Professional Documents
Culture Documents
OF
TRANSFORMERS AND REACTORS
A.K Goel,
Sr. DGM (HRD)
arunkgoel@powergrdindia.com
Ph-9599192366
07/09/2021 1
Transformer
07/09/2021 2
PRE-COMMISSIONING PROCEDURES -Purpose
Commissioning Team-
07/09/2021 3
Contd.
Witness Pre-Commissioning tests after erection of
individual equipment as per requirement of guidelines
issued by Corporate Asset Management or in line with
manufacturer's recommendation and test charging.
Investigate failure of equipment during test charging,
declare commencement of trial operation and evaluate
guaranteed test results and recommend acceptance as
may be provided in the contract.
List out deviations/ exception/ incomplete work, for
acceptance/ rejection. Proper documentation also to be
ensured by the Commissioning team based upon the
observations for the above for future reference
07/09/2021 4
Contd.
The Team shall also go through the factory test reports.
If such tests have been repeated during pre-
commissioning, the Team shall list out deviations, if
any, in the results of pre-commissioning tests with
respect to the factory tests.
07/09/2021 5
PROCESSES INVOLVED
07/09/2021 6
SAFETY
All personals should be apprised of safety procedures
Personnel protective equipment
Warning signs
Safety barriers
Fully equipped and functional fire fighting system
07/09/2021 7
CHECKS AFTER THE RECEIPT OF MAIN TANK AT SITE
07/09/2021 8
RECEIPT AND STORAGE OF
MATERIALS AT SITE
Unpacking without damaging
Any damaged or missing component to be intimated to the
manufacturer
Materials repacked and stored if commissioning not
immediate
Fragile instruments indoor storage eg:- oil level gauge,
temperature indicators etc.
Packing cases to be placed on suitable supports to allow free
flow of air no water logging, easy for inspection and
handling/transportation,
Proper drainage, no component gets submerged
07/09/2021 9
STORAGE OF MAIN TANK FOR LESS
THAN THREE MONTHS
Main tank filled with nitrogen or dry air
Daily check of pressure
If drop in pressure found, dew point to be taken
If drop in dew point, fresh nitrogen or dry air has to be
filled
Leak has to be detected and tightened
07/09/2021 10
STORAGE OF MAIN TANK FOR MORE
THAN THREE MONTHS
Filled with processed oil ( BDV > 70KV, moisture
content < 5ppm)
BDV AND water CONTENT TESTED EVERY
THREE MONTHS
If value beyond limits, oil filtration done
07/09/2021 11
INSULATING OIL
Oil in 209L drums or oil tanks
Proper record of drums to be maintained
To be checked for free moisture and appearance
Oil sample to be sent to nearest lab for testing BDV >
07/09/2021 12
SAMPLES FROM DRUM
07/09/2021 13
OIL SAMPLING FROM DRUMS
Oil drums vertical with lid upwards for 24 hours
Clean the area around lid
Use glass or brass tube to sample the oil
Discard first two samples
Suitable receptacle preferably glass bottles cleaned
07/09/2021 14
INTERNAL INSPECTION
PRECAUTIONS WHAT IS TO
DONE
07/09/2021 15
PRECAUTIONS DURING INTERNAL
INSPECTION
Along with manufacturer’s representative
Dry and sunny weather
Dry air should be used if main tank filled with nitrogen
Avoid any foreign materials
Loose materials should be removed from pockets
Protective clothing and shoes
Tools securely fastened
An inventory of all materials taken inside tank to be
maintained and checked before closing of inspection
cover
07/09/2021 16
07/09/2021 17
07/09/2021 18
07/09/2021 19
INTERNAL INSPECTION INCLUDES
Removal of any shipping blocking or temporary
support.
Examination for indication of core shifting.
Tests for unintentional core or core clamp grounds.
Visual inspection of windings, leads, and connections
foreign material.
