Professional Documents
Culture Documents
PROBLEMS/COMMON DEFECTS
REMEDIAL MEASURES
I.MOBILIZATION
-Require the contractor to strictly
4. Inadequate/lack of testing equipment follow the requirement of the contract.
on the project site.
-Conduct briefing and trained contractors
personnel on the necessity of these
5. Inadequate/lack of safety measures and
as part of the contract.
signboards including Personal Protective
Equipment of workers on the project site.
-Provide/set-up guidelines and procedures
for immediate Implementation of the
6. Improper disposal of waste materials contractor.
and debris within the project site.
-Imposed penalty if necessary.
7. Lack of the necessary permit and
clearances from local officials.
CORRECTIVE ACTION/
PROBLEMS/COMMON DEFECTS
REMEDIAL MEASURES
II. EARTHWORKS
ITEM 800-CLEARING AND GRUBBING -Verify plan if the structure to be
ITEM 801-REMOVAL OF STRUCTURES AND constructed will be directly affected
OBSTRUCTIONS by the underground utilities.
1. Presence of underground utilities such
-Report/coordinate to proper authorities
as power lines, PLDT, existing MWSS lines. for removal and or relocation.
2. Presence of underneath existing
structure such as existing footing -Check construction schedule and prepare
foundation. necessary adjustment in the contract
duration or prepare revised PERT/CPM
incorporating said encountered problem.
3.Cut-off elevation not clearly established.
CORRECTIVE ACTION/
PROBLEMS/COMMON DEFECTS
REMEDIAL MEASURES
-Conduct visual inspection to determine
actual classification of soil, recommend
removal and disposal of unsuitable
ITEM 804- EMBANKMENT materials and replaced with suitable
1. Presence of unsuitable materials. materials in accordance with
specifications.
PROBLEMS/COMMON DEFECTS
REMEDIAL MEASURES
-Conduct investigation and in-place testing to
C.CONCRETE determine actual strength.
-If structure failed to meet strength requirement
1. Concrete structure failed to meet the
through in-place testing, refer to Structural
strength requirements as per concrete sample Engineer / Designer to assess extent of
specimens. corrective works.
-Chipped off concrete to determine extent of
2. Appearance of hairline cracks cracks, then apply concrete epoxy.
-Chipped off concrete to removed honeycomb
portion, then apply concrete epoxy prior to
3. Appearance of honeycomb or spalling re-concreting.
-Provide additional shoring and bracing if
concreting is still on going.
-For minor sagging or bulging removed affected
4. Sagging or bulging of concrete. portion and plaster.
-For major bulging, removed and replaced if
necessary.
-Require the Project Engineer to make the
necessary adjustments.
5. Non-conformance to finishing/ plastering
-Removed and replaced plastering works if
requirement. necessary.
-Call the attention of the Materials Engineer to
make the necessary adjustment to conform to
6. Improper curing
standard requirements.
CORRECTIVE ACTION/
PROBLEMS/COMMON DEFECTS
REMEDIAL MEASURES
-Non-load bearing, 500 psi and load
bearing at 800 psi.
VII. MASONRY WORKS -Removed and replaced all CHB that
1. Non-conformance to the required strength does not conform to the standard
for both non-load bearing and load bearing requirements.
-Conduct visual inspection and field
CHB.
testing.
-Chipped off laid CHB and install
stiffener columns.
-Require the Project Engineer to make
2. Non-provision of lintel beam and stiffener the necessary adjustments.
column. -Reject / removed and replaced if
necessary.
-Require the Project Engineer to make
the necessary adjustments.
3. Non-conformance to the vertical and
-Reject / removed and replaced if
horizontal dowel. necessary.
CORRECTIVE ACTION/
PROBLEMS/COMMON DEFECTS
REMEDIAL MEASURES
VIII. CARPENTRY AND JOINERY WORKS
-Require the Project Engineer to
removed and replaced all undersize
1. Undersize lumber and plywood. materials.
PROBLEMS/COMMON DEFECTS
REMEDIAL MEASURES
IX. FABRICATED MATERIALS AND HARDWARE
A. DOORS -Require the Project to make the
• Doors are not well fitted to the door necessary adjustments.
frames.
• Door accessories and other hardwares -Conduct frequent inspection and
items were installed not according to verification to monitor fabrication
schedule. prior to installations.
B. WINDOWS
• Windows are not well fitted to the window
-Reject / removed and replaced if
frames. necessary.
• Window accessories and other hardwares
item were installed not according to
schedule.
