Professional Documents
Culture Documents
PERTAMINA EP
MATINDOK GAS DEVELOPMENT PROJECT (MGDP)
Ahmad SaifulAnwar
Digitally signed by HenryC Bacus Rangaswamy Guruswamy
2014.06.25 10:55:09 HenryC Bacus DN: cn=HenryC Bacus 2014.06.25 17:14:14
Date: 2014.06.25 12:42:16 +07'00'
+07'00' +07'00'
TOTAL OR PARTIAL REPRODUCTION AND/OR UTILIZATION OF THIS DOCUMENT ARE FORBIDDEN WITHOUT PRIOR WRITTEN
AUTHORIZATION OF PT. PERTAMINA EP
MTDF-PP-300-SPE-1019 2
7518-300-JSC-1300-0002
MATINDOK GAS DEVELOPMENT PROJECT (MGDP)
SPECIFICATION FOR FIELD PIPING FABRICATION,
INSTALLATION, CLEANING, FLUSHING, AND
TESTING
REVISION REVISION
SHEET REMARKS SHEET REMARKS
0 1 1A 2 3 4 0 1 1A 2 3 4
1 X X X X 46
2 X X X X 47
3 X X X 48
4 X X X 49
5 X 50
6 X X X 51
7 X X 52
8 X X 53
9 X X 54
10 X X 55
11 X X 56
12 X X 57
13 X X 58
14 X X 59
15 X X 60
16 X X X 61
17 X 62
18 X 63
19 X 64
20 X 65
21 X 66
22 X 67
23 X 68
24 X 69
25 70
26 71
27 72
28 73
29 74
30 75
31 76
32 77
33 78
34 79
35 80
36 ATTACHMENT
37 1
38 2
39 3
40 4
41 5
42 6
43 7
44 8
45 9
TABLE OF CONTENT
1.0 OBJECTIVE
This specification covers the minimum requirements for the field piping fabrication, inspection, installation,
cleaning and flushing, and testing for Matindok Gas Processing Facilities of Matindok Gas Development
Project (MGDP).
3.0 REFERENCES
The following applicable section of the latest edition of the code and standards, including addenda and
referenced documents, project's specification shall form an integral part of this specification.
Where the requirement of the subject is defined by two or more references, the more stringent reference
shall govern.
2. All pipe and piping components shall be stored off the ground and protected from the elements. This is also
applied to prefabricated assemblies at the prefabrication yard and at erection site whatever is the expected
duration of the storage.
3. The ends and openings of all pipe, components and assemblies shall be protected with suitable covers at
all times while handling and while in storage. Protective covers shall not be removed until just prior to final
assembly. Special precautions shall be taken during erection to prevent foreign matter from entering piping
system.
4. Coated and wrapped pipe shall be handled with wide canvas or leather belts or other equipment designed
to prevent damage to the coating. Skids or racks used to support coated and wrapped pipe and fittings
shall be padded. Adequate shading from the sun shall be provided to avoid sagging of the coating. Walking
on coated and wrapped pipe is strictly prohibited.
5. The area storage shall be grouped for each type of material (Carbon Steel, Incoloy, Cladding, FRP, etc)
2. Cold springing or forcing of piping for the purpose of joint makeup shall not be permitted.
3. Piping shall be supported and guided as shown on the piping and support detail drawings. Temporary
supports to facilitate piping installation and testing are permitted, and they are completely removed upon
completion. Attaching temporary supports to stainless, alloy steel or stress relieved piping by welding is
prohibited. Any field installed support, brace or guide deemed necessary by the inspector shall be installed
and indicated on as-built drawings.
4. Valves shall be installed with the stems or shaft orientation as indicated on the piping drawing. Wafer type
check valves shall be installed with the shaft in the vertical position when in horizontal runs. Globe valves
shall normally be installed with the bottom of the disc facing the flow. Valve in cryogenic liquid service
(Extended Bonnet) shall be installed such that the extended bonnet is in the vertical upright position. .
5. Dimensional Tolerance
a) The tolerances for shop or field prefabricated piping shall conform to Figure.1.
b) The tolerances for mating flanges of pumps and compressors shall be within the following range :
Flange face parallelism : 0.25 mm for pipe ≤ 10 inch, 0.5 mm for pipe 10 inch < D ≤ 20 inch, and 0.8
mm for pipe > 20 inch.
Clearances between flanges: space required for gasket + 0.8 mm.
Rotational offset: 0.8 mm
6. Threaded connections shall be chased and gage checked after welding or heat treatment. Openings for
thermo wells and other inserts shall be drilled through the connection and be free from obstruction.
Threaded joints shall be properly applied with thread lubricant seal tape only on the male end in such a
manner that will prevent the compound from reaching the interior of the fitting.
7. Where seal welding is specified for the piping service class, the threaded joint shall be thoroughly cleaned
of grease seal tape and oil and made up without the application of thread lubricant. Seal welding shall be
done by a qualified welder. Seal weld shall completely cover the exposed threads.
