You are on page 1of 10

Rockmelon & Watermelon

Project 2020

Md. Maruf Hosen


01730628497
Overview

 Total Cost 100,000 taka


 Total Sell 180,000 taka
 Estimate Profit 80,000 taka
Project Time:

March,2020 to May,2020
Estimate Cost for 0.4 Acre
 1. Lease 6,000 taka
 2. Mulching paper 18,000 taka
 3. Seed 5,000 taka
 4. Fertilizer 10,000 taka
 5. Fixed Labor 21,000 taka(4k+3k(Maruf)/month)
 6. Labor 20,000 taka
 7. Macha+BeRa+Other cost 10,000 taka
 8. Extra cost 5,000 taka
 Night guard for 1 month 5,000 taka
 Total estimate cost 100,000 taka.
Watermelon project
 1400 plant
 We calculate 1000 plants for final production
 1000 plants*4 kg=4,000 kg
 4000kg*25 taka/kg = 100,000 taka
Rockmelon Project

 1000 Rockmelon plant.


 We calculate for 700 tree.
 Minimum rockmelon in a plant is 1.5 kg.
 Total rockmelon is 1050 kg
 Minimum wholesale price/kg is 80 taka.
 Total sell price is 1000kg*80= 80,000 taka.
Total Sell

 Watermelon 100,000 taka


 Rockmelon 80,000 taka
 Total sell 180,000 taka
Profit

 Total sell 180,000 taka


 Total Cost 100,000 taka
 Profit 80,000 taka
Profit Share