• Installed doors and windows were not in
accordance with specifications.
CORRECTIVE ACTION/
PROBLEMS/COMMON DEFECTS
REMEDIAL MEASURES
PROBLEMS/COMMON DEFECTS
REMEDIAL MEASURES
XI. ROOFING WORKS
1. Non-conformance to the required gauge -Removed and replaced.
and length.
-Conduct inspection and monitoring to
2. Non-conformance to the specified ensure compliance with the plans
overlapping( end lap, side lap ). and specifications.
3. Non-conformance to the approved method -Require the Project Engineer to make
the necessary adjustment on the
of fastening and joining.
workmanship.
4. Occurrence of leaks. -Conduct further leak test, provide
5. Non-conformance to the approved silicon sealant.
material requirements such as downspouts, -Reject / removed and replaced if
gutter, flashing and ridge roll. necessary.
CORRECTIVE ACTION/
PROBLEMS/COMMON DEFECTS
REMEDIAL MEASURES
XII. FINISHES
ITEM 1018- CERAMIC TILES
-Conduct inspection, verification and
• Occurrence of cracks on the materials.
monitoring of the materials and
• Uneven laying of tiles. methods of installation to ensure
ITEM 1019- WOOD TILES compliance to specifications.
• Non-conformance to the design lay-out.
• Uneven laying of tiles. -Require/instruct the Project Engineer
to make the necessary adjustment to
ITEM 1021- CEMENT FLOOR FINISH
the materials and workmanship.
• Uneven surface.
• Presence of temperature cracks. -Reject / removed and replaced if
• Weak mixture of fine and course necessary.
aggregate.
-Defer payment of accomplishment
ITEM 1026- PEBBLE WASHOUT FINISH until contractor complied with
• Uneven surface requirements.
• Pebbles are not uniformly distributed.
• Presence of temperature cracks.
CORRECTIVE ACTION/
PROBLEMS/COMMON DEFECTS
REMEDIAL MEASURES
XIII. PAINTING/VARNISHING
PROBLEMS/COMMON DEFECTS
REMEDIAL MEASURES
XV. SANITARY WORKS
-Conduct visual inspection,
verification and monitoring of the
installation of pipes to ensure
compliance to specifications.
-Require Project Engineer to make the
A. ITEM 1002- PLUMBING the necessary adjustment on sanitary
• Clogged pipes works.
• Pipes, fixtures and other sanitary -Require the contractor to rectify
accessories were installed not in defective works and conduct another
test until such time that it passes the
accordance with the plans, e.g. slope,
requirements.
alignment. -Reject / removed and replaced
• Failure to pass the leak test. defective works if necessary.
-Defer payment of accomplishment
until the contractor complied with
the requirements.
CORRECTIVE ACTION/
PROBLEMS/COMMON DEFECTS
REMEDIAL MEASURES
-Reject / removed and replaced defective
materials.
-Conduct visual inspection, verification and
monitoring of the installation of pipes, culvert
B. PIPES CULVERT AND STORM DRAIN
and storm drain to ensure compliance to
• Appearance of cracks on the materials. specifications.
• Inadequate collaring of reinforced concrete. -Require the contractor to rectify defective
• Inadequate bedding materials. works.
• Non-conformance to the required tolerance for -Require the Project Engineer to make the
elevation, slope and alignment. necessary adjustments to conform with
specifications.
-Reject work / removed and replaced if
necessary.
PROBLEMS/COMMON DEFECTS
REMEDIAL MEASURES
PROBLEMS/COMMON DEFECTS
REMEDIAL MEASURES
XVII. MECHANICAL WORKS
A. AIR CONDITIONING SYSTEMS -Reject / remove and replace
• Airconditioning units, transfer fans, pipes defective materials.
ducts, condenser installed not according -Require the contractor to rectify
to plan. defective works and conduct test until
such time that it passes the
• Defective materials and accessories.
requirements.
• Pipes and ducts not sufficiently braced. -Conduct visual inspection, verifications
• Failed to meet performance test. and monitoring of all materials and
• Leaks on pipes. installation of mechanical works to
B. GENERATOR SET ensure compliance to the required
• Installation of auxiliary piping and control specifications.
-Reject works if necessary.
not according to plan.
-Defer payment of accomplishment until
• Defective and damaged materials. the contractor complied with the
• Pipes not sufficiently braced. requirements.
C. ELEVATORS
1. Improper handling of elevator component
resulting to damage on accessories.