07/09/2021 20
Erection of Transformer
07/09/2021 21
PRECAUTIONS DURING ERECTION-1
of 2
Minimize exposure of active parts (core+coil)
Presence of dry air ( dry air generators or dry air
cylinders )
Transformer sealed off after working hours
If tank has nitrogen then first vacuum then dry air
(<30 mbar)
07/09/2021 22
PRECAUTIONS DURING ERECTION-2
of 2
07/09/2021 23
CONDITIONS OF EXPOSED FOR OIL
FILLED TRANSFORMERS
Oil is drained out below the inspection covers
Other exposure activities are as below:
1) bushing erections
2) jumper connections of bushings
3) fixing bushing turrets
4) core insulation checking (in case the checking point not accessible
outside)
5) buchholz relay pipe work fixing on cover
6) gas release pipes/equalizer pipe fixing
7) entering inside the tank for connections/inspection etc
07/09/2021 24
FINAL TIGHTNESS TEST WITH
VACUUM
Before oil filling, leakage test is a must.
Evacuate transformer from top of tank till pressure < 50mbar.
Vacuum stopped.
released simultaneously
07/09/2021 25
VACUUM HOLDING
After passing leakage test, vacuum maintained in tank
for the duration as mentioned below
07/09/2021 26
OIL FILLING-1 of 3
Transfer oil from drums to tanks for filtration
Filtration done
Oil parameter testing :
1. Break down voltage (bdv) : 70kv (min.)
2. Moisture content : 5 ppm (max.)
3. Tan-delta at 90 °c : less than 0.01
4. Interfacial tension : more than 0.035 n/m
Nitrogen filled transformer to be oil filled under
vacuum
07/09/2021 27
OIL FILLING-2 of 3
Oil filled from bottom valve
Oil fill speed in main tank < 5klph
Oil filled in OLTC at atmospheric pressure
Oil filled in cooler banks without vacuum at
atmospheric pressure
Care must be taken not to pressurise the cooler bank
07/09/2021 28
OIL FILLING-3 of 3
Upon completion, open the top cooler isolating valve in
order to equalize the pressure in the cooler with the
transformer tank
Before filling oil into the conservator, the air cell/
07/09/2021 29
HOT OIL CIRCULATION
Oil extracted from bottom valve in main tank and
poured in from top valve
Oil heated in filter machine till 60 0c. Above 70 0c oil
oxidises
Circulation done for at least 2 times of tank volume.
(At freezing ambient temperature the circulation time is
07/09/2021 30
OIL PARAMETERS BEFORE
CHARGING
Break down voltage (BDV) : 70 KV (min.)
Moisture content : 5 ppm (max.)
Tan-delta at 90 °c : 0.01 (max.)
Total gas content : < 1%
Resistivity at 90 °c : 6 x 10 ohm-cm (min.)
Interfacial tension : 0.035 n/m (min.)
*Oxidation stability (test method as per iec 61125 ,method c, test duration:
07/09/2021 31
CONDITIONS FOR
TRANSFORMER/REACTOR TO BE WET
07/09/2021 32
PROCEDURE FOR DRYING OUT OF WET
TRANSFORMER/REACTOR-1 of 2
Carefully watched and recorded
Fire fighting ready as we deal with heat and inflammable oil
All openings of main tank for conservator, cooler banks,
07/09/2021 33
PROCEDURE FOR DRYING OUT OF WET
TRANSFORMER/REACTOR-2 of 2
If dew point ok then oil filling done else
Vacuum done till pressure of 1-5 tor for 48 hrs with
07/09/2021 34
AFTER TRANSFOMER/REACTOR IS READY
WITH OIL FILLING AND CIRCULATION,
STANDING TIME IS GIVEN AS GIVEN IN
THE TABLE AND DURING THIS FURTHER
TESTS ARE PERFORMED
07/09/2021 35
PRECOMMISSIONING TESTS-1 of 2
Core insulation test
Earth pit resistance measurement
Insulation resistance (IR) measurement
Capacitance and tan delta measurement of bushings
Capacitance and tan delta measurement of windings
Turns ratio (voltage ratio)measurement
Vector group and polarity
Magnetic balance test
