aesthetics
VII.Acknowledgements
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Schedule:
Horizontal
June 14– Dec. 7
Vertical
June 14– Nov. 23
Project Cost:
Horizontal
Horizontal Expansion $176,000 Vertical Expansion
Vertical
$231,000 Original Building
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Schedule:
Horizontal
June 14– Dec. 7
Vertical
June 14– Nov. 23
Project Cost:
Horizontal
Horizontal Expansion $176,000 Vertical Expansion
Vertical
$231,000 Original Building
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Functionality:
Elongated Floorplan
Horizontal
Stacked Floorplan
Horizontal Expansion Vertical Vertical Expansion
Original Building
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Functionality:
Elongated Floorplan
Horizontal
Stacked Floorplan
Horizontal Expansion Vertical Vertical Expansion
Original Building
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Presentation Outline
I. Project Background Conclusion:
Geothermal System
Christopher Havens | Construction Management Christopher Havens | Construction Management
Presentation Outline
I. Project Background Reason for Analysis:
VI. Recommendations
VII.Acknowledgements
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Geothermal System
Christopher Havens | Construction Management Christopher Havens | Construction Management
Presentation Outline
I. Project Background Reason for Analysis: System Components (From Mech. Breadth):
II. Analysis 1: Replacing the PEMB Geothermal System in Shop Building Horizontal Closed Loop System
I. Structural Breadth Replace Gas-Fired Heaters ~4,000 FT Buried 5 FT Below Grade
III. Analysis 2: Design-Build Phase 2 & 3
Environmentally Friendly 20 TON ( 200 MBH) Heat Exchanger
IV. Analysis 3: Horizontal Expansion vs.
Vertical Expansion Terminal Units
‘Chilled Beams’
V. Analysis 4: Geothermal System
I. Mechanical Breadth
VI. Recommendations
VII.Acknowledgements
Loop System Heat Exchanger Chilled Beams
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Geothermal System
Christopher Havens | Construction Management Christopher Havens | Construction Management
Presentation Outline
I. Project Background Cost & Schedule: Additional Factors:
VI. Recommendations
VII.Acknowledgements
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Geothermal System
Christopher Havens | Construction Management Christopher Havens | Construction Management
Presentation Outline
I. Project Background Cost & Schedule: Additional Factors:
VI. Recommendations
VII.Acknowledgements
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Geothermal System
Christopher Havens | Construction Management Christopher Havens | Construction Management
Presentation Outline
I. Project Background Conclusion:
IV. Analysis 3: Horizontal Expansion vs. Payback Period Does Not Justify Cost
Vertical Expansion
Owner Will Not Want to Reduce Demand of Natural Gas
V. Analysis 4: Geothermal System
I. Mechanical Breadth
VI. Recommendations
Geothermal System Should NOT Be Chosen
VII.Acknowledgements
The Northeastern Pennsylvania Office Building The Northeastern Pennsylvania Office Building
Recommendations
Christopher Havens | Construction Management Christopher Havens | Construction Management
Presentation Outline
I. Project Background Replacing the PEMB:
Acknowledgements
Christopher Havens | Construction Management Christopher Havens | Construction Management
Presentation Outline
Thank You:
I. Project Background