Industries Design & Vendor Documents Management Procedure
Engineering Company
(PIDEC)
Doc. No.: 1231-DE-00-DC-PCJ-001 Rev.: 01
Project No. : 1231 Project No. : 214
VENDOR DOCUMENTS
MANAGEMENT PROCEDURE
DE EXT IFI I
Eng. Phase Purpose Of Distribution (POD) Purpose Of Issue (POI) Owner's Action
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 1 of 11
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
Petrochemical
Industries Design & Vendor Documents Management Procedure
Engineering Company
(PIDEC)
Doc. No.: 1231-DE-00-DC-PCJ-001 Rev.: 01
Project No. : 1231 Project No. : 214
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 2 of 11
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
Petrochemical
Industries Design & Vendor Documents Management Procedure
Engineering Company
(PIDEC)
Doc. No.: 1231-DE-00-DC-PCJ-001 Rev.: 01
Project No. : 1231 Project No. : 214
Index Page
1. Purpose 4
2. Applicable Documents 4
3. Definitions 4
4. General Requirements 4
4.1 Language 5
4.2 Document Size 5
4.3 Electronic Documents 5
4.4 Drawing Formats 5
5 Procedure 5
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 3 of 11
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
Petrochemical
Industries Design & Vendor Documents Management Procedure
Engineering Company
(PIDEC)
Doc. No.: 1231-DE-00-DC-PCJ-001 Rev.: 01
Project No. : 1231 Project No. : 214
1. PURPOSE
Is to outline uniform technical document exchanging system between Vendor and EPs
Contractor (PIDEC) and to describe how, when and which documents shall be prepared
and issued by Vendor.
In other words it provides a basis for a controlled routing of vendor's data between the
relevant Contractor’s engineering disciplines and a proper coordination for reflecting
Contractor’s comments to the vendors until the final and certified Documents and Drawings
(Final Manufacturing Data Book) are received so that all purchased equipment conform to
agreed requirements.
The present document describes requirements to be followed by Vendor for the supply of
documentation listed in "Requirement for Documents (RFD)" which is attached to the
relevant Purchase Requisition.
2. APPLICABLE DOCUMENTS
RFD : "Requirement for Documents" which is attached to the Purchase Requisitions
VDIS : Vendor Documents Index & Schedule which shall be prepared by vendor as per
RFD form requirements in Microsoft Excel in accordance with Attachment No. 02
3. DEFINITIONS
Owner : Zanjan Agricultural & Fertilizer Industries Company (ZAFIC)
Purchaser : TexTrade Maschinen-Handels GmbH (TTM)
PMC : Construction and Project Control Management Company (CCM)
EPs Contractor : Petrochemical Industries Design and Engineering Company (PIDEC)
Vendor : Any Company appointed by Owner/Purchaser to supply or
manufacturing of equipments/materials or services related to the
Purchase Requisition
Sub-vendor : Any Company appointed by vendor to supply or manufacturing of
equipments/materials or services wholly or partly as per related the
Purchase Requisition with consideration of prior approval of
Owner/Purchaser.
4. GENERAL REQUIREMENTS
For prompt identification, traceability and control of documents following attributes shall be
considered in cover sheet and subsequent sheets within title blocks of each
document/drawings prepared for the job. (Refer to Attachment No. 03)
- Owner/Purchaser name and logo
- EPs Contractor's name and logo
- EPs Contractor's Project number
- EPs Contractor's Document number (as per this procedure)
- Document title (as per approved VDIS)
- Sheets number
- Total number of sheets
- Document Revision No.
- Purpose of Issue (POI) or EPs Contractor’s Action (as per RFD Form and sub-clause 5.4)
- Date of issue (DD/MM/YYYY)
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 4 of 11
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
Petrochemical
Industries Design & Vendor Documents Management Procedure
Engineering Company
(PIDEC)
Doc. No.: 1231-DE-00-DC-PCJ-001 Rev.: 01
Project No. : 1231 Project No. : 214
4.1 LANGUAGE
All Vendor Documents shall be written in English language.