Floating neutral point measurement
07/09/2021 36
PRECOMMISSIONING TESTS-2 of 2
Measurement of short circuit impedance
Exciting/magnetising current measurement
Operational checks on OLTC
Tests/check on bushing current transformers (BCTs)
Operational check on protection system
Stability of differential, REF of transformer/reactor
Frequency response analysis measurement (FRA)
Winding resistance measurement
Dissolved gas analysis (DGA)
07/09/2021 37
CORE INSULATION TEST
Done when the transformer/reactor is still on trailer, also
done when integrity of core insulation is affected, in
charged transformers when DGA indicates ethane,
ethylene and methane
Disconnect the three terminals from each other ( core
clamp, core lamination and ground)
Test the insulation between core clamp to ground and core
lamination to ground at 1kv ( should be > 10Mohm at 60
seconds )
Connect the three terminals once again (normal condition)
07/09/2021 38
EARTH PIT RESISTANCE
MEASUREMENT
An earth tester kit is used
Pit earthing connection removed from main grid
Measurement by three point method
Working of earth tester……
Two spikes at a distance of 25m and 50m are placed in one line
There is a dc generator
Dc current converted to ac current using rectifier and fed to
spike to prevent electrolytic effect due to dc current
Earth resistance is displayed which should be less than 1ohm, if
not the treatment with salt and charcoal is to be done
07/09/2021 39
INSULATION RESISTANCE
MEASUREMENT-1 of 3
Tests insulation between winding and tank and between
windings (rest of the windings being earthed)
Neutral should be disconnected from earth
A 5KV Insulation Tester is used
07/09/2021 40
INSULATION RESISTANCE
MEASUREMENT-2 of 3
07/09/2021 41
INSULATION RESISTANCE
MEASUREMENT-3 of 3
Two measuring factors, dielectric absorption
coefficient or index (DAI) & polarization index (PI)
DAI=RATIO OF IR at 60 secs to IR at 15 secs, it
follows:-
07/09/2021 42
CAPACITANCE AND TAN DELTA
MEASUREMENT OF BUSHINGS
Measurement of loss in insulation of bushings
Dissipation factor or loss factor (tan delta)= ratio of resistive
current to capacitive current
Kit used= 10KV or 12 KV fully automated capacitance and tan
delta measurement kit
C1 measurement in UST mode at 2KV and 10 KV (UST=
ungrounded sampling test mode)
C2 in GSTg at 1KV (grounded sampling test with guard
mode )
Limit is 0.5%
WHAT IS C1 & C2 ?.....
07/09/2021 43
CAPACITANCE AND TAN DELTA
MEASUREMENT OF WINDINGS-1 of 3
The combination for C & tan ä measurement of
winding is same as that of measurement of IR value.
07/09/2021 44
CAPACITANCE AND TAN DELTA
MEASUREMENT OF WINDINGS-2 of 3
Winding combination for auto transformer.
07/09/2021 45
CAPACITANCE AND TAN DELTA
MEASUREMENT OF WINDINGS-3 of 3
07/09/2021 46
TURNS RATIO MEASUREMENT
Kit used= Automatic Transformer Turns Ratio Meter
07/09/2021 47
VECTOR GROUP AND POLARITY-
Single Phase Transformers
Purpose:- Paralleling of transformers
07/09/2021 48
VECTOR GROUP AND POLARITY-
Three Phase Transformers
Purpose:- Paralleling of transformers
07/09/2021 49
MAGNETIC BALANCE TEST-1 of 2
Purpose:- Detect damage to winding during
transportation
07/09/2021 50
MAGNETIC BALANCE TEST-2 of 2
07/09/2021 51
FLOATING NEUTRAL POINT
MEASUREMENT
Purpose:- Detect fault in winding
07/09/2021 52
MEASUREMENT OF SHORT CIRCUIT
IMPEDANCE
Purpose:- detect winding movement that usually
occurs due to heavy fault current or mechanical
damage during transportation or installation since
dispatch from the factory.
