READINESS
P R E S E N TAT I O N
AKG-1
SHUTDOWN
DATE: 28-DEC-2020
Project Scope
Carryout Engineering Procurement Demolition and installation of PRV HEADER for 132/162-
V002, 28” PRV Corroded Header AKG-1 during Shutdown
SHUTDOWN ACTIVITIES
Mobilization of Crane
Carry out Blinding
Carry out Cold Cutting 28”- 3 joints for demolition of existing line.
Demolition of existing 28” pipe line from column using load bearing scaffolding
Demolition of PRV header line including valves and 16” down steam line up to isolation valves
Carry out installation of 28” new fabricated line and connect to the column
Carry out welding (1 Nos of 28” Joint) During SD
Carry out hydro testing at site
Carry out touch up painting
Carry out housekeeping
Project Routing for AKG-1 Scope
Manpower Histogram
70 70 70 70 70 70 70 70
70
60
60
-------NO OF PERSONS--------->
50
50
40
35 35 35 35 35 35 35 35 35 35 35 35 35
30
25 25 25 25 25 25 25
20
10
0
n n n n n n n n n n n n n n n n n n n n n n n n n n n n n n
Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja
1- 2- 3- 4- 5- 6- 7- 8- 9- 10 - 11 - 12 - 1 3 - 14 - 1 5 - 1 6 - 17 - 1 8 - 19 - 2 0 - 21 - 2 2 - 2 3 - 24 - 25 - 2 6 - 27 - 2 8 - 2 9 - 30 -
--------------MONTHS----------->
Safety Organization
Doc. No.:
HSE ORGANIZATION CHART MAINT/ALL//HSE/FRM-30
Rev.:00
Date: September 16, 2020
Page: 1 of 1
QAT ARGAS SOUT H T RAIN 5 SD- 2020
A- DESIGNATION
B- SHIFT
C- NAME
D-CONTACT NO. HSE MANAGER
DAY
SHAJU JOSEPH
55842732
HSE LEAD
DAY
RAJESH MARADANA
55893215
DAY NIGHT
33067764 66009093
For:
1 Fitness To Work 70 65 5
Covid Action Plan
Our Covid-19 Mitigation Plan for is approved and In case there is a second wave
for Covid-19 and TRAGS is effecting, we follow same protocol form our
company as well as QG and current manpower working in QG project will be
utilize.
Q & A / SUGGESTIONS
Thank You