CPM & PERT Analysis: Project Management
CPM & PERT Analysis: Project Management
Project Management
NETWORK TECHNIQUES
PERT CPM
-Program Evaluation and Critical Path Method
Review Technique Developed by El Dupont
- developed by the US for Chemical Plant
Navy with Booz Shutdown Project- about
Hamilton Lockheed same time as PERT
- on the Polaris
Missile/Submarine
program 1958
Finish-to-Finish
Relationship
FIGURE 6.18
Start-to-Finish
Relationship FIGURE 6.19
Combination
Relationship
FIGURE 6.20
6–9
Network Using Lag
FIGURE 6.21
6–10
PERT Planning Process - Steps
t = (a + 4m + b)/6
An activity’s completion time variance is:
2 = ((b-a)/6)2
a = the optimistic completion time estimate
b = the pessimistic completion time estimate
m = the most likely completion time estimate
PERT Example
A None 17 29 47 30
B A 6 12 24 13
C A 16 19 28 20
D B 13 16 19 16
E C 2 5 14 6
F D,E 2 5 8 5
PERT Example
PERT Example
Calculating the Probability at specific time
Probability of Project Completion