Professional Documents
Culture Documents
Transm
ission G
rid
Reliably:
Alternative paths must be available in case of single-element (lines,
transformers…) failure.
Efficiently:
Grid structure should avoid the creation of bottlenecks and power
should flow as directly as possible from the generators to the loads.
ƒ (Hz)
– +
Load Power
Consumption Generation
Inductance L H
Capacity C F
jXL=j·ω·L=
Reactance XL or X XL∠+90° Ω XL·I -90° XL·I² Var
=j·2·π·ƒ·L
Capacitance XC or X jXC=-j/(ω·C) XC∠-90° Ω XC·I +90° XC·I² Var
Z=(R²+X²)½
Impedance Z Z=R+jX Ω |Z|·|I|=Z·I -arctan(X/R) Z·I² VA
∠arctan(X/R)
Y=Z-1=
Admittance Y Y=Z-1=… S
=G+jB=…
Conductance G G=R/(R²+X²) S
Susceptance B B=-X/(R²+X²) S
Supplier/Generator Consumer/Load
Circuit Reactive (Q)
(I leads U) (I lags U)
Element
Ui ⋅ U j δij = δi - δj
Pij ≈ ⋅ sin(δ ij )
X ij
Then ⇒ Reminder:
U i2 U i ⋅ U j • A* is the conjugate of A;
Qij ≈ − ⋅ cos(δ ij ) • If A=A∠α, then A*=A∠-α
X ij X ij
Ui ⋅ U j
⋅ sin(δ ij )
ij ·I
Pij ≈
j·X
X ij δij Uj R
θ i j ·I
φ I
The lower the value of δij, the higher the system power
transfer margin and, thus, the better the system stability;
The higher the value of θ, the higher the amount of
reactive power to be produced at the source;
The higher the value of φ, the worse the power factor of
the load due to excessive reactive power consumption at the load site.
ANNEX
(kV)
Line Cable Line Cable Line Cable
ij ·I
j·X
S = √(3)·UL-L·IL δij Uj R
θ i j ·I
P = √(3)·UL-L·IL·cos(θ) φ I
Q = √(3)·UL-L·IL·sin(θ)
Power Transfer:
Ui Uj
Pij ≈ Ui·Uj·(1/Xij)·sin(δij) Zij
Qij ≈ Ui²·(1/Xij)-Ui·Uj·(1/Xij)·cos(δij) Sij
Maximum Power Transfer:
Ui = |Ui|∠δi
Ui²/(2·Xij) (Uncompensated)
Uj = |Uj|∠δj
Ui²/(Xij) (Compensated) δij = δi - δj
Zij = Rij + jXjj
23 Flexible Transmission Grids – Part 1: Fundamentals and Main Challenges of Modern Grids 23
Training Structure
Rotor-angle instability
mitigation: J·α(t) = Tmec(t) - Te(t)
Ui ⋅ U j
Pij ≈ ⋅ sin(δ ij )
X ij
• Compensation possible by
injecting reactive power at j.
Ui Uj
Greater management and control of transmission Xij
power flows:
Increased transmission capacity; Sij
Increased voltage stability margins.
Main types of classical compensation: Ui = |Ui|∠δi
Shunt: Uj = |Uj|∠δj
Regulates nodal voltage modules;
(Ui or Uj) δij = δi - δj
Uses Phase-Earth nodal reactances.
Inductances (low load) or Capacities (high load).
Series:
Ui ⋅ U j
Reduces Xij and δij resulting in increased dynamic
stability of the grid; Pij ≈ ⋅ sin(δ ij )
Uses capacitors.
X ij
(Overcharged transmission lines.)