07/09/2021 53
EXCITING/MAGNETIZING CURRENT
MEASUREMENT
Purpose:- It is performed to locate defects in the magnetic core
structure, shifting of windings, failure in turn to turn insulation or
problem in tap changers
Change in reluctance of magnetic circuit thus affecting the current required
to establish flux in the core.
Done before all DC tests ( DC may cause saturation of winding)
Single phase voltage upto 10KV applied on one winding while the rest of
the winding are open
07/09/2021 54
FREQUENCY RESPONSE
ANALYSIS(FRA)
Purpose:- To assess the mechanical integrity of the
transformer which may get disturbed due to
transportation shocks.
Done after erection and oil filling. Results compared with
factory value
The FRA signatures should be analyzed in conjunction with
Impact Recorder readings
07/09/2021 55
07/09/2021 56
WINDING RESISTANCE
MEASUREMENT-1 of 2
Purpose:- It is carried out to calculate the I2R losses and to calculate
winding temperature at the end of a temperature rise test. It is also
done at site to ensure healthiness of a transformer that is to check
loose connections, broken strands of conductor, high contact resistance
in tap changers, high voltage leads and bushings etc.
The winding resistance shall be preferably done when the difference in the
top and bottom temperature of the winding (temperature of oil in steady-
state condition) is equal to or less than 5 °C.
The winding resistance should preferably be carried out last after
completion of all other LV tests, as after this test core gets saturated
and tests like magnetizing current, magnetic balance etc. carried out
after winding test may be affected and indicate a misleading results,
if the core is not de-magnetized before carrying out these tests.
07/09/2021 57
WINDING RESISTANCE
MEASUREMENT-2 of 2
Measurement done using Automatic Kit
At all taps in forward and reverse direction, resistance
measured between HV to IV winding
At normal tap between IV-N winding
In LV winding between phases
All the readings taken converted to reading at 75 0C with
formula
07/09/2021 58
OPERATIONAL CHECKS ON OLTC
Purpose:- Tap changer functioning properly
Manual operation of drive. Tap position in drive and TC should be same.
Motor drive push button test. Should get switched off automatically after
one switching operation
Changeover from 9b to 10 and vice versa requires high torque. Tap
changer end position to be checked to see there is no slipping over causing
failure
Continuity of winding at all taps to be checked. At no point should the
voltage should indicate zero
With the transformer energised at rated voltage and frequency but on no
load, one complete cycle of operation to be taken
07/09/2021 59
TESTS/ CHECKS ON BUSHING CURRENT TRANSFORMERS (BCTs)-1 of 2
07/09/2021 60
TESTS/ CHECKS ON BUSHING CURRENT
TRANSFORMERS (BCTs)-2 of 2
Magnetising Curve Performance:- (Not done for metering
core)
Purpose:- To check that the current transformer is
working in the linear region of its magnetising curve.
Various values of Knee point voltage (0.25, 0.5,0.75, 1, 1.10)
applied to primary and then secondary current measured to
see the linear relationship of Voltage and current. It should
not saturate even at 1.1 Knee Point voltage
07/09/2021 61
DISSOLVED GAS ANALYSIS OF OIL
SAMPLE
07/09/2021 62
OPERATIONAL CHECKS ON
PROTECTION SYSTEM
Breather silica gel is blue in Main Tank, OLTC
MOG level ok
Marshalling Box and other kiosks OK
Valves OK
Checks on Cooling System such as (1) Checks on cooling fans-rotation,
speed & Control (Manual /temp /load) setting checks (2) Checks on
Cooling pumps- rotation, vibration/noise, oil flow direction
OTI&WTI check, calibration, cooler control, alarm, trip settings
Check on gas actuated relays such as PRD, Buchholz relay, Oil Surge
Relay
Contact Resistance Measurement of Terminal connectors
Checks on Transformer/ Reactor protection (differential, REF, Over-
current & stability tests etc.)