4.2 VENDOR'S DOCUMENT SIZE
Vendor Documents sizes shall be in accordance with following requirements:
All documents shall be as per "A" series of international Standard ISO 216 from A1, A2, A3
and A4.
Maximum size of drawings shall be A1 and minimum A4.
Those drawings in format A1, A2 or A3 shall be folded to A4 size in way that title block to
be on front (in case of hard copy required during fabrication and certainly at the end of order
completion)
All A4 documents format shall have a cover sheet (Refer to Attachment no. 03)
At right time, Contractor will supply all the necessary information such as formats, frames,
title block and comment logo in a native file for using and or insert to the required
documents.
Drawings and Documents which are not in accordance with the above instructions will be
rejected and considered as not received.
4.3 ELECTRONIC DOCUMENTS
The following commercial software as a minimum shall be used, unless otherwise approved
by PIDEC:
- AutoCAD Version 2007 and higher
- MS Office Version 2007 and higher
- Adobe Acrobat Version 9.0 and higher
Utilizing other version of above mentioned soft-wares shall be subjected to EPs Contractor's
approval.
4.4 DRAWINGS FORMAT
Drawings shall always be performed on a 1:1 scale using millimeters as unit of
measurement. Logical unit corresponding to millimeter in AutoCAD shall be used.
Dimensions shall not be exploded.
Text on drawings shall be in “Romans” font in AutoCAD and font size no smaller than 2.
5. PROCEDURE
5.1 VENDOR DOCUMENTS INDEX AND SCHEDULE (VDIS)
This form shall be filled up by Vendor, listing all documents and drawings to be submitted
with consideration of PIDEC needs which have been specified within RFD form which is
attached to the requisition. First issue of VDIS indicating all anticipated of all attributes which
has been specified within Attachment No.2
VDIS shall be submitted for PIDEC’s approval within two weeks after ordering or letter of
intent issuing. VDIS shall be updated and reissued together with Vendor’s monthly progress
reports if required. Sample of Vendor Document Index and Schedule (VDIS) is attached
here in Attachment No.2
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 5 of 11
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
Petrochemical
Industries Design & Vendor Documents Management Procedure
Engineering Company
(PIDEC)
Doc. No.: 1231-DE-00-DC-PCJ-001 Rev.: 01
Project No. : 1231 Project No. : 214
Important Note:
1: Each document must have a unique number.
2: Repeated document Number shall be checked and corrected in VDIS by vendor.
3: Any deletion and addition of documents in VDIS is subject to PIDEC's approval.
4: Deletion of documents which have already been issued to PIDEC and uploaded to VDMS
is not possible; these items shall be marked as a “Void”.
Upon uploading vendor's documents based on the approved VDIS, Project Vendor
Document Coordinator (VDC), and other concerning people will be automatically informed
via e-mail from pidecerp@pidec.com, PIDEC is responsible to work on the first issue of
vendor documents and reflect their comments/approval to vendor by 14 calendar days and
9 calendar days for further issues with uploading comments to VDMS
Upon uploading PIDEC comments to the system, VDMS will automatically send back the
reply Transmittal to vendor and other concerning people via e-mail from
pidecerp@pidec.com.
Vendor has to consider all comments and incorporate them to the fabrication and
accordingly proceed to revise respective drawings by 14 calendar days with uploading new
revision to VDMS.
Important Note:
Uploading PDF file of Vendor Documents in the system is mandatory, because this is trigger
for sending automatic transmittal to all concerning people, if the vendor document file is
basically in the native format such as calculations, models and etc. a fake cover sheet in
PDF format shall be uploaded.
E-files of documents and drawings shall be named same as document/drawing number.
General work flow of Vendor document management is attached here in Attachment No.4.
