Overview
2
Asset Integrity Strategy
• Strategy Adopted is Similar to Miskar Asset Strategy
• Compliance with BG standards and guidelines
• Compliance with UK (SCR / PFEER/PSSR) and Tunisian
Regulation
• Identification of Safety Critical Elements through SCR and
PFEER
• Identification of SCE’s performance standards
• Establishing a maintenance and inspection Plan
• Appointment of technical Authority for each SCE’s
• Appointment of ICP for pressure system, pipeline and sub sea
Structure
• Performing maintenance and inspection plan
• Checking compliance with performance standards
• Putting in place correction actions if required
PFEER: Prevention of Fire and Explosion, and Emergency Response Regulations
SCR : Offshore Safety Case Regulations
3
Status of Key Asset integrity Documentation
4
Status of Key Asset integrity Documentation
5
Status of WSoE
6
Pressure System Inspection
7
Status of Base line Survey
8
Pressure Vessels Categorisation
Number
83
73
54
41 34 46
26
17 15 19
8 7
2 8 7 0 0 0
9
Pressure Vessels Inspection Plan
10
Initial SD plan
Hasdrubal - SD PLAN
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
Miskar Asset
Contractual Shut Down 5 Days 5 Days 14 Days 5 Days 5 Days 14 Days 5 Days 5 Days 14 Days 5 Days 5 Days 14 Days 5 Days
Activities
Hasdrubal Asset
IP 12 REQUIREMENTS IVI
Quarter Q4 Q1 Q1 Q3 Q1
Contractual Shut Down 14 Days 5 Days 5 Days 14 Days 5 Days 5 Days 14 Days 5 Days 5 Days 14 Days 5 Days 5 Days
key
11
Offshore Structure Inspection Plan
July/ 2011 X
July/ 2013 X
July/ 2014 X
July/ 2018 X
July/ 2017 X
July/ 2023 X
• Major Survey: Detailed visual inspection and wall thickness of the topside and
Remote Operated Vehicle (ROV) of the subsea structure
• Intermediate Survey: Detailed visual inspection of the topside of the structure
12
Multiphase Pipeline inspection program
Year
Area Covered: Details of examinations to be carried out
Within 6 months
Pipeline Internal Inspection ILI In-Line Inspection of operation
2010
13
Export Pipeline inspection program
Year
Area Covered: Details of examinations to be carried out
Within 2
CIPPS on buried pipeline from insulation joint
years of
Export Pipeline within Hasdrubal and the STEG site at Ben
operation
Sahloun.
2011
Within 2
DCVG on buried pipeline from insulation joint to years of
Export Pipeline
boundary fence within Hasdrubal plant. operation
2011
Within 6
months of
Export Pipeline In line inspection
operation
2010
14
Business Plan
• Business Plan
15
Corrosion monitoring Requirements
• Platform
– Platform top side are not equipped with corrosion monitoring
systems, process pipe work and vessels are mainly corrosion
resistant material to Hasdrubal conditions (316L, DSS and alloy 625
Clad)
• Pipeline
– Corrosion coupons and probes are erected in the terminal inlet
facility to monitor the pipeline corrosion.
– Daily download of the probes data is required in the start up period in
order to monitor the performance of the corrosion inhibitor. Any
corrosion rate more than 0.1mm/year have to be reported.
– Loss weight Coupons are to be retrieved and analysed initially every
3months
– Bio-probe assembly to be retrieved and tested every 2months
– Iron count on weekly basis
– Pipeline Pigging is required on weekly basis until the corrosion rate
and the effectiveness of the inhibitor has been demonstrated
16
Corrosion monitoring Requirements
• Plant
– Probes and coupons are installed where corrosion is likely to
take place (mainly due to process upset)
– Weekly download of probes data is required in the start up
period. Any corrosion rate more than 0.1mm/year have to be
reported
– Loss weight Coupons are to be retrieved initially every
3months
– Bio-probe assembly to be retrieved and tested every 2months
• Gabes
– Gabes site is not equipped with corrosion monitoring systems,
Butane and Propane considered non corrosive media
17
List of major AI contracts
18
Issues / Concerns / Challenges
• Pipeline inspection
– CRA section of the pipeline
– Wall thickness of spools using divers( high cost /Access/Periodicity)
– Performance of the Corrosion Inhibitor (in presence of high CO2
content 4%)
• Base line inspection
– Scope will not be completed before start up
– Completion after start up
• Shut downs
– Synergy with Miskar asset
– Limitation of the number of day due to contractual agreements to
undertake the scope of work and specially in 2019
– High number of hydrotest waivers to be requested (26 identified)
19
THANK YOU