07/09/2021 63
RESTRICTED EARTH FAULT
PROTECTION-1 of 3
Purpose:- To detect faults within the
Transformer/Reactor
07/09/2021 64
RESTRICTED EARTH FAULT
PROTECTION-2 of 3
Two ways to conduct: (1) through Primary test Tap (M point)
if available (2) using actual earthing if M point not available
Through Primary Test Tap
Measure the spill current in REF relay which should be nearly zero.
Switch off Current Injection.
Reverse the polarity of R phase Bushing CT and again start Current
Injection.
Appreciable spill current will appear in REF relay.
Repeat the same procedure for Y and B phases and note down the
results.
This test has to be performed from both HV side & LV side w.r.t.
Neutral.
Testing of Reactor will be done similarly
07/09/2021 65
RESTRICTED EARTH FAULT
PROTECTION-3 of 3
Primary test tap not available
Apply 440V three phase voltage at three phase bushing of H.V. side with
the help of three phase variac.
Earth the R phase of the LV side (through isolator earth switch or
discharge rod).
Measure the spill voltage (in mV)/ spill current (in mA) at REF relay
which should be nearly zero.
Reverse the polarity of R phase Bushing CT and again switch on 440V
supply.
Appreciable spill voltage/ current will appear in REF relay.
Repeat the same procedure for Y and B phases and note down the results
in formats.
.
Testing of Reactor will be done similarly
07/09/2021 66
CHECK LIST FOR ENERGISATION OF
TRANSFORMER/ REACTOR-1 of 2
Release air at the high points, like oil communicating bushings, buchholz
petcock, tank cover and the cooling devices including headers, radiators,
pumps, expansion joints etc. of the transformer. Air release should be resorted
from low points to high points.
Check tightness
Check that the valves are in the correct position
Silica gel in breather is blue and oil cup is fill with oil
CC, CL properly grounded
Check oil level in main tank and OLTC conservators, bushings
Connection of terminal connectors
Bushing CT terminal properly shorted and earthed
Neutral bushing earthed
Tan delta test taps earthed
07/09/2021 67
CHECK LIST FOR ENERGISATION OF
TRANSFORMER/ REACTOR-2 of 2
Tap position should be same at control cubicle and the tap head
Step by step operation- local and remote electrical operation as well as manual operation and parallel
operation, if any
Electric and mechanical limit switches and protective relays
Oil parameter results should conform to the limits mentioned
Check OTI and WTI settings
Ensure oil in thermometer pockets as well as OTI and WTI pockets
Installation of buchholz relay, Oil surge relay, PRD
Check Insulation resistance of auxiliary circuit at 2KV
Check the earthing of main tank and cooler banks at two different places
Measure the supply of the auxiliary circuits
Check the direction of installation of oil pumps
Check the direction of rotation of the pumps and fans
Check the working of the oil flow indicators
Check the setting of the thermal overload relays, heating and lighting of cubicles
Check the protection of the Transformer/reactor
07/09/2021 68
POST COMMISSIONING CHECKS/TESTS
FOR TRANSFORMERS AND REACTORS
07/09/2021 69
Thanks
07/09/2021 70
CHARGING OF
TRANSFORMER/REACTOR
Just before charging, an oil sample has to be taken for DGA, BDV, and
moisture measurement
The equipment charged from incoming side whether 400 or 220 KV on no
load
Initial Magnetising current is very high depending upon the moment of cycle
Transformer should be kept on no load for 12 hours
During this time, vibrations, abnormal cracking noise, etc. are to be observed
After that it may be checked for gas collection.
After successful charging, performance of transformer / rector should be
checked under loading; OTI/WTI readings should be monitored for 24 hours
and ensured that they are as per loading.
DGA samples may be sent as per Standard practice (after 24 hrs of
energizing, one week, 15 days, one month and three months after charging,
thereafter as per normal frequency of 6 months ).
07/09/2021 71