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 6 of 11
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
Petrochemical
Industries Design & Vendor Documents Management Procedure
Engineering Company
(PIDEC)
Doc. No.: 1231-DE-00-DC-PCJ-001 Rev.: 01
Project No. : 1231 Project No. : 214
Example:
VD-1231-01-201A-DWG-001
Note: For any Coordination and Numbering of Steel Structures/Grating’s Shop Drawings
for domestic orders, reference shall be made to Attachment No.1.
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 7 of 11
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
Petrochemical
Industries Design & Vendor Documents Management Procedure
Engineering Company
(PIDEC)
Doc. No.: 1231-DE-00-DC-PCJ-001 Rev.: 01
Project No. : 1231 Project No. : 214
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 8 of 11
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
Petrochemical
Industries Design & Vendor Documents Management Procedure
Engineering Company
(PIDEC)
Doc. No.: 1231-DE-00-DC-PCJ-001 Rev.: 01
Project No. : 1231 Project No. : 214
Important Note: This transmittal shall be used only for PIDEC's own Technical documents
such as Requisition, Data Sheets, Specification and any other Technical documents except
Vendor's documents.
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 9 of 11
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
Petrochemical
Industries Design & Vendor Documents Management Procedure
Engineering Company
(PIDEC)
Doc. No.: 1231-DE-00-DC-PCJ-001 Rev.: 01
Project No. : 1231 Project No. : 214
1) Sender/Receiver
OT: OWNER / Tehran
TTM: PURCHASER / GERMANY
MT: PMC / Tehran
PS: PIDEC / Shiraz
XXX: Vendor Abbreviation (max. 5 and min.3 Characters) i.e. PKA as Petro Kimia Arvin
Example:
5.12.1 Communications shall be replied by each parties within Five (5) working days from the
Date of receipt of the E-Mail.
6. FINAL VENDOR DATA BOOK
The purpose of this part of procedure is to give an adequate guidance to Vendors to prepare
the Final Vendor Data Book (VDB) and/or Quality Record Book (QRB) in a uniform format
to enable Owner/MC and PIDEC to compile the same and furnish the Project Final
Mechanical Catalogue Books (MC Books) of the plant as a important part of project records
and archives, therefore all the vendors are requested to follow this procedure and furnish
their share accordingly.
- All drawings and documents shall be legible with good copy/print quality.
- Vendor shall ensure that the information and data included in the Final Data Book is
sufficient and will serve the purpose of such document. List and index of binders shall be
agreed between vendor and PIDEC in advance, in this regard reference shall be made
to RFD form which attached to the requisition, approved Vendor Documents Index and
Schedule (VDIS) and other quality records which shall be prepared during manufacturing
and supply as per QCP /ITP and so on.
- Maximum size of drawings shall be A1 and drawings in format A1, A2 or A3 shall be
folded to A4 size in way that title block to be on front and to be inserted in A4 size plastic
cover preferably.
- Each set of the required documents shall surely be provided in separate Binder.
- The Hard Binders shall be of White colored and shall be labeled in colored font and logo
as per Attachment No.08.(Note: a binder is a hard cover with 4 metal rings inside which
will be used to hold bunch or loose pieces of papers as shown in att. No. 08)
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 10 of 11
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
Petrochemical
Industries Design & Vendor Documents Management Procedure
Engineering Company
(PIDEC)
Doc. No.: 1231-DE-00-DC-PCJ-001 Rev.: 01
Project No. : 1231 Project No. : 214
- Upon order completion, vendor shall attend to submit one set hard copy Plus one set
CD/DVD of Final Vendor's Data Book for PIDEC's review and comment, obviously after
receiving PIDEC's approval, three (3) sets of approved Vendor's Data Books shall be
dispatched to the PIDEC's postal address and/or anywhere else that specified by PIDEC
Plus Two (2) sets CD/DVD (including same documents along with a clickable index so
that documents to be opened by clicking on index) which shall be sent to PIDEC's postal
address.
- The binders shall be packed in wooden or metallic boxes for overseas orders and strong
cardboard cartons for domestic orders to avoid damage during the seaworthy, air and/or
land transportation.
