You are on page 1of 35

Project Planning and Scheduling are two core parts

of Engineering Management

Professor Shahidul Islam . Planning and Scheduling Sem 2, 2020/2021 1


03/28/2021 2
03/28/2021 3
03/28/2021 4
03/28/2021 5
03/28/2021 6
03/28/2021 7
03/28/2021 8
03/28/2021 9
03/28/2021 10
03/28/2021 11
03/28/2021 12
03/28/2021 13
03/28/2021 14
03/28/2021 15
03/28/2021 16
03/28/2021 17
03/28/2021 18
03/28/2021 19
03/28/2021 20
03/28/2021 21
Project Planning and Scheduling are two core parts
of Engineering Management

The Planning and Scheduling of engineering Activities


can be divided into ten (10) major steps

Professor Shahidul Islam . Planning and Scheduling Sem 2, 2020/2021 22


Project Planning and Scheduling

Establish and agree the scheduling assumptions, especially a clear


Step 1 set of scheduling objectives For example, product quality grade, time
and cost limitations that will affect activities.

Overall strategy for the project are:

 Methodology or technology to be used and how it will be applied


 Sources of resources and their competence, or training needs
 Working hours, holidays, other interruptions Preparing a Schedule

03/28/2021 23
Project Planning and Scheduling
Step 2
 Identify each logical work area as reflected in the WBS and the
activities associated with each

 Make sure that all the necessary major activities and tasks have
been included to create the required intermediate and final
deliverables

 If you have too many activities consider using "hammocks” to group


discrete tasks as one activity Preparing a Schedule Project
Hammock - An aggregate or summary activity. All related activities
are tied as one summary activity and reported at the summary level.

03/28/2021 24
Project Planning and Scheduling

Step 3 Establish the project's natural or "inherent" logic

 Some projects have very clear logic while others provide


more options depending on resources or the nature of the project
or other circumstances
 Nevertheless, there is almost always a preferred way of doing things
 It is worth spending time to look for it
 Work the activities from the beginning to the end
 Then work from the end back to the beginning! Preparing a Schedule

03/28/2021 25
Project Planning and Scheduling

Step 3 continued

 Develop a flow chart or logic diagram – AKA a network diagram –


paint a picture of the schedule

 Use the work breakdown structure as a “To do” list


 Which of these items must be done first? –Label that item “A”
 What must follow next? –Label those B, C, D, etc
 Now ask what can be done concurrently with A, B or C?
 Assemble a simple logic diagram arranged from left
to right Project Planning and Scheduling with Logic Diagram

 Use large sheets of paper, cards on the wall or sticky notes


 More than 30 activities, separate project into two phases

03/28/2021
26
Project Planning and Scheduling

Incorporate any "Management Choice" logic, i.e., dates or


Step 4 sequence mandated by management

 These may or may not make sense


 Make sure that management understands the implications of
imposed management decisions
  Adjust the logic accordingly
 Always double check that the schedule logic is sound
 Steps 3 and 4 establish the schedule network configuration Preparing
a Schedule

03/28/2021 27
Planning and Scheduling

Step 5 Estimate the duration of each activity or task

 Pay particular attention to this step since the whole schedule will depend
upon it
 Use all available sources of information
 Be careful with published information since the circumstances of your
project may be different
 Some tasks will still be difficult to estimate, seek expert help, use ranges
 Document areas of high uncertainty (risk)
 Always aim for the “most likely" duration – don't build in contingency at
every step, or the project will not fly
 Always be realistic – you can refine on the second pass and make
appropriate contingency allowances later Preparing a Schedule Project
Planning and Scheduling

03/28/2021 28
Planning and Scheduling

Step 5 ContinuedEstimate the duration of each activity or task

 Pay particular attention to this step since the whole schedule will
depend upon it
 Use all available sources of information
 Some tasks will still be difficult to estimate, seek expert help, use
ranges
 Document areas of high uncertainty (risk)
 Always aim for the “most likely" duration – don't build in
contingency at every step, or the project will not fly
 Always be realistic – you can refine on the second pass and
make appropriate contingency allowances later Preparing a
Schedule Project

03/28/2021 29
03/28/2021 30
Project Planning and Scheduling

Step 6 Continue Examine the values of (ES-LS) and (EF-LF)

 The string of activities where these values of (ES-LS) and (EF-LF)


are zero is the longest path through the network
 This is known as the Critical Path
 Where the values are positive indicates that there is Float for
those activities Preparing a Schedule.

Note :
Detail on CPM and PERT will be discussed and carried out practice at week 7

03/28/2021 31
03/28/2021 32
03/28/2021 33
03/28/2021 34
03/28/2021 35

You might also like