Ui Uj
Xij
Voltage regulation
through shunt reactive power compensation:
Phase angle control Sij
through phase shifting:
SVC: Static VAR Compensator
STATCOM: STATic Synchronous COMpensator
PST: Phase Shifting Transformer
Ui = |Ui|∠δi
Uj = |Uj|∠δj
U i .U j δij = δi - δj
Pij ≈ . sin ( δ ij )
X ij
Impedance modification
through series reactive power compensation:
Ui Uj
Xij
Maximum Theoretical Power
Transfer: Sij
Without reactive power
compensation: Ui = |Ui|∠δi
Uj = |Uj|∠δj
1 U i2
U j = U i ⋅ cos(δ ij ) ⇒ max{Pij } = ⋅
δij = δi - δj
2 X ij
Ui ⋅ U j
With reactive power compensation: Pij ≈ ⋅ sin(δ ij )
X ij
U i2
U j = U i ⇒ max {Pij } =
X ij
ij ·I
R XL Lj
j·X
Sij δij Uj R
θ i j ·I
2·XC 2·XC φ I
Ui Um Uj Ui = Um = U j = U
R/2 XL/2 R/2 XL/2 Lj X L = X ij
U2 δ
2·XC Sij Ideal
Sij 2·XC Pij ≈ 2 ⋅ ⋅ sin ij
Compensator X ij 2
Note:
value R and
in this XL assumed to have the same ohmic
example
Active Power available at Load
80% U Uj
6060 80%
70%
value in this example
Ui i XXijij
Uj
70%
2
SSij P(X
PP )==EU
(XL= EUs2 i/²/(X
/ (2)ijX))L)
5050
60%
60% ij
max
Pmax Max
MaxL)= s i²/(X (2 X
ij L Est
Est
50%
50%
4040
40%
40% 2
Ouest
Ouest
PP == EU
EU
P (R)= 2²/(4R(4R)ij))
PcPc Pmax
Max
max
Max(R)= //(4R)
ssii²/(4R ij
30%
30%
3030
20%
20%
60%
60% Pmax(X
60% PMax
Pmax(X
60% PMax L) L
)
EjRjRincrease
U
E increase
2020
10%
10% 19%19%
19%
19% PP
Pmax(R)
Pmax(R)
Max
Max
0%0%
44 Flexible Transmission Grids – Part 1: Fundamentals and Main Challenges of Modern Grids 44
Reactive Power Compensation
Series Compensation
Ui Uj Ui Uj’ Uj
R XL Lj R XL XC Lj
Sij Sij Series
Compensation
Ui
L ·I
Ui
j·X
δij Uj R δij Uj
θ L ·I
φ θ φ
C ·I
I Ui - Uj I Ui - Uj
j·X
L ·I
R·
L I
j·X
Uj’
C
ij C
1.00
0.90
Ui
Load Voltage Uj (pu)
0.75
Pj @ 0.9 pf
(lagging)
Uj
0 20 40 60 80 100
Pj (% PMax)
Bypass Varistor
Capacitor Bank
Capacitor Bank
Bypass Varistor
Damping Reactor
Spark Gap
Series Capacitor
Spark Gap
Composite Insulator
Damping Reactor
Bypass Switch
47 Flexible Transmission Grids – Part 1: Fundamentals and Main Challenges of Modern Grids 47
Reactive Power Compensation
SCS Experience in Chile
Customer: Translec.
Scope: 500 KV substations (S/S): * SCS stands for Series Capacitor System.
1 new S/S at Charrua;
Santiago
1 S/S extension at Ancoa;
Pacific Ocean
1 S/S modification at Alto Jahuel; Alto Jahuel
+ Four 500 kV SCS* Units:
Ranging 227- 392 MVar.
+ All SCS integration studies:
TOV, TRV, relay settings, stability…
Argentina
Completion: 2004; 2x 500kV lines
Note: Extremely demanding seismic design.
Ancoa
2x 500kV lines
Charrua
Ralco
48 Flexible Transmission Grids – Part 1: Fundamentals and Main Challenges of Modern Grids 48
Reactive Power Compensation
Summary
Shunt Compensation:
Many possibilities:
Load side;
Generation side;
Midpoint.
May be accomplished either by inductances or capacities:
Shunt inductances for no-load or light load;
Shunt capacitors for heavy load.
Series Compensation:
Uses series capacitors to:
Improve voltage profile and dynamic stability;
Increase theoretical transmission capacity;
Overcompensation may lead to sub-synchronous resonance.
Two Types:
HVDC = High Voltage Direct Current (< 500 kVdc);
UHVDC = Ultra High Voltage Direct Current (> 500 kVdc);
Two technologies:
LCC – Line Commutated Converter (Classical);
VSC – Voltage Source Converter.
VSC: Transistor
Converter
Converter
Transformer
Uses transistors: +
Can be switched on/off at high Vdc
speed; _
53 Flexible Transmission Grids – Part 1: Fundamentals and Main Challenges of Modern Grids 53
Training Structure
AC Issues:
Economic:
Expensive overhead transmission lines;
Need of reactive power compensation.
Technical:
Limited maximum length of underground/under water cables;
Unable to perform asynchronous interconnections;
Stability issues difficult to handle;
High losses;
Difficult to stop the spread of cascading blackouts.
Cable schemes:
Submarine > 40 km; Break Even
DC Distance
Underground > 40 km. DC
Converter
Stations AC
Back to back:
When synchronisation
of AC connections is AC
Stations
impossible;
Transmission
Frequency conversion: Distance
- e.g. 50 Hz to 60 Hz.
Rectifier Inverter
Asynchronous AC
Back to Back Vdc
Idc
network interconnection.
F F
Rectifier Inverter
DC Line
F F
Point to Point
Rectifier Inverter
Receiving
End
Long
submarine/underground
Vdc
cables (> 40 km).
Idc
e.g.: Offshore wind farms and
F F
islands.
59 Flexible Transmission Grids – Part 1: Fundamentals and Main Challenges of Modern Grids 59
DC Transmission Systems
Going for UHVDC
Requirements:
Efficient & cost-effective 3500
Transmission losses
transmission of very high
Line cost
levels of power which is 3000
Station cost
generated far from the load 2500
centres:
2000
e.g.: Hydro, coal, nuclear.