6.1 CONTENT OF VENDOR'S FINAL DATA BOOK
All Final Data Book shall be compiled in accordance with this procedure and approved VDIS
which is prepared as per "Requirements for Documents (RFD)", of each requisition plus
Quality Record Book (QRB).
6.2 QUALITY RECORD BOOK (QRB)
The vendor shall submit required numbers of copies of inspection reports, test records and
certificates, complete with identification and traceability records, when applicable, as the
Quality Record Book (QRB) in hard binders by the time specified in the purchase order as
a final documentation as described above to the attention of Owner/PMC or his assigned
representative.
This shall generally include, but not be limited to, the followings with respect to the
requisition requirements; however the final contents of QRB shall be agreed with the
Owner/Purchaser or his assigned representative:
- Table of contents (This table shall be reviewed by the Owner/MC or his assigned
representative in advance to completing the QRB)
- Copy of Inspection Release Notes signed by authorized inspector (if required.
- Manufacturer’s certificates of Conformance
- Material test certificates with the list to identify the certificates against the parts listed
below:
- All low alloy and high alloy materials including those for internal parts.
- Pressure retaining parts attachments of pressure vessels, which are directly,
welded on the pressure retaining parts, such as reinforcing pads, parts for
skirt/saddle, excluding minor parts.
- Carbon steel for low temperature services
- Special materials such as non-ASTM/ASME materials.
- Any non ASTM/ASME materials indicating equivalent ASTM material.
- Other parts and materials specified in the Requisition.
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 11 of 11
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
Petrochemical
Industries Design & Vendor Documents Management Procedure
Engineering Company
(PIDEC)
Doc. No.: 1231-DE-00-DC-PCJ-001 Rev.: 01
Project No. : 1231 Project No. : 214
- All other reports as specified in respective specification and approved inspection and
test plan.
- Welding procedure specification (WPS) with weld map for itemized pressure vessels,
tanks, heat exchangers and fired heater coils.
- Welding procedure qualification records (PQR) for itemized pressure vessels, tanks,
heat exchangers and fired heater coils.
- Welder qualification records (WQR) for itemized pressure vessels, tanks, heat
exchangers and fired heater coils and so on.
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 12 of 11
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
(ATTACHMENT NO. 1)
COORDINATION & NUMBERING SYSTEM FOR
STEEL STRUCTURE\GRATING SHOP DRAWINGS
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 1 of 4
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
1. Following settings shall be arranged with Steel structure Vendors as a minimum When
vendor’s scope is to prepare the shop fabrication drawings:
a. Define suitable steel structure connections in Tekla software based on the project standard specifications.
b. Set the quality of Materials and profiles based on design requirements in Tekla software. “Standard Profile”
or “equivalent built-up section” shall be considered based on the contract.
c. Tekla version shall be agreed upon and same version shall be used for all structures.
d. Title of Models shall be agreed. Part of model name shall be model revision (Rev00, Rev01…).
e. Type of Bolts, nuts and washers shall be defined correctly in Tekla based on the agreed standards which
is mentioned in the respective specification. The Weights shall be specified and defined correctly in Tekla.
f. All “prefixes”, “Piece tags” and part numbering system shall be defined and agreed.
g. Templates for “General Arrangement Drawing”, “Assembly Drawings”, “Single Parts Drawing” and etc. shall
be defined based on the project formats.
h. Template and kind of “Fabrication Reports” shall be specified.
i. Review and finalizing all attributes of connections particularly for special connections.
j. General and common notes for all drawings such as “General Arrangement Drawings” and “Assembly
Drawings” shall be coordinated.
k. All requirements under clause (1) shall be considered, before modeling of any structure. In special cases
and because of time limitation, only items “1.d”, “1.g” and “1.h” could be done in parallel with the modeling
of the structures. All the other items shall be finalized before modeling.
