TEST
Presented
By
RITESH KUMAR
JE(NQA),QAE(WP/WE),KOLKATA
SCOPE
•Covers inspection and pressure test requirements for valves such as:
Gate valve , Check valve, Plug valve, Ball type valve, Butterfly valve etc.
Stamp Transfer
• Cut out metal strip which previously dipped during metal pouring
• Punch inspector’s seal and heat no. on respective items
• Stamp transfer done mainly to recognise further when other type of inspection to be done
Visual inspection and Dimensional check of the valve component
•Spray penetrant on those surfaces and after 05 minutes wipe with dry cloth
•Spray developer on the exposed surfaces .if any crack present on those surface penetrant spread and
crack is eaisly visible
Issue I-note
I-note will be issued only after all inspection have been completed including that of
documentation preservation and packaging.