Professional Documents
Culture Documents
COST ESTIMATING
1
COST PLANNING AND COST ESTIMATING
Cost planning tells a project owner how much a proposed project will cost.
Additionally, cost planning will tell when the expected expenses will most likely
occur.
This information is critical for obtaining project financing and for determining
whether a project can be profitable. Without cost planning, project owners could
enter blindly into construction projects and possibly into insolvency.
2
COST PLANNING AND COST ESTIMATING
After the owner has set a maximum cost, cost planning will determine
whether that cost cap can be met. If not, the project is not feasible in its
current state and should be reworked to reduce costs.
3
COST PLANNING AND COST ESTIMATING
The first is an overall budget for the project. This is the total amount
that the project is expected to cost. This amount is based on the current
project scope and design and can be determined through various types of
estimates.
4
COST PLANNING AND COST ESTIMATING
5
COST PLANNING AND COST ESTIMATING
Cost planning should be done three times before the start of construction: once at
the project's initial inception, once after the preliminary design is complete, and
once after the final design is permitted.
Additionally, the cost plan should be regularly updated and tracked during the
course of construction to ensure accuracy, typically after each project milestone.
Warning: Although construction costs can be planned and estimated, they can
significantly change during the course of actual construction. The best way to
meet original cost planning estimates is to limit the amount of design change that
occurs on a project.
6
SAMPLE COST PLAN
CUMULATIVE COST
COST PLAN
ACT ACTIVITY COST WT W E E K
ID NAME (P) (%) 1 2 3 4 5 6 7 8 P
-- 1.00M
01 Site Prep & Excavation 36,000 3.6 3.6
02 Concrete & Steel Works 300,000 30.0 7.5 7.5 7.5 7.5
03 Carpentry 240,000 24.0 -- 0.75M 6 6 6 6
04 Masonry 96,000 9.6 3.2 3.2 3.2
05 Doors & Windows 90,000 9.0 4.5 4.5
-- 0.50M
06 Tile Works 50,000 5.0 5
07 Plumbing 40,000 4.0 2 2
08 Electrical 26,000 2.6 -- 0.25M 1.3 1.3
09 Roofing 90,000 9.0 4.5 4.5
10 Painting & Clearing 32,000 3.2 3.2
TIME
Total = 1,000,000
Weekly Accomplishment (%) 3.6 7.5 15.5 18 21.2 18.7 12.3 3.2
Cumulative Accomplishment (%) 3.6 11.1 26.6 44.6 65.8 84.5 96.8 100
Weekly Cash Flow (Php) 36 000 75 000 155 000 180 000 212 000 187 000 123 000 32 000
Cumulative Cash Flow (Php) 36 000 111 000 266 000 446 000 658 000 845 000 968 000 1 000 000
UP NEXT:
COST ESTIMATING
7
COST PLANNING AND COST ESTIMATING
Estimates usually include contingencies, which are downside risk estimates that
make allowance for unknown risks associated with a project.
8
TYPES OF CONSTRUCTION ESTIMATES
There are several kinds of estimating techniques; these can be grouped into two
main categories:
9
ESTIMATING & THE PROJECT DEVELOPMENT
The degree of accuracy of estimates will increase as the project progresses:
STAGE 1 STAGE 2 STAGE 3 STAGE 4 GOAL
Preliminary or Detailed Contract Sum Operational
Rough Estimate Estimate Estimate
USED IN Briefing stage, Bidding or Contract values Actual cost Accurate
feasibility study tendering for client during execution estimate for
approval feedback and
analysis
SOURCE Previous project Accurate Contract values Actual site and
records and ratio quantities based based on bid operational
estimates on working negotiation and information
drawings and type of contract
documents
TYPICAL 25% to 15% 15% to 10% 10% to 5% 5% 5% to 3%
RANGE OF
ACCURACY
ACTION BY Client and top Engineering Client, contractor Contractor Client and top
management division/designer management management
11
THE APPROXIMATE OR ROUGH ESTIMATE
References:
1. Pinoy House Plans Website: www.pinoyhouseplans.com
2. Home Ideas Magazine Available at NBS
3. Provided by Consultants Handbook by Langdon & Seah / Arcadis
12
THE DETAILED ESTIMATE
What is BOM?
What is BOQ?
13
THE DETAILED ESTIMATE
14
BILL OF MATERIALS (BOM)
15
BILL OF QUANTITIES (BOQ)
16
BOM vs BOM
FOOTING: FOOTING:
Concrete (cu.m) Cement (bag), Sand (cu.m), Gravel (cu.m)
Rebar (kg) Rebar (pcs)
Tie Wire (kg) Tie Wire (kg)
Used for Tendering Used for Construction
17
BOM vs BOM - Examples
18
REVIEW OF CONCRETE ESTIMATE
19
REVIEW OF CONCRETE ESTIMATE
Material Factor for Concrete By: Max Fajardo
CLASS/MIXTURE PROPORTION CEMENT SAND GRAVEL
(Cement:Sand:Gravel) (40 kg) (cu m) (cu m)
Class
Mixture C cubic meter
of half 1 :sand,
3.0 : 6a cubic meter6.00
of gravel and a0.50
portion mixture 1.00
of cement
depending on the class plus water will yield a little more than one cubic meter of volume.
This will serve as contingency or wastage.
Different companies use different values. Hence, estimators should use their own company
standard in estimating.
20
USES AND STRENGTH OF CLASS/MIXTURE
21
REINFORCED-CONCRETE ESTIMATE
Shortest L = 6.0 m 8 1 25
Longest L = 12.0 m 10 1-1/4 32
Increment = 1.5 m
12 1-1/2 40
16 2 50
22