8. Socket weld joints shall be carefully aligned and set to ensure that a clearance of 1.5 to 2 mm remains
between the end of the insert and the bottom of the socket to provide for expansion during welding. Socket
weld valves shall be welded in electric arc welding process to minimize distortions and valves with having
metal seats shall be closed hand tight during welding.
9. Coating and wrapping of underground piping shall be in accordance with specification No. MTDF-PP-300-
SPE-1010, "Specification for Wrapping for Tape Protective Coating."
10. Flange bolt holes shall be aligned to straddle the natural centerlines of the pipe or fitting unless otherwise
noted on the piping drawing. Flanged joints shall be made up in such a manner as to avoid uneven loading
of the bolts and gasket. The flange faces shall be pre aligned and the nuts tightened in the recommended
crossing pattern to maintain the alignment and avoid uneven stressing of the bolts. Studs bolts are to be
tightened to the full value shown in spec No. MTDF-PP-300-SPE-1008 ”Specification for Bolting”. If after
tightening a flanged joint has to bed is assembled, whatever is the reason, a new gasket shall be installed.
Special care must be exercised with flanged joints using spiral wound or ring joint gasket, if leak-tight joints
are to be obtained.
11. Whenever repairs or additions involving welding are made following the pressure test, the affected piping
system shall be retested under the original test conditions.
12. Where insulation flange kits are to be installed, care shall be taken not to damage the bolt sleeves and
gasket.
13. Pipe routing may sometimes require field modifications to avoid interferences or correct errors in design or
fabrication. The need for such modifications or additions shall be determined by the field and shall be
approved by COMPANY engineer or inspector. All field changes or modifications shall be reflected on the
as built record drawings and shall be incorporated in the final as-built revision of the piping drawings.
7.0 INSPECTION
The COMPANY inspector shall at all reasonable times have access to the work wherever it is in
preparation or progress. This includes manufacture, fabrication, heat treatment, assembly, erection,
examination and testing of piping and piping components. The inspector shall be notified 2 days minimum
prior to commencement of any such activities or procedures. The inspector shall have the right to audit any
examination and testing, inspect any work in progress or finished product, and review all certifications and
records. The inspector shall have the authority to reject any materials, procedures or work which fails to
meet the requirements of this specification or the documents referenced herein.
The approval of the inspector shall not relieve the engineering contractor of the responsibility for
compliance with the engineering design and specifications or the requirements of the applicable codes, or
company's requests previously agreed on.
MTDF-PP-300-SPE-1019 - Rev. 2 | 7518-300-JSC-1300-0002 Page 10 of 16
MATINDOK GAS DEVELOPMENT PROJECT (MGDP)
SPECIFICATION FOR FIELD PIPING FABRICATION,
INSTALLATION, CLEANING, FLUSHING, AND
TESTING
The team inspector shall include any properly authorized representative of COMPANY.
1. Upon completion of erection, piping systems shall be visually inspected for completeness, proper
gasketing, proper valve installation, supporting, proper control valve installation, proper routing, proper
alignment, proper corrosion protection and proper insulation.
2. Piping systems and associated equipment are to be checked against P&IDs, drawing sand other relevant
specifications to ensure that all fittings, connections, slope of lines, etc., are in accordance with design
requirements.
3. The location and lengths of pipe shoes shall be checked to ensure that as the lines expand or contract
when taken into service, the pipe shoes will remain on the supports. These are to be rechecked as the
system is warmed up or cooled down and reach operating temperature.
4. Each flanged connection in cryogenic piping systems shall be carefully inspected for alignment of flanges
and gasket and for correct and uniform bolt tightening to a pre-determined torque. Molybdenum disulphide
base lubricant applied to all bolt threads and between the nuts and flange will reduce galling and permit
uniform tightening.
8.1 General
All process and utility pressure piping shall be pressure tested as required by the applicable codes and as
described herein. Pressure piping includes all piping designated to convey or contain process or utility
fluids at either positive or negative internal pressure. Open vents and drains, etc. at essentially atmospheric
pressure are not to be considered pressure piping. Seal welding shall not be used to remedy a thread joint
that leaks during testing.
For hydrostatic testing of piping with equipment (i.e. vessels, heat exchanger etc) the test pressure
shall be in accordance with ASME B31.3 2010 Edition paragraph 345.4.3.
Should the design temperature be higher than the temperature of the test fluid the test pressure
shall be checked as per equation 24 of ASME B31.3 2010 Edition.
Each reinforcing pad for pressure openings shall be tested with air at a pressure of 60 - 100 psig
2
(4.2 - 7 kg/cm G) and a bubble test solution shall be applied to inspect all welds.
(1) The fluid is non-flammable and non-toxic such as air, water, inert gas, etc.
2
(2) The design pressure does not exceed 10.5 kg/cm G (150 psig).
(3) The design temperature is between -29°C and 186°C.
8.4.2 The test pressure gage should be located at the high point of the system being tested. If this is impractical
the gage may be located elsewhere. When the gage is installed at lower point, static above the gage shall
be calculated and deducted from the gage reading to determine the full pressure at the high point.
The number of pressure gages used for test shall be at least two and they have to be certified.
