You are on page 1of 10

TRAGS HSE

READINESS
P R E S E N TAT I O N
AKG-1
SHUTDOWN

28” PRV HEADER


REPLACEMENT
PROJECT FOR AKG-1

DATE: 28-DEC-2020
Project Scope

 Carryout Engineering Procurement Demolition and installation of PRV HEADER for 132/162-
V002, 28” PRV Corroded Header AKG-1 during Shutdown
SHUTDOWN ACTIVITIES
 Mobilization of Crane
 Carry out Blinding
 Carry out Cold Cutting 28”- 3 joints for demolition of existing line.
 Demolition of existing 28” pipe line from column using load bearing scaffolding
 Demolition of PRV header line including valves and 16” down steam line up to isolation valves
 Carry out installation of 28” new fabricated line and connect to the column
 Carry out welding (1 Nos of 28” Joint) During SD
 Carry out hydro testing at site
 Carry out touch up painting
 Carry out housekeeping
Project Routing for AKG-1 Scope
Manpower Histogram

AKG-1 SD MANPOWER HISTOGRAM


80

70 70 70 70 70 70 70 70
70

60
60
-------NO OF PERSONS--------->

50
50

40
35 35 35 35 35 35 35 35 35 35 35 35 35

30
25 25 25 25 25 25 25

20

10

0
n n n n n n n n n n n n n n n n n n n n n n n n n n n n n n
Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja Ja
1- 2- 3- 4- 5- 6- 7- 8- 9- 10 - 11 - 12 - 1 3 - 14 - 1 5 - 1 6 - 17 - 1 8 - 19 - 2 0 - 21 - 2 2 - 2 3 - 24 - 25 - 2 6 - 27 - 2 8 - 2 9 - 30 -
--------------MONTHS----------->
Safety Organization
Doc. No.:
HSE ORGANIZATION CHART MAINT/ALL//HSE/FRM-30
Rev.:00
Date: September 16, 2020
Page: 1 of 1
QAT ARGAS SOUT H T RAIN 5 SD- 2020

A- DESIGNATION
B- SHIFT
C- NAME
D-CONTACT NO. HSE MANAGER

DAY

SHAJU JOSEPH

55842732

HSE LEAD

DAY

RAJESH MARADANA

55893215

HSE OFFICER HSE OFFICER

DAY NIGHT

CHANDRA BHUSHAN SHAIKH KALIMULLAH

33067764 66009093

For:

00 FOR APPROVAL 15-Dec-20 PROJECT MANAGER


Prepared by : Rajesh Maradana (HSE Lead)
Rev Purpose Date Approved By Notes
TRAGS HSE KPI’s

Items Target Items Target


IIF Action Cards 50 Fatality 0
HSE Hazard Hunt / HSE Inspection 20 TRIR 0
Covid 19 Audit Daily (D/N) 20 LTI 0
Safety Walkthrough (Site Management) Daily Restricted Work Case
0
(D/N)
PTW Audits 50 Medical Treatment Cases 0
Fatigue Assessment 15% First Aid Cases 0
Action Close Out against target date 100% Near Miss 0
Shutdown Award & Recognition 10% Fire & Explosion 0
Waste Segregation Compliance >=98.5%
Training & Medical Requirement

TRAGS Training Need Analysis


Currently Remaining
SL # List Of Trainings Required Persons
Trained Training
1 Plant Safety Induction 70 70 0
2 Shutdown Induction 70 0 70
Heat Stress
3 N/A N/A N/A
Awareness
4 Fire Watch 4 4 0
5 WMS 6 6 0
6 Defensive Driving 5 5 0
7 Work At Height 70 70 0

Medical (Fitness To Work ) Status


Fit To Work
SL # QG Onshore Medical Required Persons To Be Submitted

1 Fitness To Work 70 65 5
Covid Action Plan

Separate covid action plan prepared and aliened with Qatargas


Operations Interim Measures in Response to COVID-19 Pandemic Rev-04.

Our Covid-19 Mitigation Plan for is approved and In case there is a second wave
for Covid-19 and TRAGS is effecting, we follow same protocol form our
company as well as QG and current manpower working in QG project will be
utilize.
Q & A / SUGGESTIONS
Thank You

You might also like