Planning For Radio Coverage & Capacity 2.0
Planning For Radio Coverage & Capacity 2.0
• Coverage planning
Three terms
Tool and case
• Capacity planning
Three terms
Method and case
• Relationship
Balance of Uplink and Downlink
EIRP
BTS Set-top power
UL DL
margin
If traffic in 15 min is 0.2 Erl, then traffic in one hour is 0.2×4 = 0.8Erl
If traffic in 15 min is 0.2 Erl, then traffic in one hour is also about 0.2 Erl when
distribution of traffic is even
AN N!
Grade of Service N
K!
AK
K 0
A = Expected traffic intensity in Erlangs N = Number of circuits in group
TRX
Number
Elang GOS
TRX Channel
Erlang-B
Configuration Configuration
Useful information
• Subscriber quantity: 100,000
• Call loss rate: 2%
• Traffic model: 0.015Erl
• Number of BTSs: 120
TRX/Channel/
Coverage Coverage area Traffic Load
…
Dimensioning per Site pre Site
Configuration
Traffic model
Coverage
Subscribers Limitation limitation
END
Distribution Judgment
Capacity
Frequency Figure out the max.
limitation
Planning configuration
Traffic Load
Channel
per Site
Configuration
Coverage area
per Site
BTS Quantity
Coverage of uplink
No signal to
MS
1 SDCCH/4 SDCCH/8
3 SDCCH/8 + SDCCH/4