MUSD
1500
it significantly reduces:
0
765kV AC 500kV DC 800kV DC
Overall investment cost;
Transmission of 6400MW over 2000kM
Transmission losses; Estimate of evaluated costs
* * * *
⇔ S ij = U i ⋅ U i ⋅ Y ij − U i ⋅ U j ⋅ Y ij ⇔ δij = δi - δj
⇔ S ij = U i2 ⋅ Yij ∠(− γ ij ) − U i ⋅ U j ⋅ Yij ∠(δ ij − γ ij )
14444442444444 3
[
144444424444443
]
⇔ S ij = U i2 ⋅ g ij − U i ⋅ U j ⋅ Yij ⋅ cos(δ ij − γ ij ) + j − U i2 ⋅ bij − U i ⋅ U j ⋅ Yij ⋅ sin(δ ij − γ ij )
P Q
ij ij
62 Flexible Transmission Grids – Part 1: Fundamentals and Main Challenges of Modern Grids 62
BACKUP
Deriving Power Transfer Equations (2/2)
4 – Extract Pij and Qij components from 3: Ui Uj
Pij = U ⋅ g ij − U i ⋅ U j ⋅ Yij ⋅ cos(δ ij − γ ij )
i
2
Yij
S ij = Pij + jQij ⇒
Qij = −U i ⋅ bij − U i ⋅ U j ⋅ Yij ⋅ sin(δ ij − γ ij )
2
Sij
5 – Recall Some Trigonometric Expressions: Ui = |Ui|∠δi
π
cos α + = − sin(α ) Uj = |Uj|∠δj
2
π Yij = Yij∠γij = gij+jbij
sin α + = cos(α )
2 gij = Rij/(R²ij+X²ij) = Yij·cos(γij)
6 – Recall that, for Transmission Grids: bij = -Xij/(R²ij+ X²ij) = Yij·sin(γij)
g ij ≈ 0 δij = δi - δj
Rij << X ij π
⇒ γ ij ≈ − ⇒ Rij ≈ 0 ⇒ 1
X ij > 0 (Lines are inductive) 2 Yij ≈ bij ≈ −
X ij
ij · I
1 – Transmission Grids:
φ =
ij ·I
j·X
• Rij << Xij ⇒ Rij ≈ 0;
j·X
• Line Active Power Xij·I·cos(φ)
δij Uj R losses ≈ 0; δij Uj
θ i j ·I • Pij ≈ Pj. θ
φ I φ I
3 – From the phasor diagram on the top right and from 2, we obtain:
U i ⋅ sin(δ ij ) = X ij ⋅ I ⋅ cos(ϕ )
Pij Ui ⋅ U j
(ϕ ) =
P ij ⇒ U i ⋅ sin(δ ij ) = X ij ⋅ I ⋅ ⇔ Pij = ⋅ sin(δ ij )
cos U j ⋅ I X ij
U j ⋅ I
64 Flexible Transmission Grids – Part 1: Fundamentals and Main Challenges of Modern Grids 64
BACKUP
Maximum Power Transfer – Uncompensated Line
Ui Uj
1 – Base Equations: Zij
U j = U i ⋅ cos(δ ij ) − Rij ⋅ cos(ϕ ) − X ij ⋅ sin(δ ij )
Ui ⋅ U j
Pij ≈ X ⋅ sin(δ ij ) Ui
ij
ij ·I
j·X
2 – We can obtain the following: Uj R
δij
• Considering mainly resistive load (φ is small) θ i j ·I
φ I
• Considering Rij negligible (≈ 0)
U j ≈ U i ⋅ cos(δ ij ) With considerations given in 2 (on the left)
the upper phase diagram simplifies
Ui ⋅ U j ⇒
( )
to the phase diagram depicted below.
P
ij ≈ ⋅ sin δ ij
X ij Ui
j·Xij·I
U i2 U i2
⇒ Pij ≈ ⋅ sin(δ ij ) ⋅ cos(δ ij ) ⇔ Pij ≈ ⋅ sin(2 ⋅ δ ij )
X ij 2 ⋅ X ij
δij
θ
I Uj
65 Flexible Transmission Grids – Part 1: Fundamentals and Main Challenges of Modern Grids 65
BACKUP
Maximum Power Transfer – Compensated Line
1 – Compensated system: Ui Uj
Zij
U j = U i
U i2
Ui ⋅ U j ⇒ Pij ≈ ⋅ sin(δ ij )
P
ij ≈ ⋅ sin(δ ij ) X ij
X ij
Ui
ij ·I
j·X
δij Uj R
θ ij ·I Uj,Compensated
φ I
66 Flexible Transmission Grids – Part 1: Fundamentals and Main Challenges of Modern Grids 66