8.4.3 The hydrostatic test fluid shall be fresh water which shall not contain more than 30 ppm chlorides for
hydrostatic test of Austenitic Stainless Steel. Where water may adversely affect the operating commodity or
the piping material other suitable liquid may be used with COMPANY approval on an individual basis.
8.4.4 The system shall be thoroughly purged of air and then pressured to the specified test pressure and held for
sufficient time to allow all joints to be inspected, but in no case for less than ten minutes. The system shall
not be allowed to stand pressurized except during the actual test period as temperature changes may
cause excessive pressure or vacuum.
8.5.2 All cryogenic piping that cannot be completely dried after test shall be pneumatic tested. Care should be
o
taken to remove all water from piping to be operated below 0 C. This includes relief valves, control valves
and other piping components that have been tested in the shop.
8.5.3 In consideration of the potentially hazardous conditions present during pneumatic testing, all non-essential
personnel shall be cleared from the are and barricades placed at a safe distance to prevent unauthorized
person centering during pressurization. Test personnel should wear ear protection at all times.
8.5.4 The system of pneumatic test is to be minimized to limit the extent of damage in case of failure during test.
Volume of the test circuit shall be limited as follows:
Where necessary to conduct pneumatic test of greater pressure/volume than listed above, written approval
must be obtained from the COMPANY.
8.5.5 Pressurization of the system shall be in gradual steps of about 15% withholding period between each step
to allow piping to equalize strains and for preliminary inspection for leaks.
8.5.6 The test pressure shall be held for 30 minutes for all joints to be inspected for leaks with soap solution or
sonic testing equipment.
8.5.7 After completion of test, depressurization shall be gradual to allow equalization of strains and to minimize
noise.
8.8.2 All blanks, blinds, valves, gages, temporary supports and restraints installed for testing shall be removed
on completion of testing. Removal must be certified for every component by signature of the COMPANY
inspector and operations superintendent.
8.8.3 Where flanged joints are disassembled for removal of test blanks, the gasket must be replaced. New
gaskets shall be used in the final makeup of all joints. This includes flange joint opened for the testing or
cleaning of piping system. Instruments removed or blocked off for testing shall be replaced or reconnected.
8.8.4 All bolts at flanged joints shall be inspected for tightness and tightened or replaced to the satisfaction of the
inspector.
MTDF-PP-300-SPE-1019 - Rev. 2 | 7518-300-JSC-1300-0002 Page 14 of 16
MATINDOK GAS DEVELOPMENT PROJECT (MGDP)
SPECIFICATION FOR FIELD PIPING FABRICATION,
INSTALLATION, CLEANING, FLUSHING, AND
TESTING
A complete history of each system tested shall be maintained. The test diagram in conjunction with the
corresponding P&ID, line data index and test schedule will be used for this package. The test record shall
be including at least the following:
8.9.3 Safety
(1) Every feasible step should be taken to prevent a failure from occurring. The safety of the
operating/construction personnel must be provided for in the event a failure occurs.
(2) Testing schedule should be posted prior to starting the test and since in many cases test could
involve pipe and equipment in more than one plant all supervision in the areas of interfaces must
be aware that the testing is taking place.
(3) Prior to beginning the physical test operation/construction will make a dry line check marking their
records as to location of blinds, positions of valves and conditions of all branch lines indicated. At
this time any cascading to other systems will also be checked for acceptability of the test medium.
(4) After the test is complete operation/construction personnel will compare records and when there is
complete agreement the test log will be signed off by both parties.
9.1 General
Piping assemblies shall be dry, thoroughly cleaned and free from dirt, slag and other loose foreign
materials both inside and out when erected. Before assembly they shall be up-ended and rapped to
dislodge any dirt and debris. Hot bends shall be turbine or otherwise cleaned to remove adherent sand
and grit. Where an assembly is incomplete when erected, any opening shall remain covered until the
installation is finished.
(1) Normally, piping systems are flushed with water after erection. Unless otherwise specified, piping
systems are flushed with minimum velocity of 3 m/s.
However, this will be avoided in certain piping such as compressor suction lines, lube oil and seal
oil lines and cryogenic systems having low points and cavities that cannot be readily dried out
(2) Where other special conditions exist, specific specifications will cover cleaning and preparations.
9.5 Flushing
Except as stated above, all completed systems shall be internally cleaned to remove dirt and debris by
flushing with water or flowing with steam or air. Precautions shall be taken to ensure that debris is not
flushed into associated vessels, equipment, or dead ends. Flushing shall not be carried out through
exchangers, machinery or other equipment which could be damaged. Control valves, orifice plates, and
other in-line instruments should be removed during the flushing operation. Flushing may normally be done
before, during, or after pressure testing. Acceptance criteria of flushing are no foreign matter remained at
the wire mesh (#20, 10X10 cm).
Rev.2
9.6 Blowing
For blowing compressed air shall be used. Temporary oil free compressor shall be used to generate
compressed air.
The following shall be prepared before blowing:
a) Make sure that all of tools needed for blowing (temporary lines, masking tape) have been
prepared.
b) In-line instruments and other equipments which have problem with water contact / sensitive item
shall be removed.
Acceptance criteria of blowing are no debris (hard material) at paper or adhesive tape put in exhaust
stream.