2. In this stage and after completing the model with consideration of clause “1”, vendor shall
upload the model along with its GA drawings including profile name (no part No.) ,reports
and signed check list into VDMS with consideration of following sub-clauses:
a. The signed check list shall be put in the model folder.
b. The model document shall consist of a “zip” file without any “pdf” file.
c. “GA” drawings and “Reports” shall consist of native files and “pdf” files.
d. Purpose of issue of all drawings and reports in this stage shall be “For Review”.
3. The uploaded documents and model will be reviewed and any comments on the model will
be submitted by a “tbp” (Tekla BIMSight Project) file on the model. Comments on “pdf” files
will be given in a “pdf” file format in the corresponding document location.
4. Stage “2” and “3” shall be repeated till getting the “No Comment”.
5. Fabrication just can be started after getting the “No Comment” on all respective
documents/drawings.
6. vendor shall upload the final documents in VDMS as follows:
a. Final model as only a “zip” file. This “zip” file shall consist of all drawings, reports and check list.
b. “GA” drawings as a native and “pdf” file. These “GA” drawings show all members with the item No. (e.g.
BE12, CO23…). This pdf file consist of all “GA” drawings sheets.
c. “Assembly” drawings as native (ACad) and without any “pdf” file.
d. “Single Part” drawings as native (ACad) and without any “pdf” file.
e. “Reports” as a native (word, excel…) and with single “pdf” file consist of all reports.
f. Purpose of issue of all drawings and reports in this stage shall be “For Fabrication”.
7. PIDEC will put its “No Comment” on “GA” drawings and “Reports”. Other drawings are for
information of PIDEC and if there are comments on those drawings, vendor will be informed;
otherwise no other communication is necessary.
8. Whereas, a lot of Shop Drawings shall be prepared by Vendors against Steel Structure and
Grating requisitions and all shall be reviewed and commented by Contractor (PIDEC)
through VDMS platform, therefore, following instruction is defined in order to better manage
of all concerning vendor’s documents.
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 2 of 4
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
B) All Drawings under each category shall be zipped and this zipped file shall be renamed
as follows:
VD-1231-XXX(X)-XXX-XX XXX X
a b c d e
a,b,c : as described in part 6.5
d : represent Category code as follows:
- MOD for Models
- GAD for General Arrangement Drawings
- SAD for Shop Assembly Drawings
- SPD for Single Part Drawings
- RPT for Reports
Note 1: Any document except above mentioned items such as Procedures, Plans, ITPs
and etc shall be numbered as Article No. 6.5 of procedure.
e : represent a five or six concatenated digits which two first digits show Unit
Number, three second digits and if required a set letter (e.g. A, B,…) show a
serial number .
Examples: VD-1231-740A-MOD-93151A
VD-1231-740A-GAD-93151A
VD-1231-740A-SAD-93151A
VD-1231-740A-SPD-93151A
VD-1231-740A-RPT-93151A
C) All Drawings within each zipped file except SPD drawings (Note 2) shall be renamed
as follows.
Note 2: SPD Drawings will be generated and automatically numbered by Tekla software.
VD-1231-XXX(X)-XXX-XX XXX X- XXX
a b c d e f
a,b,c,d,e : as defined in clause (B)
f : Represent the vendor drawing sequential number from 001
Examples: VD-1231-740A-GAD-93151A-001
VD-1231-740A-GAD-93151A-002
VD-1231-740A-GAD-93151A-003
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 3 of 4
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
Following check list will be used for control of works and suitability of vendor documents:
Model Name :
Project No. : Job Detailer Job Engineer Lead Engineer
OK NC NA OK NC NA OK NC NA
MODEL
1 Structure Axes Compatible w/Eng. drawings
2 Monorail/Crane beams details & stoppers
3 Base Plate Detail and types RND
OK: Applied Correctly NC: Not Correct NA: Not Applicable RND: Randomly Checking point
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 4 of 4
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
(ATTACHMENT NO. 2)
VENDOR DOCUMENT INDEX
& SCHEDULE (VDIS)
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 1 of 2
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC Page 2 of 2
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
(ATTACHMENT NO. 3)
VENDOR DOCUMENT TITLE BLOCK
AND FORMATS
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 1 of 5
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 2 of 5
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 3 of 5
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 4 of 5
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 5 of 5
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
(ATTACHMENT NO. 4)
PROJECT DOCUMENTS
TYPE & CODE
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 1 of 2
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
Doc. Doc.
