CLIENT: DLF LIMITED PROJECT: AMEX NEW COMPLEX

DAVID ADAMSON INDIA PVT. LTD.


CLIENT : DLF LIMITED
PROJECT : AMEX NEW COMPLEX, GURUGRAM HARYANA
PROJECT CODE : ID0013
WORK DETAILS : SUMMARY_MLCP-CONCRETE & SHUTTERING

SHUTTERING
SR. NO. DESCRIPTION CONCRETE (CUM) REMARK
(SQM)
1:4:8 M30 M35 M60 M80
A FOUNDATION

1 FOOTINGS 376.16 397.63


2 PCC FOR FOOTINGS 37.75 38.65
3 COLUMNS (FOOTING TO B3 LEVEL) 23.44 101.85

B BASEMENT 3

1 COLUMNS (B3 TO B2 LEVEL) 168.88 776.93


6.70 51.59
2 GRADE SLAB 194.72
3 PCC FOR GRADE SLAB 101.41 -

C BASEMENT 2

1 COLUMNS (B2 TO B1 LEVEL) 167.40 767.99


8.32 62.37
2 SLAB 172.27 3.435 0.261 822.23
3 BEAM 89.88
4 BEAM 28.00 625.26
5 BEAM 0.3735

D BASEMENT 1

1 COLUMNS (B1 TO GROUND LEVEL) 263.62 1157.10


11.56 86.67
2 SLAB 249.44 3.435 0.261 1181.14
3 BEAM 129.30
4 BEAM 36.87 842.24
5 BEAM 0.4545

E GROUND FLOOR

1 COLUMNS (GROUND TO P1 LEVEL) 128.66 570.60


6.48 48.60
2 SLAB 245.92 3.381 0.261 1225.23
3 BEAM 124.18
4 BEAM 27.91 983.34
5 BEAM 1.08

F P1 FLOOR

1 COLUMNS (P1 TO P2 LEVEL) 128.66 570.60


6.48 48.60
2 SLAB 244.33 3.41 0.26 1212.21
3 BEAM 123.97
4 BEAM 24.78 954.73
5 BEAM 1.13

G P2 FLOOR

1 COLUMNS (P2 TO P3 LEVEL) 128.66 570.60


6.48 48.60
2 SLAB 244.33 3.41 0.26 1212.21
3 BEAM 123.97
4 BEAM 24.78 954.73
5 BEAM 1.13

29-07-2022 SUMMARY 1
CLIENT: DLF LIMITED PROJECT: AMEX NEW COMPLEX

CLIENT : DLF LIMITED


PROJECT : AMEX NEW COMPLEX, GURUGRAM HARYANA
PROJECT CODE : ID0013
WORK DETAILS : SUMMARY_MLCP-CONCRETE & SHUTTERING

SHUTTERING
SR. NO. DESCRIPTION CONCRETE (CUM) REMARK
(SQM)
H P3 FLOOR

1 COLUMNS (P3 TO P4 LEVEL) 128.66 570.60


6.48 48.60
2 SLAB 244.33 3.41 0.26 1212.21
3 BEAM 123.97
4 BEAM 24.78 954.73
5 BEAM 1.13

I P4 FLOOR

1 COLUMNS (P4 TO P5 LEVEL) 128.66 570.60


6.48 48.60
2 SLAB 244.33 3.41 0.26 1212.21
3 BEAM 123.97
4 BEAM 24.78 954.73
5 BEAM 1.13

J P5 FLOOR

1 COLUMNS (P5 TO P6 LEVEL) 128.66 570.60


6.48 48.60
2 SLAB 244.33 3.41 0.26 1212.21
3 BEAM 123.97
4 BEAM 24.78 954.73
5 BEAM 1.13

K P6 FLOOR

1 COLUMNS (P6 TO P7 LEVEL) 156.41 685.65


9.72 72.90
2 SLAB 244.33 3.41 0.26 1212.21
3 BEAM 123.97
4 BEAM 24.78 954.73
5 BEAM 1.13

L TERRACE FLOOR /P7

1 SLAB 231.05 3.36 0.26 1212.84


2 BEAM 123.97
3 BEAM 24.78 954.73
4 BEAM 1.13
5 COLUMN (ABOVE TERRACE) 39.65 188.39
7.56 56.70

M RAMP 04

1 RAMP (BEAM,SLAB,PARAPET WALL) 144.77 925.18

N STAIRCASE

1 STAIRCASE 07 60.00 300.77


2 STAIRCASE 08 26.94 198.24
3 STAIRCASE 09 22.07 114.57

O SW/NSW

1 NSW-LIFT WALLS 68.43 684.28


2 PARAPET WALL 219.34 1754.75

P DRAIN CHANNELS

DRAIN CHANNELS IN GRADE SLAB &


1 16.97 58.75
TYPICAL FLOOR

Q MUMTY LEVEL

MUMTY ROOF-SLAB,BEAM & OTHER As drawings are not


1 STRUCTURAL MEMBER INCLUDING 50 350.00 available, Qty
ELEVATIONAL FEATURES assumed

TOTAL 139.16 4755.17 0.00 1891.65 95.19 33394.75

29-07-2022 SUMMARY 1
CLIENT: DLF LIMITED PROJECT: AMEX NEW COMPLEX

DAVID ADAMSON INDIA PVT. LTD.


CLIENT : DLF LIMITED
PROJECT : AMEX NEW COMPLEX, GURUGRAM HARYANA
PROJECT CODE : ID0013
WORK DETAILS : SUMMARY_MLCP-CONCRETE & SHUTTERING

GRADE OF SHUTTERING
SR. NO. DESCRIPTION CONCRETE (CUM) Total QTY REMARK
CONCRETE (SQM)

A RAMP 04

1 COMPACTED FINE SAND FILLING (CUM) 1.00 122.20

B STAIRCASE

1 LIGHT WEIGHT FILLING (SQM) 9.49

C DRAIN CHANNELS

1 PERFORATED PRECAST SLAB (RMT) 65.27


2 MS GRATING (RMT) 183.04