MOP Dismantle V-Pole


Mounting XL Project
Prepared by :
Adi Satya Mulia Saragih / AWX332170
Eko Imam Minardi / e00253439 www.huawei.com
www.huawei.com

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

Page 1
Security Level:

1. EHS & TOOLS PREPARATION


www.huawei.com

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential


1.1 Personal Protection Equipment / Alat Perrlindungan Diri Preparation
PPE/ APD :
• Ground & Climb Helmet
• Safety Shoes
• Full Body Harness (Working at Height)
• Working Lanyard
• Double Lanyard with Absorber
• Safety Gloves

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential


1.2 Safety Kit Prepaaration

First aid kit

Safety sign & Barricade line


emergency phone
number

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential


1.3 Tool’s List

No Tools Quantity
1 Toolbox complete 1 set
2 Pulley/ Katrol 1 pcs
3 Rope/ Tali 2 pcs
4 Shackles 1 pcs
5 Transceivers 1 set
6 WD-40/ Pembersih karat 1 pcs

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential


Wrenches Pulley/ Katrol Rope/ Tali

First aid kit

Transceiver/ HT Shackles Pembersih karat/ WD-40

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential


1.4 Competency Certification Check

Electricity

Huawei Pass ID

Every Worker Work at the tower


should have certification WAH,

Basic First Aid

WAH

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential


Security Level:

2. Methode of Procedure
V-Pole Mounting Dismantle
www.huawei.com

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential


2.1 Preparation Team & Tool’s Dismantle Actvity
Here are a few steps before working on the dismantle process
Check Point / a few step’s before start Dismantle Process

1. Use PPE according to the composition of each work


2. Conduct toolbox meetings with team
3. Prepare all the equipment for dismantle such as rope, pulley, HT, etc. in accordance with MOP
dismantle
4. Install pulleys / pulleys to the strongest structures in the tower

 Team List for dismantle Activity :


A. Work on tower : 4 orang (WAH Certified Licence)
B. Traction sling : 2 person
C. Lifting sling : 2 person

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 9


2.2 Overview V-Pole Mounting

1. Vertical Mounting
2. Horizontal Mounting
3. Arm Bracket

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 10


Overview V-Pole Mounting

Horizontal mounting : 5 Meter Vertical mounting : 3 Meter


3

1. Vertical Mounting : 6 pcs (8 pcs U-Bolt for each vertical mounting)


2. Horizontal Mounting : 6 pcs (2 pcs U-Bolt for each Horizontal mounting)
3. Arm Bracket : 12 pcs

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 11


2.3 Dismantle Process
V-Pole Mounting dismantle Process

 Dismantle Vertical Mounting Process :


1. Install pulleys / pulleys to the strongest
structures in the tower.
2. Determine the mounting to be dismantled first,
find the Horizontal Mounting position at the
bottom & Loosen U-Bolt from Arm Bracket to
Horizontal Mounting (4 U-Bolt).
3. Slide Horizontal Mounting together (4 people
in the U-Bolt position that has been loosened)
so that the vertical mounting
position.approaches the Leg Tower.
4. Ikat vertical mounting (simpul Icicle Clove
Hitch) dengan tali yang sudah terhubung ke
katrol dan tali kendali.
5. Release one by one U-Bolt on vertical
mountings.
6. After all U-Bolt on the vertical mounting
release, move the vertical mounting load on
the pulley slowly.
7. Lower the vertical mounting slowly, control the
vertical mounting so that it does not collide
with the existing device or to the tower by 1. Vertical Mounting
using a control rope (lifting sling). 2. Horizontal Mounting
8. Repeat Step 2 to Dismantle next Vertical 3. Arm Bracket
mounting side

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 12


Dismantle Process
 Dismantle Horizontal Mounting Process :

1. Determine the Horizontal Mounting to be


dismantled, find the lowest position first and
the Vertical Mounting has been lowered.
2. Tie the horizontal position at the bottom
(Icicle Clove Hitch knot) with a rope that is
connected to the pulley and the control
rope.
3. Release one by one U-Bolt on the arm
bracket.
4. After all the U-Bolt on the Arm Bracket is
open, slowly move the Horizontal Mounting
load on the pulley.
5. Lower it the Horizontal Mounting slowly,
control the Horizontal Mounting so as not to
hit the existing device or to the tower by
using a control rope (lifting Sling).

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 13


Dismantle Process
 Dismantle Arm Bracket :

1. Lower it the arm bracket one by one,


after all Vertical Mounting and Horizontal
Mounting have been lowered.
2. Tie the Arm Bracket with a rope that has
been connected to the pulley and control
rope.
3. Release one by one U-Bolt on from the
leg tower.
4. After all the U-Bolt in the tower leg is
open, slowly move the Arm Bracket load
on the pulley.
5. Lower the Arm Bracket slowly, control
the Arm Bracket so it does not collide
with the existing device or to the tower
by using a control rope (lifting Sling).

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 14


Tali ke arah Katrol

Tali Kendali

Knot Icicle Clove Hitch to tie Mounting

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 15


Mounting Vertical/
Horizontal

Lifting sling/ Tali


Kendali

Traction sling/

Mounting to be lowered Lifting Sling Position (2 person)


vertically

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 16


Shackles

Traction Sling Position (2 people)

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 17


Mounting after being lowered

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 18


2.3 Perkiraan Estimasi Waktu
Duration
No Work Description Quantity
(hour)
1 Preparation Tool’s & Team @Day 1
2 Dismantle Vertical Mounting 6 pcs 6
3 Dismantle Horizontal Mounting 6 pcs 6
4 Dismantle Arm bracket 12 pcs 6
Total 19
Duration Dismantle Process
1. Persiapan Team dan peralatan dismantle : 1 hour / day
2. Dismantle Vertical Mounting : 1 hour / mounting unit
3. Dismantle Horizontal Mounting : 1 hour / mounting unit
4. Dismantle Arm bracket : 0.5 hour / arm unit

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 19


Security Level:

3. Clearance of Site

www.huawei.com

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential


3. Clearance of Site
Before Leave site, please check :
1. Check All Tool’s
2. Clean the site area from the remnants of material and rubbish
3. Report to HS to leave site & Close Gate Site

Photo Before – After Dismantle Mounting

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 21