Type of Document Type of Document
Code Code
Above-ground piping Plan APP Policy PLC
Analysis Report ARP Procedure PCJ
Bar Bending Schedule BBS Procedure Qualification Record PQR
Basis Of Design BOD Process Description PDS
Bill Of Quantity BOQ Process Flow Diagram PFD
Block Diagram BLD Proposal PRP
Calculation Sheet CAL Purchase Order POR
Catalogue CAT Quality Control Plan QCP
Certificate CER Quarterly Report QRP
Change Order COR Regulation REG
Commercial Bid Analysis CBA Report RPT
Company Standards CSD Requirement for Documents RFD
Construction Standard Specification CSS Requisition Control Index RCI
Contract CNT Schedule SCH
Daily Report DRP Scope Of Inspection SOI
Data Processing (2D, 3D) DPR Shipping Release Note SRN
Data Sheets DSH Single Line Diagram SLD
Design Criteria DCR Sizing Calculation Sheet CSH
Design Philosophy DPH Sketch SKT
Drawing (Exclude Plot Plan Layout/arrangement) DWG Specification SPE
Diagram (Exclude PFD/P&ID / UFD / Single Line) DIG Standard drawing SDG
Document Control Index DCI Strategy STR
Documents Index and Schedule DIS Table TBL
Engineering Standard Specification ESS Technical Bid Analysis TBA
Equipment List EQL Technical Requisition REQ
Estimation EST Temporary Delivery TMD
Fabrication Schedule FAS Test & Inspection Plan ITP
Financial Balance Sheet FBS Under-ground piping Plan UPP
Format FMT Utility Distribution Diagram UDD
Frame FRM Utility Flow Diagram UFD
Heat and Material Balance Sheet HMB Vendor Data Requirement Form VDR
Index INX Vendor List VLS
Inspection Procedure Manual IPM Weekly Report WRP
Inspection Record INR Welder Performance Qualification report WPQ
Inspection Requirement INP Welding Book WBK
Invoice INV Welding Map/Plan WMP
Isometric Drawing ISO Welding Procedure Specification WPS
Key Plan KPL Work Breakdown Structure WBS
Legend LGD Work Instruction WIN
Letter of Conformity LOC Model MOD
List LST General Arrangement Drawings GAD
Manual MNL Shop Assembly Drawing SAD
Master Document List MDL Single Part Drawing SPD
Material List MAL
Material Standard Specification MSS
Material Take Off MTO
Minutes of Meeting MOM
Monthly Progress Report MPR
Material Control Index MCI
Non Destructive Test Map/Plan NPL
Organization Chart ORC
Performance Curve PCU
Permanent Delivery PMD
Piping & Instrumentation Diagram PID
Planning Program PRG
Plot Plan / Layout / Arrangement PPL
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 2 of 2
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
(ATTACHMENT NO. 5)
VENDOR DOCUMENT HANDLING
WORK FLOW
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 1 of 2
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 2 of 2
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
(ATTACHMENT NO. 6)
DOCUMENT TRANSMITTAL FROM
PIDEC TO VENDORS
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, Page 1 of 2
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure, reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC Page 2 of 2
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
(ATTACHMENT NO. 7)
FINAL BOOK BINDER AND LABEL
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure,
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
Page 1 of 4
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure,
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
Page 2 of 4
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC:
This document with all its rights is the property of ZAFIC and must be held in confidence. No disclosure,
reproduction or other use of the document in whole or parts is to be made without the prior consent of ZAFIC
Page 3 of 4
EPs Contractor: ZANJAN UREA FERTILIZER PROJECT Owner: PMC: